Ralph Assmann Performance of LHC Collimation R. Assmann, CERN 13/09/2010 ColMat Meeting, GSI … for the LHC Collimation Project CERN and EuCARD/ColMat Collaboration.

Slides:



Advertisements
Similar presentations
Collimation with retracted TCSGs R. Bruce, R. Kwee, S. Redaelli.
Advertisements

DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Critical beam losses during Commissioning & Initial Operation Guillaume Robert-Demolaize (CERN and Univ. Joseph Fourier, Grenoble) with R. Assmann, S.
Collimation MDs LHC Study Working Group Daniel Wollmann for the Collimation-Team, BLM-Team, Impedance-Team, … LHC Study Working Group,
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
External Review on LHC Machine Protection, CERN, Collimation of encountered losses D. Wollmann, R.W. Assmann, F. Burkart, R. Bruce, M. Cauchi,
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
Ralph Assmann What Do We Want To Measure (in 2009) R. Assmann S. Redaelli, V. Previtali CERN/BE discussed with W. Scandale CERN/EN26/3/2009CC09  See also.
Concept of a Collimation System with Enhanced Operational Stability and Performance.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
CERN Phase II Collimation Conceptual Review Summary 09 April 2009 LARP CM12 Napa, CA Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
Improving Collimator Setup Efficiency LHC Beam Operation Committee, G. Valentino, R.W. Assmann, R. Bruce, F. Burkart, M. Cauchi, D. Deboy, S.
Case study: Energy deposition in superconducting magnets in IR7 AMT Workshop A.Ferrari, M.Magistris, M.Santana, V.Vlachoudis CERN Fri 4/3/2005.
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
R. Assmann, June 2009 Operational Experience with the LHC Collimation System R. Assmann, CERN 8/6/2009 for the Collimation Project Team Visit TU Munich.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
NM4SixTrack Implementation of new composite materials for HL-LHC collimator upgrades in SixTrack “Tracking for SixTrack” workshop – CERN, R.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
Collimation design considerations at CERN (with some applications to LHC) R. Bruce on behalf of the CERN LHC collimation project R. Bruce,
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Ralph Assmann 1
LHC Collimation Working Group Monday, 21 March 2016 Analysis of collimator BPMs in the 2015 run A.Valloni, G. Valentino with input from R. Bruce, A. Mereghetti,
How low can we go? Getting below β*=3.5m R. Bruce, R.W. Assmann Acknowledgment: T. Baer, W. Bartmann, C. Bracco, S. Fartoukh, M. Giovannozzi, B. Goddard,W.
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Tracking simulations of protons quench test
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Joint Meeting SPS Upgrade Study Group and SPS Task Force
Halo scraping and loss rates at collimators
Status of LHC Operations
Beam collimation for SPPC
Intensity Evolution Estimate for LHC
LHC Morning Meeting - G. Arduini
Tuesday TOTEM and transverse loss map (1) OK
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
CERN, Geneva, Switzerland PAC 2003 – Portland, Oregon, USA
LHC Injection and Dump Protection
The 4th International Particle Accelerator Conference, IPAC13
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
LHC Collimation Requirements
Optic design and performance evaluation for SPPC collimation systems
Beam halo and beam losses in IR1 and IR5
Yesterday morning Held 1647 for a while – SPS kicker problem
Why do BLMs need to know the Quench Levels?
Collimation after LS1: cleaning and β* reach
Saturday 7th May Sat – Sun night
Collimation margins and *
Summary Thursday h21: Stable beams fill #1303.
Collimators: Operations - Baseline Assumptions
Improving Collimator Setup Efficiency
Collimator Efficiency Study
Collimation qualification during the first weeks of the 2011 run
MD Planning Fri – Sat (1. – 2.7.)
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Operational Results of LHC Collimator Alignment using Machine Learning
Presentation transcript:

Ralph Assmann Performance of LHC Collimation R. Assmann, CERN 13/09/2010 ColMat Meeting, GSI … for the LHC Collimation Project CERN and EuCARD/ColMat Collaboration

