RF System to RF Module Interface C Whyte, University of Strathclyde For the MICE RF team 1 MICE RF Module Engineering Review LBNL Center for Beam Physics.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

MICE RF Cavities and RFCC Module Update Derun Li Lawrence Berkeley National Laboratory MICE RF Workshop Daresbury Laboratory, UK April 17, 2012 April 17,
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team MICE Project Board & RLSR, 24th November
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
RF Layout 3pi/2 for Discussion. 2 RF Design mtg 14/1/15 Output line from amplifier is lower than the PRY, needs to go high to clear PRY to couple to South.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Collaboration meeting, DL, 19 h – 23 h October 2008 Andrew Moss ASTeC Collaboration meeting, DL, 19 th – 23 th October 2008 MICE RF distribution system.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
Progress on the MICE RF Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board 14th November 2013.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Linac Marx Modulator Update Trevor Butler 5/20/2015.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
Muon- RF Phase Determination K Ronald, Strathclyde Contributions from many MICE: Tim Stanley, Chris Rogers, Rutherford Lab, Yordan Karadzhov, Geneva, Paul.
1Matthias LiepeAugust 2, 2007 LLRF for the ERL Matthias Liepe.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Anders Sunesson RF Group ESS Accelerator Division
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
14 th ESLS RF Meeting – Trieste, September 2010 ALBA RF Status 1/28 ALBA RF Status Francis Perez.
1Matthias LiepeAugust 2, 2007 Future Options Matthias Liepe.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 30 th April 2014.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
The MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review, 9th September 2015.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 6th April 2016.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
Andrew Moss STFC, ASTeC Example amplifier control system Example of current STFC copper cavity in operation –Using SF6 insulated waveguide –Conditioning.
MICE Demonstration of Ionisation Cooling Colin Whyte University of Strathclyde On behalf of the MICE collaboration 1RF Review 9th-10th Sept. 2015, Abingdon.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
RF Module Integration Colin Whyte University of Strathclyde on behalf of the MICE collaboration 1RF Review 9th & 10th Sept '15 Abingdon.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Linac RF System Design Options Y. Kang RAD/SNS/NScD/ORNL Project – X Collaboration Meeting April , 2011.
The RF Phase Determination for MICE Alexander Dick For the MICE RF Team.
Muon-transit RF Phase Determination K Ronald, University of Strathclyde For the MICE RF group 1MICE Optics Review, 15th January 2016.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Areal RF Station A. Vardanyan
Resource Loaded Schedule and Budget Profile
Status of the MICE RF System
Completion of the MICE-US construction project
MICE RF System Power Supplies, Control and Monitoring Status report
Status of the MICE Construction Project
RF Layout 3pi/2 for Discussion
Injectors BLM system: PS Ring installation at EYETS
Progress on the MICE RF Systems
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
RF operation of REX-ISOLDE
ELEMENTS: Need to install, integrate, commission and operate:
ELEMENTS: Need to install, integrate, commission and operate:
Breakout Session SC3 – Undulator
Presentation transcript:

RF System to RF Module Interface C Whyte, University of Strathclyde For the MICE RF team 1 MICE RF Module Engineering Review LBNL Center for Beam Physics

Content 2 Redesigned distribution network The demonstration experiment has simpler distribution requirements Now makes sense to use ‘over air-gap’ network Replaces STEP V under floor scheme Muon-RF phase determination Initial tests with waveforms from MTA tests Hardware now at Strathclyde for RF tests Status of RF drive system Plans for test, delivery and installation of amplifiers Proposal for a full system test at RAL Requires appropriate EE and RF resources Development of RF Controls & Monitoring systems Development of LLRF Resource Issues MICE RF Module Engineering Review LBNL Center for Beam Physics

MICE High Power RF systems 3 MICE HPRF system requirements have changed Fewer cavities, no coupling coil Required operational date on the beamline is Summer 2017 Requires early commissioning of the hardware: Starting Aug 2016 Enables demonstration of ionisation cooling with re-acceleration First results complete before end US fiscal year 2017 The MICE Demonstration of Ionisation Cooling requires Two cavities bracketed by two thin LiH absorbers, sandwiching main absorber MICE RF Module Engineering Review LBNL Center for Beam Physics

MICE High Power RF systems 4 2MW peak output from RF drive amplifiers, are unchanged LLRF ~10 % overhead to achieve regulation Estimated <10 % loss in transmission line Power delivered to each cavity 1.62 MW, Anticipated gradient in each cavity 10.3 MV/m Slight uplift in gradient from 7.2 MV/m in each ‘STEP V’ cavity MICE RF Module Engineering Review LBNL Center for Beam Physics

