June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.

Slides:



Advertisements
Similar presentations
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
Advertisements

October 21, 2003LST Mechanical Design Review - SLACN. Yu BaBar IFR Upgrades An FEA Study of the Effects of Adding Brass Plates in the IFR.
August 6, 2007Bill Wisniewski1 Collaboration post-operations planning: analysis, computing, manpower (brief). BaBar Detector Rampdown Detector Description.
March 23, 2009Bill Wisniewski1 Disposition flow charts Laying out the onion layers; temporary and longer term storage The measured radiation environment.
Jan 28th, 2009Colin Jessop at Notre Dame An experiment to measure CP violation in B mesons Colin Jessop University of Notre Dame.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2005 IR-2 Installation Discussion H.J. Krebs October 22, 2003.
BaBar: The Detector Richard F Boyce 21 October 2003.
May 5, 2004H.J. Krebs LST Installation Readiness Review 2004 IR-2 Installation Schedule H.J. Krebs May 5, 2004.
March 23, 2009H.J. Krebs1 BaBar D&D Schedule & Budget Overview H. James Krebs March 23, 2009.
March 23, 200Bill Wisniewski1 Intro to BaBar Detector and its subsystems Identify the assets Look at reuse potential Preserve the assets Minimal maintenance.
May 4, 2004Bill Wisniewski1 Installation Review. May 4, 2004Bill Wisniewski2 Charge ( W. Althouse, G. Bowden, W. Innes(chair), J.Weisend, (D. Nelson))
October 22, 2003H.J. Krebs1 LST Mechanical Design Review Mechanical Installation Preparation H. James Krebs October 21, 2003.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003.
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and Fabrication Status H.J. Krebs October 10, 2003.
August 6, 2007Bill Wisniewski1 D&D Task Force: PEPII team: S.DeBarger, S.Ecklund, A.Hill, D.Kharakh, M.Zurawel BaBar team: H.J.Krebs, S.Pierson, W.Wisniewski.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
ORKA Preservation Task Force ORKA Preservation Task Force first meeting Wednesday, February 8, Notes by Peter H. Garbincius Notes from meeting are.
11/15/02H.J. Krebs IFR Improvement Phase II (Barrel) Mechanical Engineering Issues H. James Krebs November 15, 2002.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
July 7, 2008Bill Wisniewski1 Identify the assets Look at reuse potential Preserve the assets Minimal maintenance state Settle ownership Plan & execute.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
The BaBar Upgrade Load transfer of the Barrel and Endcap Calorimeters Richard F Boyce 21 October 2003.
Blair Ratcliff, SLACUS R&D Meeting, Sept. 3, 2008 Blair Ratcliff SLAC Detector R&D: Overview and Opportunities Detector Overview (some old news!). Present.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
SPHENIX MECHANICAL D. Lynch, R. Ruggiero June 12, /12/2014sPHENIX Mechanical Design.
SPHENIX MECHANICAL D. Lynch & R. Ruggiero July 31, /29/2014sPHENIX Mechanical Design.
DON LYNCH DECEMBER 4, AGENDA December 4, BABAR Magnet Update Outer HCal Structural Analysis (Assembly and Support) sPHENIX Project Management.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
BABAR Overview & Ramp-Down Planning David B. MacFarlane Deputy Director, PPA August 6, 2007.
May 31, 2010Bill Wisniewski1 Mechanical Integration Issues.
October 7, 2009H.J. Krebs1 Super B WorkShop Overview of BaBar Detector Assembly/Installation Documentation Jim Krebs.
Integration Prototype1 BaBar Integration as a Prototype for SuperB Bill Wisniewski SuperB Workshop at LNF 6 April 2011.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
Comments on Services Elba Comments on Services & … Bill Wisniewski SLAC.
October 6, 2009Bill Wisniewski1 State of drawings Remedies? Forward Region DIRC/DCH/EMC interplay Road Trip Discussion Beam pipe & forward cone plug ‘Quick’
01 June 2011F. Raffaelli1 Super B Mechanical integration. List of reference persons and institutions for the mechanic of the sub detectors. Review of the.
Miscellaneous MEC Topics Mainz, CM September 2016, MEC Session J
Integration meeting F.Raffaelli
St. George Infrastructure
Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005
BaBar LST Upgrade Mark Convery SLAC 13 Jun 07.
Bill Wisniewski SuperB Frascati Meeting September 30, 2010
LARP Vertical Test Facility
HCAL M&O-B Budget CMS Finance Board
Transport Issues for EMC Barrel
Workshop Goals for the Detector Groups
SiD LoI Costs M. Breidenbach 29 July 2010 M. Breidenbach.
The Compact Muon Solenoid Detector
SoLID Magnet - Engineering and Cost
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
Integration and IR Hall
LST Module Installation
Limited Streamer Tubes
RPC and LST at High Luminosity
Francesco Forti SuperB Workshop LNF, March, 2006
SuperB Integration Summary of previous integration sessions.
Limited Streamer Tube Project Summary
as a prototype for Super c-tau factory
SuperB Integration Summary of the Integration Status
BaBar LST Upgrade Richard F Boyce
Polarized 3He target installation
Presentation transcript:

June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview

June 2, 2008 Bill Wisniewski2 BaBar Detector Cerenkov Detector (DIRC) 144 quartz bars PMTs 1.5 T Solenoid Electromagnetic Calorimeter 6580 CsI(Tl) crystals Drift Chamber 40 stereo layers Instrumented Flux Return iron/RPCs (muon/neutral hadrons) Silicon Vertex Tracker 5 layers, double sided strips e + (3.1 GeV) e - (9 GeV)

June 2, 2008 Bill Wisniewski3 BaBar Detector ‘Ideal’

June 2, 2008 Bill Wisniewski4 BaBar Detector ‘Actual’ Shield wall removed

June 2, 2008 Bill Wisniewski5 BaBar Detector Disassembly BaBar completed the IFR upgrade in Fall This upgrade took place over three campaigns: IFR Forward Endcap Resistive Plate Chambers in 2002, 1 st third of IFR Barrel Limited Streamer Tubes in 2004, balance of IFR Barrel sextants with LSTs in –Barrel upgrade required uncabling of forward end of SVT, forward end of EMC, load transfer of EMC, removal of most of the corner blocks fore and aft, removal of flux bars, releasing some of the cryostat restraints, pulling forward doors to walls. –Experience gained in these campaigns plus experience from the initial detector assembly provide excellent input for planning the detector disassembly process, estimating the required manpower (both labor and engineering), as well as M&S.

June 2, 2008 Bill Wisniewski6 Project Schedule 51 months duration Assumptions –Project start date July 1, 2008 –Dismantling tasks performed sequentially Tooling refurbishment performed in parallel at IR-12 Can be optimized with additional work crews Experienced supervision may not exist for multiple crews –Use of personnel knowledgeable in the disassembly of BaBar –Items hauled away are assumed to be trash Ending location TBD –Metals are stored due to metals moratorium Location TBD

June 2, 2008 Bill Wisniewski7 Concrete Radiation Shield Wall

June 2, 2008 Bill Wisniewski8 IFR Background Shield Wall

June 2, 2008 Bill Wisniewski9 SVT & PEP Support Tube Installation

June 2, 2008 Bill Wisniewski10 Silican Vertex Tracker (SVT)

June 2, 2008 Bill Wisniewski11 Silican Vertex Tracker (SVT) The SVT Detector and the PEP Support Tube are a married assembly –This system was extracted from BaBar in 2002 Removed from the forward end on beamline A detailed project plan exists including schedule and resource estimates Extraction/insertion tooling exists in good working condition

June 2, 2008 Bill Wisniewski12 Drift Chamber

June 2, 2008 Bill Wisniewski13 Drift Chamber Supported by the DIRC Central Support Tube –Removed from the forward end in main disassembly area It is assumed that the Drift Chamber will end up on display at a lab or university If disposed of: –Beryllium inner tube –Gold plated wires Gas system racks Reusable items –Most items considered obsolete Extraction tooling exists – Somewhat scattered –Good condition (stored inside) –Needs to be gathered to one location

June 2, 2008 Bill Wisniewski14 DIRC

June 2, 2008 Bill Wisniewski15 DIRC Central/Strong Support Tube Assembly

June 2, 2008 Bill Wisniewski16

June 2, 2008 Bill Wisniewski17 DIRC Magnetic Shield Cylinder

June 2, 2008 Bill Wisniewski18 DIRC Major detector components –Stand off box with 11,000 phototubes –Quartz Bar Boxes –Central/Strong Support Tube with Horsecollar and Magnet Bucking Coil –DIRC Magnetic Shield All major components removed from backward end in main disassembly area Reusable items –Quartz bars. DIRC support tube. –Magnet Bucking Coil Most extraction equipment exists –Good condition (stored inside)

