Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24
Buildings in site E & control building Administration building Singles room building canteen
Buildings area in site Administration building canteen Single rooms building
Workshop area and internet camera Workshop area Internet camera1 Internet camera2
Tanks 81,82, 83 Tank No.81 Tank No.82 Tank No. 100
GTs area in site
Tanks area in site Tank LDO 071 Tank LDO 072 Tank Treated HFO 061 Tank Treated HFO 062 Tank LDO 073 Tank Treated HFO 063 Tank 051 Treated HFO Tank 052 Treated HFO Tank RAW HFO 042 Tank RAW HFO 041
Internal roads in site Road No.1 Road No.4 Road No.2 Road No.3
Unloading area position in site Unloading area
Tank No. Size of tank m3 Tanks Excavation Ground Compaction Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer % % % % % % % % % % % % % % Tanks foundation works progress – Excavation & sub base layers compaction
Tank No. Size of tank m3 Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer % % % Tanks foundation works progress –sub base layers compaction inside tanks area
Tanks foundation civil activities progress CuringPouring main Found. Wooden Formwork Instal. Rebar works Pouring lean concrete Achievement compaction Total Depth backfilling No. Tank 100% 1.4 m41 100% 1.4 m42 100% 1.6 m51 100% 1.6 m52 100% 1.4 m61 100% 1.4 m62 100% 1.4 m63 100% 1.4 m71 100% 1.4 m72 100% 2.03 m73 100% 1.3 m81 80%100% 1.3 m82 77%1.3 m %1.3 m90
Compaction 1 st layer sub base for inner area of tank 62
Removing wooden formwork for foundation of tank 81
Wooden formwork works for foundation of tank 82
Building Total Depth backfilling Excavation works Compaction 4 layers sub base Casting of Lean concrete Rebar works Pouring concrete 1 st layer 2 nd layer 3 rd layer 4 th layer Administration building 1 m 100% finished 40% Canteen building 1 m 100% finished 40% Singles room building 1 m 100% finished 100% finished Electrical & control building 1 m 100% finished Fire fighting building 1 m 100% finished Buildings foundation progress
Pouring lean concrete layer for foundation of admin building
Q.C test for lean concrete layer of admin building
Pouring lean concrete layer for foundation of canteen building
Q.C test for lean concrete layer of canteen building
Extra excavation for foundation of E&C building
curing Pouring concrete Wooden formwork Rebar works Lean concrete 4 th layer sub base comp. 3rd layer sub base comp. 2nd t layer sub base comp. 1 st layer sub base comp. Sub grade comp. Excavation NO 12%100% GT21 70%100% GT22 35%100% GT23 20%87%100% GT24 Main foundation installation progress of stacks
Rebar works for stack foundation of GT21
Rebar works for stack foundation of GT22
Rebar works for stack foundation of GT23
Rebar works for stack foundation of GT24
Main foundation curing Pouring main foundation Wooden formwork installation Rebar formwork installation Pouring lean concrete 4th layer sub base compaction 3rd layer sub base compaction 2nd layer sub base compaction 1 st layer sub base compaction Subgrade compaction Excavation NO 60%100% GT21 60%100% GT22 60%100% GT23 50%100% GT24 Fin Fan coolers foundation progress
Compaction 4 th layer sub base for fin fan cooler foundation of GT21
Compaction 4 th layer sub base for fin fan cooler foundation of GT22
Compaction 4 th layer sub base for fin fan cooler foundation of GT23
Ground compaction works for roads achievement 100% 1.Road No. 1 achievement 100% 2.Road No. 2 achievement 100% 3.Road No. 3 achievement 100% 4.Road No. 4 achievement 100% 5.Widening roads. 6.Compaction 1 st layer for road No.1
Excavation for foundation of PECC & CO2 for GT21
Excavation for foundation of PECC & CO2 for GT23
Installation boundary fence 1.1 st sub base layer compaction 100% 2.2 nd sub base layer compaction 100% 3.Pouring concrete for blinding level of foundation. 4.Pouring concrete to panels of fence. 5.Extract concrete panels from steel forms.
Boundary fence progress
Installing panels at north side of fence
Installing bases at east side of fence
Installing columns at east side of fence
Mechanical works 1. Stack pre assemble Stack support shaft for GT21 (100%) Stack support shaft for GT24 (100%) Stack support shaft for GT24 - fabricating works for gangways (40%) Stack thermal shield for GT21 (1%) (hold) Application of stack support shaft for GT22 ( 60%) Application of stack support shaft for GT23 (95%) Transition duct GT21 70% Transition duct GT22 50% Transition duct GT23 50% Transition duct GT24 30% Protection duct GT21,GT22,GT23,GT24 (50%)
Stack Pre Assemble remarksProtection duct Transition duct Thermal shield Support shaft Stack no. 50%70%hold100%GT21 50% hold60%GT22 50% hold95%GT23 50%30%hold100%GT24
Welding horizontal joints for stack support shaft of GT23
Welding vertical joints for stack support shaft of GT22
Fabrication works for stack support shaft of GT23
Welding works for stack support shaft of GT23
Fabrication works for stack support shaft of GT22
Q.C test for vertical joints of stack support shaft for GT22
Mech. Daily Progress Report 1-Dec-12 Site:- Haydaria site Mechanical Engineering Department Date: 1-Dec-12 Mech. Daily Progress Report Arrival Time:7:00 AM Departure Time: 5:00 PM Overtime:0Hours TAEngineerForeman MCH. Technicians WELDE R laborsTotal Mech. Manager Signature TA ZEKI AL SAADI
MECHANICAL ACTIVITIES Activities Minister of Electricity Visit Store 1- Inventory of the generator accessories Unit Transport of the exhaust frame parts 2- Installation of the extension duct 3- Preparations to install the Aux. compartment Unit Preparations to install the extension duct Unit Installation of the upper exhaust plenum Unit Preparations to install the extension ducts 2- Installation of the upper exhaust plenum
Minister of Electricity Visit
Store
Inventory of the generator accessories
Unit 21
Transport of the exhaust frame parts
Installation of the extension duct
Preparations to install the Aux. compartment
Unit 22
Preparations to install the extension duct
Unit 23
Installation of the upper exhaust plenum
Unit 24
Preparations to install the extension ducts
Installation of the upper exhaust plenum
Preparation for installing generator of GT21
Preparation of installation aux. comp
Installation aux. comp for GT 24
Installation aux. comp for GT 23
Installation aux. comp for GT 22
Installation aux. comp for GT 21
Grounding grid laying for stack of GT24
Fabrication electrical service boards
Maintenance for sockets & lighting
Preparation to do the Inspection thermo shied
inspection and inventory for EXTENSION EXHAUST for GT23 and GT 21
inspection and inventory for transition duct for GT 24,21
inspection and inventory for Generators parts boxes for GT21,22,23,24