LHC Collimation System The LHC collimation system is the most elaborate collimation system built for any accelerator: 88 movable collimators with two jaws, absorbers, 2 warm cleaning insertions, experimental collimation, radiation handling, material robustness, … Involves a necessary complex control of ~400 DOF with several settings through the LHC operational cycle. It is studied and optimized since 2001 in the beam cleaning / collimation WG and the LHC collimation project. The previous talks explained its functioning and the results obtained with beam in detail. The system is designed as a cleaning system (determines location of collimators) but also offers passive protection (not ideal phase coverage). Here focus on MP issues of this complex system… Ralph Assmann 2

… celebration after 6.5 years of hard work in BE, EN, TE, RP, … 2009

less than 1%new territorysurvive At less than 1% of nominal intensity LHC enters new territory. Collimators must survive expected beam loss… Comparing stored beam energy 3 × protons7 TeV/c Nominal LHC design:3 × protons accelerated to 7 TeV/c circulating at 11 kHz in a SC ring Stored Energy

The LHC Collimator (Phase 1 MainDesign) R. Assmann, CERN MJ proton beam 1.2 m 3 mm beam passage with RF contacts for guiding image currents Designed for maximum robustness: Advanced CC jaws with water cooling! Mostly with different jaw materials. Some very different with 2 beams! Other types: Mostly with different jaw materials. Some very different with 2 beams!

Precision Requirements closest to beam: primary (TCP) and secondary (TCS) collimators R. Assmann, PAC 5/09 ParameterUnitSpecification Jaw materialCFC Jaw length TCS TCP cm Jaw taperingcm Jaw cross sectionmm 2 65 × 25 Jaw resistivityμΩm≤ 10 Surface roughnessμm≤ 1.6 Jaw flatness errorμm≤ 40 Heat loadkW≤ 7 Jaw temperature°C≤ 50 Bake-out temp.°C250 Minimal gapmm≤ 0.5 Maximal gapmm≥ 58 Jaw position controlμm≤ 10 Jaw angle controlμrad≤ 15 Reproducibilityμm≤ Specification Gaps: ± 6/7  2-3 mm LHC collimators must work as precision devices!

R. Assmann, PAC 5/09 System Design Momentum Cleaning Betatron Cleaning “Phase I” 108 collimators and absorbers in phase I (only movable shown in sketch)

Multi-Stage Cleaning & Protection 3-4 Stages Secondary halo p p e  Primary collimator Core Unavoidable losses Shower Beam propagation Impact parameter ≤ 1  m Primary halo (p) e  Shower p Tertiary halo Secondary collimator High Z coll CFC W/Cu High Z coll Super- conducting magnets SC magnets and particle physics exp. CFC collimator R. Assmann, PAC 5/09

Beam Loss Monitors for Monitoring Losses at Collimators R. Assmann, PAC 5/09 Beam Loss Monitors for Collimation PHASE I COLLIMATOR TCSG Beam Direction

Role of Collimation Correct setup of collimation ensures highly efficient beam cleaning: –Tolerance for allowable LHC beam losses is maximized. –Risk of quenches is minimized. –Operational efficiency and integrated luminosity is maximized. Correct setup of collimation ensures also several safety functions: –Protection of accelerator against fast losses, e.g. erroneous dumps, wrong injection kicks, trips of fast magnets, RF trips, …  losses appear at collimators within given phase space coverage. –Protection of accelerator against long-term losses: radiation at foreseen locations, effectiveness of absorbers, survival of magnets, … –Correct environmental impact with losses at foreseen locations. –Robustness of collimation system against failures: collimators only damaged with multiple errors (e.g. asynchronous dump + dump protection out). Ralph Assmann 10

Collimation Condition Good settings for given machine state! for 2010: setup with relaxed 3.5 TeV tolerances (x 2.8) and limit on  * (> 2.5 m)  intermediate collimator settings! Ralph Assmann 11

Collimation Setting Calculation The collimator settings are calculated to: –Provide good efficiency. –Provide the correct collimator hierarchy (slow primary losses at primary collimators). –Protect the accelerator against the specified design errors. –Provide continuous cleaning and protection during all stages of beam operation: injection, prepare ramp, ramp, squeeze, collision, physics. –Provide maximum tolerances to beam and various collimator families. –Provide warning thresholds on all collimator axis positions versus time. –Provide interlock thresholds on all collimator axis positions versus time. –Provide interlock thresholds on all collimator gaps versus beam energy. Complex problem with some 100,000 numbers to control the system. Redundant calculation: time-dependent (ABP), energy-dependent (OP) Ralph Assmann 12

