Muon works in the next months. MDT Up to May 15 Commissioning of EE From May 15 for (at least) 2 moths DCS works – Installation of new hardware – New.

Slides:



Advertisements
Similar presentations
CSC upgrade for LS1 USA-15 rack: layout, construction and installation 11 th February 2013.
Advertisements

Large Wheel Installation Helped with initial installation in 2005 Installed EML and EMS chambers in sector frame. Last chamber installed 31 October 2006.
Problems with UPS racks last week... During the DSS tests on the weekend Jun 1-2 all racks connected to „interruptable“ UPS were cut by DSS at some point.
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
1 Raw Event : ByteStream implementation Muon Workshop, April 2002 A. Nisati, for the Muon Trigger group.
BOE/BME – MDT: DCS For the 2 BOE, DCS needs to handle 2 x 2 HV (1 ch/multilayer) 2x LV 2x JTAG, associated 2 MDMs/ELMBs Monitoring of T, B and CSM sensors.
ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1.
ATLAS muon endcap 1 layer of tracking chambers (MDT) 3 layers of trigger chambers (TGC) which we are working on ATLAS TGC installation and commissioning.
DCS Plans and Pending Activities for 2013/14 Shutdown Muons in general Replacement/upgrade of DCS computers OS migration to Win-7, Win-2008 or SL6 PVSS.
November 18, 2008 John Haggerty 1 PHENIX In Run 9 John Haggerty Brookhaven National Laboratory.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
14/6/2000 End Cap Muon Trigger Review at CERN 1 Muon Track Trigger Processing on Slave and Hi-pT Boards C.Fukunaga/Tokyo Metropolitan University TGC electronics.
Anatoli Romaniouk, TRT IB meeting October 30 th 2013 TRT meetings Quite many constrains! 1.
1 ATLAS Readiness for Run 2 C. Gemme (INFN Genova) ATLAS Collaboration CSN1 – venerdi’ 17 Aprile 2015.
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
June 17, 2004 / Collab Meeting Strategy to reduce uncertainty on a  to < 0.25 ppm David Hertzog University of Illinois at Urbana-Champaign n Present data.
October 3, 2008 John Haggerty 1 PHENIX Plan for Run 9 John Haggerty Brookhaven National Laboratory.
The Status of the ATLAS Experiment Dr Alan Watson University of Birmingham on behalf of the ATLAS Collaboration.
SG 27/1/2014. Muon week format MondayTuesdayWednesdayThursdayFriday MorningSoftware Smaller upgrades / Pashe 2 PerformanceNSWPlenary Afternoon LS1 and.
Сессия Ученого Совета ОФВЭ 27 декабря 2006 Проект CMS в 2006 Ю.М.Иванов В.В.Сулимов.
Luca Spogli Università Roma Tre & INFN Roma Tre
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
The 1st Result of Global Commissioning of the ATALS Endcap Muon Trigger System in ATLAS Cavern Takuya SUGIMOTO (Nagoya University) On behalf of TGC Group.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
Zhen YAN, Muon Offline DQ meeting, 05/10/2015 Signed off runs(express stream) since last Friday meeting Default defects:  MS_RPC_BA_ROD_PROBLEM_1  MS_RPC_BC_ROD_PROBLEM_1.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI New recuperation system for n-Pentane:  Installation of the module in parallel of the first.
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Project Office Activities R. Vuillermet 08/09/2015R. Vuillermet PH-ADO-PO1.
THE H8 TEST STAND Conceptual Design Mechanical supports Status of preparation Project schedule 1 (Brandeis, CERN, MPI, Seattle - presented by Sandro Palestini)
February 26 th 2013Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
ATLAS The ConditionDB is accessed by the offline reconstruction framework (ATHENA). COOLCOnditions Objects for LHC The interface is provided by COOL (COnditions.
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
Real data in the Muon Spectrometer Bernardo RESENDE and a lot of other people not named here NIKHEF Jamboree, December 2008.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 3, 2013.
EPS HEP 2007 Manchester -- Thilo Pauly July The ATLAS Level-1 Trigger Overview and Status Report including Cosmic-Ray Commissioning Thilo.
Savannah to Jira Migration
The Barrel Level-1 Muon Trigger: Status and perspective for run-2
P. Paolucci G. Pugliese M.Tytgat
eTOF - status and plan CBM-STAR joint Workshop Outline Introduction
Zhe Yang Michigan REU Program Symposium August 9, 2017
LKr status R. Fantechi.
Gas system Commissioning procedures and status
Introduction Status before the 2009 run Results from the 2009 run
ATLAS MDT HV – LV Detector Control System (DCS)
G.Alexeev for Dubna group ITEP, April 28, Muon System Status Report from Dubna.
Technical Support Activities in EP-ADO-PO
RPC Barrel HV & LV system Lappeenranta University
UCLA Meeting: Notes TMB upgrade for ME1/1 issues
Japan Participation in Phase-II TDAQ Upgrade
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Integration issues Denis Diyakov, Alexander Seletskiy,
EMU Slice Test Run Plan a working document.
for the transition region on behalf of the RPC upgrade group
Commissioning of the MUON Spectrometers in ATLAS and CMS
Why Micromegas? Muon Upgrade Workshop, 27/01/2012 Jörg Wotschack.
GEM Leakage Current Testing: CMS Perspective
Technical Support Activities in PH-ADO-PO
ATLAS Muon Spectrometer and
ATLAS USA15 - Rack 52U with 9U crates, remote PS
B904 Status Report by Fred B.
Bringing the ATLAS Muon Spectrometer to Life with Cosmic Rays
RPC Readiness for installation
АВЛИГАТАЙ ТЭМЦЭХ ҮНДЭСНИЙ ХӨТӨЛБӨР /танилцуулга/
Pierluigi Paolucci & Giovanni Polese
Plans for the 2004 CSC Beam Test
Presentation transcript:

Muon works in the next months

MDT Up to May 15 Commissioning of EE From May 15 for (at least) 2 moths DCS works – Installation of new hardware – New operating systems etc. During Summer: Calibration of Power supplies Some gas fixes on EOS (in parallel of other works) At the end of the shut down, when the Big wheels will be in running position: Gas fixes for the EOL (Pallazzani required) Installation of BOE (also RPC) in the fall 2013 De-installation of sMDT from small wheel A Need access (scaffolding?) to reach rim of both Small Wheels for alignment works – For the SWC proposed to do this operation in the fall when the Wheel will be in the trench. Installation of alignment frames in the sectors 12 and 14 between BMFs Installation of new RODS in USA15 to double the read out for the Small Wheel. Summer 2014 Installation of BME chambers. Replace of Fans for all the VME PS.

TGC TGC Sector logic upgrade Fixing the ROD Busy issue (in parallel with Sector Logic work) – Need access to central resources and DAQ. Change of Fan Trays on the wheels Change of TGC chambers – On TGC1 chambers ready in the fall – For TGC3 need to have the wheels in running position Installation of new NIM modules on the MiniRacks (?) Replacement of Fans on VME PS

RPC To be defined after weekly meeting

CSC Repair of 2 CSC stations on SWC Deployment and commissioning of the CSC new ROD

Alignment See slides of Christoph

DCS See slides of Stephanie