Flexible coax Line Trimmers Hybrid Splitter Directional Coupler in each line 4616 Pre Amplifier TH116 Amplifier 500kW Load Directional Coupler 6 inch RF network 5 MICE RF Module Engineering Review LBNL Center for Beam Physics Simplified distribution network- feasible to route overhead Off-centre mounting of hybrid takes up phase shift Orientation of load arbitrary- align with the 6” distribution line and share mountings Minimised length of 4” line- minimises losses

RF network 6 MICE RF Module Engineering Review LBNL Center for Beam Physics 2 nd amplifier moved to 3 rd position behind wall to ease installation in congested area With 2 RF amplifiers now relatively straightforward to place auxiliary systems (cooling) Water cooling for load will need to route over the air gap on the transmission lines Load on each splitter to absorb unbalanced reflections Retracted crane hook clears coax over the wall. Support from present ‘shield wall’ and yoke

RF network 7 MICE RF Module Engineering Review LBNL Center for Beam Physics

Power Distribution Network 8 New experiment will demand higher power (1MW peak, 1kW average) in 4” lines 4” components rated to 1.12MW peak in air at 1 bar A full reflect (during cavity fill or spark) will double line voltage (eq. to 4MW) Mitigate by slow fill Mitigate with insulating gas MICE RF Module Engineering Review LBNL Center for Beam Physics

Power to Cavity Module Interfaces LLRF RF Power Coupler arc detection Vacuum Tuners Controls MICE RF Module Engineering Review LBNL Center for Beam Physics 9

LLRF systems MICE LLRF: provide 1% amplitude, 0.5 o phase regulation, power ramp-up Will control tuner system System is closely related to existing Daresbury accelerators Boards will be tested during the amplifier commissioning programme LLRF system, timeframe and resources Crate build up, A Moss and DL Electronics staff Includes all analogue aspects and hardware Software Development Requires FPGA software: VHDL - XILINX (Spartan) programmer Principle code already exists In use at DL (ALICE) and development at RAL (ISIS) Requires modification RAL (ISIS) currently developing Daresbury code from ALICE for use at 200MHz, similar timescales to MICE. MICE requirement: synergy with ASTeC requirement to recruit Combination LLRF and XILINX is rare, but VHDL software expertise is widely required- but also in demand 10 MICE RF Module Engineering Review LBNL Center for Beam Physics

Timing System, Desired Specification We wish to know the difference between Transit time of any of our muons (in essence through ToF1) A zero crossing of the RF system in any cavity- choose the first cavity Specification for RF timing is ~3x stricter than ToF resolution 50ps MICE RF Module Engineering Review LBNL Center for Beam Physics 11 ToF 1 Cavity 1 RF Amp 1 LLRF Beamline HPRF RF Drive LLRF Feedback TDC’s (ToF) TDC’s (RF) Digitisers Datarecorders RF Clock Trigger Discriminators (RF) Discriminators (ToF) ToF Signals RG MHz LLRF MO MO Signal (RG213) Computers RF Amp 2 HPRF Cavity 2 RF Drive Cavity 2 (RG213) Cavity 1 (RG213)

Comparison of Fourier domain rebuilt signal MICE RF Module Engineering Review LBNL Center for Beam Physics 12 Data from FNAL tests – Processed using subsample Fourier domain reconstruction – Compared to original high data rate recording

RF Power Amplifier No 1 Programme: Timeframes 13 April 2015 Definition of controls and automation system/interfaces/interlocks Draft documents under review Nov 2015 Amplifier no 1 PSU automation system completion Commission and test amplifier No. 2 with No. 1 racks Test automatic/remote control systems Aug 2016 Re-Installation and test into loads at RAL MICE RF Module Engineering Review LBNL Center for Beam Physics

Proposal for Full RF System Tests 14 Justification Tight time schedule for demonstration experiment Require rapid commissioning of whole system Provides opportunity for full shakedown of RF system Delivers pre-prepped cavities by end 2016 Opportunity HPRF Tests, start late August 2016, base est. 8 weeks for first cavity As soon as amplifier no. 1 is available Need to build discrete control racks for each system Change from single integrated control system Feasible given sufficient EE Resource through 2015 & 16 Requires LLRF control Requires UK/US RF experts Second cavity commissioned partially in parallel, ready for test as soon as 1 st cavity completed Test of second cavity (shorter timeframe) Subsequent test of Amplifier 2 with cavity 2 MICE RF Module Engineering Review LBNL Center for Beam Physics

RF System Controls 15 Plans drafted (in review) for the controls and monitoring interfaces required for the RF system and interfacing to other vital subsystems Will allow expedited build of remote control system and data logging system as soon as effort is available Needs of each cavity and RF system have been analysed The system will include a range of analogue monitoring inputs, (both slow and fast ~MHz rate) digital inputs (binary, 3 state, 8 state) analogue control inputs analogue outputs Large number of individual variables Reviewing which need individual interfaces MICE RF Module Engineering Review LBNL Center for Beam Physics