Required Flexibility The LHC collider is not a static accelerator! As a consequence the collimation system cannot be a static system either! Several settings for various stages with ramp functions in between. Interlock thresholds change as a function of operational stage. Only energy-dependent interlock thresholds remain unchanged. All collimation tasks in operational sequence  operator has to execute the sequence tasks completely and in correct order. Initially some problems (private sequences) but now works reliably. Sequence check tasks process implemented to enforce correct execution. Ralph Assmann 13

Collimation Setting Overview (in terms of  beam size, valid – ) LHC Collimation team 14 Ramp functions move smoothly from set 1 to set 2 during energy ramp! 3.5 TeV setup took ~30 h of beam time with single bunch of 1e11 p. Time distributed over 10 days with ~1 collimation shift per day.

Tobias BaerSeptember, 3 rd Phase Space Coverage: Injection B1 TCP.C6L7.B1 TCP.D6L7.B1 TCLIA.4R2 TCLIB.6R2.B1 TCSG.D4L7.B1 TCSG.B4L7.B1 TCSG.4R6.B1 TCSG.6R7.B1 9σ9σ9σ9σ

Tobias BaerSeptember, 3 rd Phase Space Coverage: 3.5 TeV, β*=3.5 m B2 TCP.C6R7.B 2 TCP.D6R7.B 2 TCSG.D4R7.B 2 TCSG.B4R7. B2 TCSG.6L7. B2 TCSG.A4R7. B2 TCSG.D5L7. B σ

Measuring Tails (10 min end-of-fill) 8:30 meeting17 Jaw towards beam Beam Loss Jaw position TCP.D6R7.B2

Beam Intensity 8:30 meeting e11 p % Beam dumped from beam loss on Q5 in IR7 (warm) with 84 s integration time!

Beam Distribution: Beam 2 Tail V after 13h of Physics 8:30 meeting19  y = 0.27 mm ~ 5.7  ~ 4.7  ~ 3.7  3.5% of beam within 1.5 

Beam 2 H Tail after 3h30 of Physics 8:30 meeting20 Florian Burkart et al

Measured Cleaning at 3.5 TeV (beam1, vertical beam loss, intermediate settings) LPCC, R. Assmann IR8 IR1 IR2 IR5 Momentum Cleaning Dump Protection Col. 2m optics exposes IR’s as expected! Protected by tertiary collimators. 21

Simulated Cleaning at 3.5 TeV (beam1, vertical beam loss, intermediate settings) Ralph Assmann 22 No Imperfections

Measured Cleaning at 3.5 TeV (beam1, vertical beam loss, intermediate settings) LPCC, R. Assmann factor 1,000 factor 4,000 Betatron Cleaning IR8 factor 600, Cleaning efficiency: > %

Simulated Cleaning at 3.5 TeV (beam1, vertical beam loss, intermediate settings) Ralph Assmann 24 factor 33,000 No Imperfections

Meas. & Sim. Cleaning at 3.5 TeV (beam1, vertical beam loss, intermediate settings) LPCC, R. Assmann IR8 25 IR7 Confirms expected limiting losses in SC dispersion suppressor Find factor 8 higher, as explained from imperfections! Confirms expected limiting losses in SC dispersion suppressor Find factor 8 higher, as explained from imperfections!

Betatron Cleaning: Peak Leakage to SC Magnet Ralph Assmann TeV D. Wollmann et al

Betatron Cleaning: Leakage (Sum) to Horizontal TCT’s Ralph Assmann TeV D. Wollmann et al

Betatron Cleaning: Leakage (Sum) to Vertical TCT’s Ralph Assmann TeV D. Wollmann et al

Betatron Cleaning: Leakage to Dump Protection Ralph Assmann TeV D. Wollmann et al

