2012-2013 Shutdown Update Switchyard - Neutrino Muon MTest - MCenter Michael Geelhoed 2/22/13.

Slides:



Advertisements
Similar presentations
Red: Berm PipeYellow: G2 Vac pump St.Blue: G2 EnclosureGreen: Bermpipe Flange Vacuum Issue Feb 1stMarch 1stApril 1stMay 1stJune 1st Michael Geelhoed 2/20/12.
Advertisements

Pipes Single Wall Pipes Double Wall Pipes
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
NuMI Radiation and Environmental Protection NBI th International workshop on Neutrino Beams and Instrumentation September 5-9, 2006 Mike Martens.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
F ERMILAB T EST B EAM F ACILITY Aria Soha March 17, 2011.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Christopher Nantista ML-SCRF Technology Meeting July 28, 2010 REPORT.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
F ERMILAB T EST B EAM F ACILITY Aria Soha All Experimenter’s Meeting December 15, 2014.
F ERMILAB T EST B EAM F ACILITY Aria Soha All Experimenter’s Meeting October 20, 2014.
F ERMILAB T EST B EAM F ACILITY Aria Soha All Experimenter’s Meeting January 26, 2015.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
1 RUN 2008 OPERA events: Status Report M. Ieva on behalf of Bari Emulsion Lab OPERA Collaboration Meeting, April 1st - 5th, 2009.
MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Maciej Ostręga Michal Zimny IBL CO 2 cooling progress meeting
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
D. Gasser ST/CV 1 Fluid distribution from UW85 Fully available now.
F ERMILAB T EST B EAM F ACILITY Aria Soha March 22, 2011.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Decay Solenoid – what do we have to do to make it work?
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
High Rate Tracking Test Beam Area David Christian & Richard Coleman.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
F ERMILAB T EST B EAM F ACILITY Aria Soha June 12, 2012.
All Experimenters’ Meeting September 23, Accelerator Operation Summary Calendar Week # 38 NuMI Weekly Integrated Intensity 4.57 E18 protons BNB.
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
All Experimenters’ Meeting November 25, 2013 Photo by Martin Murphy.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
Fermilab Test Beam and Irradiation Facilities Erik Ramberg 10 January, 2013.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
FESS - OPS SHUTDOWN UPDATE. ELECTRICAL Feeder 46A Cable tie in - COMP. A0,C0, E0 CRYO Transformers & Switchgear - Not Complete Master Substation - COMP.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
RAMI Paul Aden. RAMI Analysis Reliability Visual inspection during each shutdown Service schedule for necessary components Majority of components to have.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Minerva Test Beam 2 Status Geoff Savage for the Test Beam 2 Team March 23, /23/2015AEM - Minerva Test Beam 2 Status1.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
David BAILLEUX On behalf of the Caltech group Issues for the Laser Monitoring System M&O - US CMS ECAL IB meeting 19 March Chilled water supply.
S A Griffiths CM42 June 2015 Electrical & Control.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
He Plant, LN2 Systems and Commissioing
1.3-GHz Cavity Vacuum Furnace at IB4
SPS cryogenic proximity equipment and SM18 validation
WP 3 coordination meeting Saclay May 2008
Teleconference ACS – FREIA 20th February 2018
NEW COMPLIANCE REGULATIONS
Cryomodule Assembly Plan
(WBS ) Alan Wootton, LLNL April 24, 2002
Upgraded Injector Test Facility
CRYOMODULE FINAL ASSEMBLY
Presentation transcript:

Shutdown Update Switchyard - Neutrino Muon MTest - MCenter Michael Geelhoed 2/22/13

Switchyard Vacuum Pump Control Box Power Supply Issue Vendor sending conversion kits 208 was wired Made connections and installed TC gauges Michael Geelhoed 2/22/13

MTest and MCenter Bore scoped bermpipe between MC3 and MC4 Installed 1397 Welch pump Michael Geelhoed 2/22/13

MTest and MCenter Achieved 1.53E-1 Torr and improving Attempting to install new Rougher pump at M05 Michael Geelhoed 2/22/13

Neutrino Muon Michael Geelhoed 2/22/13 G2 Box SWIC Referenced by AMG Instrumentation reassembling G2 Enclosure Down stream beamline align as founds V424 needed “large” adjustments Break vacuum connections with MSD

Neutrino Muon Michael Geelhoed 2/22/13 G2 NM1 Berm Pipe 2300 Wednesday – Noticed Vacuum readings poor 2330 Wednesday – Ops investigated noticed nothing different 0730 Thursday – Water Collection bucket 2.5 gallons 0900 Thursday – Confirmed pooling water at the G-port 1000 Thursday – Dispensed dye packs around G-port 1030 Thursday – No visual change in water output color 1130 Thursday – Dispensed fragrance tracker around G-port 1300 Thursday – No aroma detected in G Thursday – Vented Berm pipe 1400 Thursday – Visually inspected G port for dye tracks Currently we have a problem and our investigation continues

Neutrino Muon Michael Geelhoed 2/22/13 Currently we have a problem and our investigation continues

Michael Geelhoed 2/22/13 Remaining Enclosure Tasks  Vacuum Stations (MSD and EE Support)  208  NM2 (Waiting to hear back from Vendor)  NM3 (Waiting to hear back from Vendor)  Box SWIC in DS G2 (Instrumentation, MSD and AMG)  Electrical connections for magnets in G2 and NM1  G1 Stub Upstream Isolator washer change-out (delivery eta 2/18)  NM2 Torlon Spacer and pipe stand  Final Alignment of Enclosures  G2  NM1  NM2  NM3 (ready)  General clean-up of enclosures  C and upstream to F sector  G2  NM1  NM2  NM3 SY & Neutrino Muon

Next Week Continue to investigate Berm pipe problem Awaiting conversion kits for 3 pump stations Instrumentation is reassembling the Box SWIC Pumping down MCenter beamline from MC3 to MC4 Michael Geelhoed 2/22/13