Cavity Module Interlocks parameterEnable – digital output Digital Input Setpoint analog Readback analog value Light sensor 1 (at RF coupler RHS – Quick RF and HT trip on detection of light. Expert Operator to be able to choose between trips of RF, HT, or both yes no Threshold to be user- settable, by RF Expert Operator, for conditioning. Light sensor 2 (at RF coupler LHS – Quick RF and HT trip on detection of light. Expert Operator to be able to choose between trips of RF, HT, or both yes no Threshold, to be user- settable by RF Expert Operator, for conditioning. “Vacuum Good” signal from vacuum system noyesno Interlock and RF quick- trip if “Vacuum Bad” Further Channels? MICE RF Module Engineering Review LBNL Center for Beam Physics 16

RF Control System RF systems will require remote, automated control system ‘State Machine’ description Headline list of primary states and conditions below 17 MICE RF Module Engineering Review LBNL Center for Beam Physics OFF No conditions ENABLED Hardware keys inserted STANDBY Heaters Nominal Hardware keys RF load coolant RF tube coolant Compressed Air PSU coolant READY PPS RF Permit HT enclosures shut Heaters Nominal Cavity and Vessel pressure Nominal Cavity coolant Nominal Cavity tuner pressures SF 6 pressure Hardware keys RF load coolant RF tube coolant Compressed Air PSU coolant ON Nominal RF waveforms Radiation & Arc sensors PPS RF Permit HT enclosures shut Heaters Nominal Cavity and Vessel pressure Nominal Cavity coolant Nominal Cavity tuner pressures SF 6 pressure Hardware keys RF load coolant RF tube coolant Compressed Air PSU coolant

Sequence for operating amplifiers: 4616 Tetrode pre-amp116 triode output stage Air Water Filament timed Grid 1 on to 200vcathode bias on HT oncathode modulator on Screen pulse on4616 RF on at 10kW 4616 RF on116 HT on MICE RF Module Engineering Review LBNL Center for Beam Physics 18

MICE RF Module Engineering Review LBNL Center for Beam Physics 19 General or Common Instrumentation:

Summary 20 MICE RF Module Engineering Review LBNL Center for Beam Physics Substantial redesign of distribution network Mitigates installation conflicts (both schedule and potential physical) Eliminates most of the 4” line Fourier domain reconstruction progressing with REAL pick off data from MTA Some variation in time offset to understand Proposal for full system tests in mid-late 2016 Will debug system ahead of operation in summer 2017 Control/Automation requirements drafted & under review Needed to expedite control rack construction. 1 st pass list of control parameters generated Remote control essential for 2016 full system tests LLRF software staffing issue has emerged Key software expertise has left Daresbury (hardware expertise in place) Require to address urgently as required to allow system test in late 2016 Exploring solutions to problem including link to ISIS programme

Additional Slides 21 MICE RF Module Engineering Review LBNL Center for Beam Physics

RF network: STEP V/VI 22 MICE RF Module Engineering Review LBNL Center for Beam Physics 4 off 6 inch coax lines over wall Pressurised to increase power handling Manually adjustable line trimmers installed at cavity to take up assembly errors in coax length Flexible coax final feeds Allows for small misalignments 10 hybrid splitters Split power for the opposed couplers of each cavity Lines pressurised with 2Bar Nitrogen Amplifiers behind Shield Wall Distribution Network to MICE

Preparation Programme: Timeframes 23 Cavity No 1 programme: May 2016: Module delivered assembled, baked, LLRF tested from LBNL Re-test tuning, exercising of the tuners Acceptance Criteria Require RF specialists: UK + US Prepare for evacuation: pump, gauge installation: Vacuum engineer and mechanical technicians Prepare cavity diagnostic systems, control systems, cooling, RF Engineering, Controls and Monitoring, Mechanical Technicians 4 weeks Install in upstream space against shield wall (parallel to Up Stream Solenoid)- See R. Preece talk May require installing X-ray shield (est ~80 microSv/hr at 3m) 2 weeks, mostly mechanical effort, plus Engineering/Health Physics for design Evacuation, estimate 2 weeks (RF and Vacuum Engineering) Install, tune overhead RF lines, 2 weeks concurrent with evacuation (RF, Mech. Technicians) Retest of cavity tune after evacuation, 1 week Potential to be ready around July 2016 MICE RF Module Engineering Review LBNL Center for Beam Physics

