Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005.

Slides:



Advertisements
Similar presentations
Additional CREs to address Stability Limits Beth Garza TAC June 26, 2008.
Advertisements

RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
Regional Planning Group Charter Revisions May 2008.
Regional Planning Group Project
Singleton Project New 8-ine breaker-and-a-half 345-kV station. Increase North-Houston limit by approximately 700 MW. Increase switching flexibility and.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
INTERNATIONAL RIGHT OF WAY ASSOCIATION | MARCH 20, 2015 STAKEHOLDER MANAGEMENT SOLUTIONS.
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
Houston Area Dynamic Reactive Project March 11,
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
July 13, 2012 Transmission Needs Analysis Scenario 1 Update: BAU All Technologies.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Aug 17, 2012 RPG Meeting KEC & MEC – Load Addition Project – ERCOT Independent Review Ehsan Ur Rehman Planning Engineer ERCOT.
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
Advanced Meter Settlement Background and NPRR. Overview PUC Rule (wholesale settlement) Project – Wholesale Settlement Project Filed Deployment.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Kurten Switch Project ERCOT Board of Directors Bill Bojorquez System Planning December 13, 2005.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
PRR 547 – Trading Hubs CMWG Presentation to WMS October 21, 2004.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
1 TAC Report to the ERCOT Board February 21, 2006.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
Air Conditioner Efficiency. Air Conditioner Problem Suppose an older home in San Antonio is equipped with a central air-conditioning unit with SEER rating.
January 29, 2015 Technical Advisory Committee (TAC) Update to RMS Kathy Scott February 3, 2015 TAC Update to RMS 1.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
ERCOT Independent Review
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
May 8, 2008 Technical Advisory Committee CenterPoint Energy Rothwood Substation Project Jay Teixeira Manager, Regional Planning.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
PJM© Market Efficiency RTEP Proposal Window PJM TEAC 1/9/2014 – Market Efficiency Presentation.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
Houston Import Project – ERCOT Independent Review
RELIABILITY AND OPERATIONS SUBCOMMITTEE Report to TAC Austin, TX December 1, 2011 Kenneth A. Donohoo, P.E. Chairperson Oncor Electric Delivery Company.
Houston Import Study Update
Freeport Area Master Plan Project
Freeport Area Master Plan Project -
Nacogdoches to Lufkin SS 345 kV Line Project
ONCOR Electric Delivery/ Texas New Mexico Power East Bell County to TNP One 345 kV Line Upgrade Projects Board of Directors July 17, 2007.
Description of Project
Status Update for Reliability/Market Power Mitigation Assessment
TAC Report to the ERCOT Board
Warren Lasher Manager, Long-Term Planning and Policy
Modifications to Planning Charter
Status Update for Reliability/Market Power Mitigation Assessment
Presentation transcript:

Houston Area Constraint Mitigation Project ERCOT Board of Directors March 15, 2005

1.Upgrade Jewett-Tomball/TH Wharton 345kV double circuit ($9.5M) 2.Construct new Hillje 345kV switching station in the STP-Holman 345kV line ($10.8M) 3.Build new Parish –Hillje 345kV double circuit ($79.25M) 4.Add STP-Hillje 345kV circuit on open position of existing STP-Parish line ($8.35M) 5.Replace autotransformers at Greens Bayou, Tomball, Addicks and O’Brien ($12.2M) 6.Replace miscellaneous breakers, terminal equipment, and 138 kV conductors ($1.86M) Description of Project

Jewett-Tomball/TH Wharton upgrade and autotransformer change outs scheduled in-service in 2007 Remainder of package scheduled in-service in 2008 Total cost of package of projects is $122 million (or approximately $20 million annual carrying cost) Projected production cost savings (in nominal $millions): Annual savings of ~$63M significantly exceeds the $20M annual carrying cost of the project * Cost and Savings of Project

1.Centerpoint evaluated 28 different packages of projects 2.ERCOT performed an economic evaluation of over 90 different combinations of these projects 3.Sensitivities to the economic savings on the final recommendation: Retirement of TX Genco units Lower natural gas price forecast Options Considered The Hilje option 27 increases the transfer capability into Houston while improving system reliability, operation flexibility and market efficiency

The Stakeholder review period for this project began in September Comments supporting the initial package of projects were received from: TXU Energy Austin Energy Direct Energy STEC – supported, however, did not believe STEC portion of package was required A second comment period was held in January 2005 following the economic analysis performed by ERCOT. Comments supporting the results were received from: CenterPoint Energy Reliant Energy TXU Energy City Public Service of San Antonio Austin Energy Constellation AEP Stakeholder comments at all stages of the review have been in support of the project, with no dissenting comments TAC endorsed the recommendation on March 3, 2005 Stakeholder Review

ERCOT staff recommends that the Board endorse the need for the Houston Area Constraint Mitigation Project as described in the ERCOT report to the Board. Recommendation