Stability of Betatron Cleaning 3.5 TeV Excellent news! There are some variations by a factor 6. Peak leakage remains very low: –Max to SC magnet: 0.06 % –Max to hor. TCT’s (sum):0.06 % –Max to ver. TCT’s (sum):0.12 % –Max to dump protection:0.52 % No systematic trend at all visible. Biggest possible deterioration:factor 2 for TCT in B1 vertical Ratio from dump protection to hor. TCT’s proves that these tungsten collimators were always in the shadow of the IR6 collimators  SAFE! August experience proves that we can run stable for long periods without violating safety! However, … Ralph Assmann 30

Momentum Cleaning at 3.5 TeV Insufficient data to analyze stability. Still seems to work correctly for the following cases: –Beam 1, positive energy errors –Beam 1, negative energy errors –Beam 2, negative energy errors Found middle of August to not work correctly in: –Beam 2, positive energy errors –Must be 3.6 sigma error in the system (collimator and/or orbit) Consequences: –Should be fixed to avoid unnecessary risks (1 protection layer less). –Might have been there since setup: not checked due to large overhead for momentum cleaning tests. Must avoid these short-cuts. Will be fixed and analyzed at 3.5 TeV. Ralph Assmann 31

Momentum Cleaning, B2, Positive Energy Offset Ralph Assmann 32

Outlook: Upgrades We plan upgrades on present system for 2011 (during christmas break): –Use of squeeze factor for interlocks during squeeze. –More automated setup: faster and less prone to human error (risk of wrong dump during collimator setup with broken hierarchy). Upgrades in 2012 shutdown: –Relocate all losses to IR3 (radiation to electronics) and catch losses in dispersion suppressors (DS collimators). Upgrades in 2016 shutdown: –Full collimation upgrade. –Collimators with in-jaw buttons: non-destructive centering and setup of collimators. 100 times faster setup. Can be done every fill. Precise interlock of orbit – collimator offsets. Tested in SPS successfully. Ralph Assmann 33

Installation of 1 st Phase II Collimator (CERN type, BPM’s in jaws, into SPS for beam tests) R. Assmann, CERN 34 January 8, 2010 EuCARD

Phase 2 LHC Collimator Test with SPS (for 2016 upgrade) Instead of halo-based setup (lengthy, risky, special fill) phase 2 collimators will have in-jaw buttons. Much, much easier then! Setup every fill in 10’s of seconds. SPS results very nice: no clear effect of showers, can track beam center. Ralph Assmann 35 Center while changing gap Jaw-BPM measurement upstream Jaw-BPM measurement downstream (to be understood – calibrated) Here: Close collimation gap while keeping center Plot: D. Wollmann EuCARD

Phase 2 Coll. With SPS Beam Drifts Standard BLM-based Method – Observing Jaw-BPM’s Ralph Assmann 36 Jaw-BPM upstream Jaw-BPM downstream Set gap center Re-do BLM based set-up to follow beam center  Brings also back jaw- BPM’s to previous reading! after 15 min Agreement BLM – jaw BPM: 10 – 20  m level Will solve many LHC issues! Agreement BLM – jaw BPM: 10 – 20  m level Will solve many LHC issues! Plot: D. Wollmann EuCARD

-3 m shifted in s halo Halo Loss Map Upgrade Scenario +3 m shifted in s Downstream of IR7  -cleaning transversely shifted by 3 cm cryo-collimators NEW concept Losses of off-momentum protons from single-diffractive scattering in TCP without new magnets and civil engineering TCRYO

LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Jan 2010 No 1/xx First prototype to be delivered from SLAC to CERN in August Installation into SPS in 2010/11 shutdown. Beam tests in Time to build 5 collimators: 1 year. If decision in 2012 then available in 2013… Rotatable high Z jaw allows for multiple damaging beam hits! US Work on Phase II Design (LARP funded, SLAC linear collider design to LHC) T. Markiewicz

Conclusion LHC collimation works with expected performance level and has shown an amazing stability over the last 2 months. Collimation interlocking has proven very effective, catching even non specified errors (e.g. ramp up of beam energy from 3.5 TeV with beam inside the machine). The achieved orbit tolerances are non-conform, especially in the IR’s. So far no sign of increased losses in the IR’s. So good enough for intermediate collimation settings at 3.5 TeV and  * = 3.5 m. The collimation system should be kept well set up, to be prepared for rare and unlikely accident cases. 2 weeks running does not prove safety. Ralph Assmann 39