June 2, 2008 Bill Wisniewski19 Forward Endcap End Cap Calorimeter

June 2, 2008 Bill Wisniewski20 End Cap Calorimeter All major components removed from forward end in main disassembly area –Ship to IR-12 for final disassembly Reusable items –Crystals Stored in humidity control container Some with heavier radiation damage Most extraction equipment exists –Good Condition Items stored inside but somewhat scattered –Some items will need to be replaced

June 2, 2008 Bill Wisniewski21 Barrel Electromagnetic Calorimeter

June 2, 2008 Bill Wisniewski22 Barrel Electromagnetic Calorimeter Removed from forward end in main disassembly area –Ship to IR-12 for final disassembly Reusable items –Crystals in structure Control humidity and temperature Most extraction equipment exists –Condition varies Some items stored inside Large items stored outside –Items are somewhat scattered –Some items will need to be replaced

June 2, 2008 Bill Wisniewski23 BaBar Magnet System

June 2, 2008 Bill Wisniewski24 Magnet Valve Box With Current Leads

June 2, 2008 Bill Wisniewski25 IR-2 Helium Liquefier

June 2, 2008 Bill Wisniewski26 BaBar Magnet System Solenoid is removed from backward side in main assembly area Uses EMC extraction beam assembly with magnet-specific tooling Most extraction equipment exists –Stored outside Needs refurbishment Reusable items –Solenoid and Valve Box –Power Supply plus spare –Helium Liquefier and controls –LN 2 Dewar

June 2, 2008 Bill Wisniewski27 Instrumented Flux Return (LSTs) Barrel

June 2, 2008 Bill Wisniewski28 Instrumented Flux Return Limited Streamer Tubes (LSTs) –Removed from detector on beam line Most extraction equipment exists in good condition Will be stored for possible future application –Storage crates available from LCLS 75 tons of brass absorber plates –Removed from detector on beam line Most extraction equipment exists –Needs refurbishment

June 2, 2008 Bill Wisniewski29 Instrumented Flux Return Backward End Door RPCs

June 2, 2008 Bill Wisniewski30 Instrumented Flux Return (RPCs) End Door

June 2, 2008 Bill Wisniewski31 Instrumented Flux Return (RPCs) Resistive Plate Chambers (RPCs) –Barrel 6 RPCs in Barrel (Layer 19) –Approx 250 lbs each –Must disassemble barrel steel and support structure to remove these chambers –Forward End Doors 16 layers, 3 modules high, both east and west –96 total chambers »Approx. 150 lbs each Removed from detector on beam line RPCs shall be disposed of –Backward End Doors 18 layers, 3 modules high, both east and west –108 total chambers »Approx. 150 lbs each Removed from detector on beam line –Most extraction equipment exists Needs some refurbishment 30 tons of brass absorber plates (FWD End Door) –Removed from detector on beam line Most extraction equipment exists –Needs refurbishment

June 2, 2008 Bill Wisniewski32 Barrel Flux Return

June 2, 2008 Bill Wisniewski33 Barrel Flux Return Disassembly

June 2, 2008 Bill Wisniewski34 End Door Flux Return

June 2, 2008 Bill Wisniewski35 Flux Return 962 tons of steel (not including end plugs) –Heaviest items 46.2 tons Disassembled in main disassembly area Most tooling exists –Needs refurbishment (stored outside) –Some new tooling needed for safety reasons Affected by metals moratorium

June 2, 2008 Bill Wisniewski36 Moving the Detector Off Beam Line

June 2, 2008 Bill Wisniewski37 Miscellaneous Stairs & Walkways

June 2, 2008 Bill Wisniewski38 West Detector Platform Electronics Racks

June 2, 2008 Bill Wisniewski39 BaBar Electronics House

June 2, 2008 Bill Wisniewski40 BaBar Electronics House – First Floor

June 2, 2008 Bill Wisniewski41 Building 636 (BaBar Gas Shack)

June 2, 2008 Bill Wisniewski42 Chiller Land

June 2, 2008 Bill Wisniewski43