RF System Controls 24 Plans drafted (in discussion and review) for the controls and monitoring interfaces required for the RF system and interfacing to other vital subsystems Will allow expedited build of remote control system and data logging system as soon as effort is available Each Cavity: 17 analogue inputs, 1 analogue output, 4 digital inputs (2 logic states) Each RF system: 24 digital inputs (2 logic states), 4 digital inputs (3 states), 1 digital input (8+ logic states), 22 analogue signal inputs (13 are high, ~MHz, speed), 3 analogue control inputs Some of these may be logically ‘AND-ed’ outside the control logic MICE RF Module Engineering Review LBNL Center for Beam Physics

Timing System, Detailed Specification We wish to know the difference between Transit time of any of our muons (in essence through ToF1) A zero crossing of the RF system in any cavity- choose the first cavity Use tracker measurement of trajectories to project forward to each cavity in turn LLRF phase (0.5 o ) stability specification is ~3x stricter than the resolution desired for the RF timing system <20ps or <0.4% of the RF cycle In turn specification for RF timing is ~3x stricter than ToF resolution 50ps ~1% Should mean the timing accuracy is ~1% of RF cycle, defined by ToFs resolution Stability, and/or accurate knowledge, of all parameters in the system will be important Long cable runs, with dielectric insulated coaxial lines? Phase relationship between the cavity fields and the signals on the test ports Relationship between ToF signals and actual Muon transit MICE RF Module Engineering Review LBNL Center for Beam Physics 25

Overview of Timing Critical Elements Sketch illustrates relationships of key components in the Demonstration experiment Work in progress: Mathematical tests of digitiser interpolation Test of signal reconstruction with lab generated and MTA cavity waveforms Test sensitivity to vertical resolution, temporal sample rate, noise, bandwidth Work to be undertaken: Test TDC/Discriminators in MHz environment ToF 1 Cavity 1 RF Amp 1 LLRF Beamline HPRF RF Drive LLRF Feedback TDC’s (ToF) TDC’s (RF) Digitisers Datarecorders RF Clock Trigger Discriminators (RF) Discriminators (ToF) ToF Signals RG MHz LLRF MO MO Signal (RG213) Computers RF Amp 2 HPRF Cavity 2 RF Drive Cavity 2 (RG213) Cavity 1 (RG213) MICE RF Module Engineering Review LBNL Center for Beam Physics 26

‘Sub’ Nyquist digitisation To acquire at Nyquist on 200 MHz would demand a sampling rate of ~1-2 G.Sa/sec, for 1ms – Demands ~1 to 2 MB per acquired channel, > 7.2 GB/hr (assuming an 8 bit digitiser) – 400  s window presently being acquired at MTA- requires minutes to record traces Fourier domain signal reconstruction – The Fourier transform of the undersampled data maps the signal into its ‘unaliased’, relatively low frequency range We may then retransform to the time domain to determine the time evolution of the signal at some arbitrary point in time Must satisfy Nyquist on the linewidth- for our cavity natural linewidth is ~5 kHz, effective linewidth is ~10 kHz, so sampling rate ~few hundred k.Sa/sec should be sufficient We assume 20 M.Sa/sec, with 1ms we now have about 20 kB per 8 bit recorded channel, data rate of ~72 MB/hr per channel MICE RF Module Engineering Review LBNL Center for Beam Physics 27

Timing hardware and Tests Use TDC and discriminators used in ToF system TDC’s CAEN V ps multi-hit 25ps bin size maps to 7ps uncertainty (assuming Uniform PDF) LeCroy 4415A discriminators Need to be tested in RF environment (alternatives available) Use of same electronics as ToF mitigates systematic uncertainty & drift TDC hardware, discriminators and crates now assembled at Strathclyde. RF connection boards being fabricated to allow tests at RF frequencies To make efficient integration into DAQ ideally use VME digitisers for the sub- sample reconstruction At present continue to use fast, 8 bit, DSO’s to capture signal Plan to use CAEN V1761 digitisers 1GHz, 4G.Sa/sec, 10 bit, 2 Channel instrument Capable of 57.6MS/Ch 28 MICE RF Module Engineering Review LBNL Center for Beam Physics

Cavity No 1 Programme: Timeframes 29 May 2016: Module delivered assembled, baked, LLRF tested from LBNL Re-test tuning Exercise Tuners Acceptance Criteria Prepare for evacuation: pump, gauge installation: Prepare cavity diagnostic systems, control systems, cooling, 4 weeks Install in upstream space against shield wall (parallel to upstream solenoid)- See R. Preece talk May require install X-ray shield (est ~80 microSv/hr at 3m) 2 weeks Evacuation, 2 weeks Install & tune overhead RF lines, 2 weeks concurrent with evacuation Retest of cavity tune after evacuation, 1 week Can complete around July 2016 MICE RF Module Engineering Review LBNL Center for Beam Physics