PS CHILLED WATER PROJECT SHUT-DOWN 2000-2001 WHY? THE AGE OF THE PIPING - installed in 1957- 44 years ago - technical life of piping normally 30-50 years.

Slides:



Advertisements
Similar presentations
IT-3872 Refurbishment of the piping of the chilled water circuit of the Proton Synchrotron Alexandre Broche EN-CV-PJ.
Advertisements

Technical Vocational Schools (TEE). Secondary schools (duration 3 years) C.V.T. GEORGIKI ANAPTIXI C.V.T. GEORGIKI ANAPTIXI Naples 9-10/10/2006.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
21/01/02 - ECAL Cooling - Arnaud Hormiere ST/CV 1 Development of ECAL COOLING PLANT Application to a Super Module.
F-595 Chiller contract report Jose Botelho Direito EN/CV/DC Thermosyphon cooling workshop §5 Thursday, October 20, 2011.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire SSD/SDD Proposal Upgrade 30/08/2012
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
EN-CV interventions during YETS
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
Matthew Gardner, 8/20/14.  Replace old water based AC system with conventional rooftop AC system. Drain and abandon old water lines.  Remove old air.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Exquisite Heat For Steam Boilers. Time based system  Thermostat Demand Analysis over time will determine the length of burner fire time of the boiler.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
INVITATION TO TENDER PROCEDURE INVITATION TO TENDER PROCEDURE IT–4134/EN/LHC Supply and Commissioning of HVAC Systems for Five LHC Surface Buildings B.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
WA 104 : TOOLS FOR WORK ORGANIZATION IN THE CLEAN ROOM Erwan Bertrand Olga Beltramello.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
INVITATION TO TENDER PROCEDURE INVITATION TO TENDER PROCEDURE IT–4154/EN Supply Centrifugal Water Pumps B. Jenssen
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Asbestos and Health. Overview n n Background on asbestos n n Uses of asbestos n n Health Effects n n Risk factors n n Medical tests n n Proper handling.
Electrical energy is a very convenient form of energy and it can be easily Converted into other forms. To meet the ever increasing use of electric power.
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
Demineralised water cooling system
SPS-FIRE The SPS Fire Safety Project Planning Status
News and Introduction from CERN June 15th, 2005
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
The Control of Hazardous Energy (Lockout-Tagout)
Situation of the Static Var Compensators at CERN.
LBDS TSU & AS-I failure report (Sept. 2016)
Sources of Energy ELECTRICAL MECHANICAL PNEUMATIC FLUID AND GASES
Status and Plans for InCA
Ongoing consolidation of magnets
INVITATION TO TENDER PROCEDURE IT-4344/EP Design, Supply, Installation, Testing and Commissioning of a Cleanroom extension for the integration of ATLAS.
Francois and Lau EATM 17 July 2012
Safety in Construction and Upgrade Phases
Stewardship Practice: Where & How?
EN-CV Progress EHN1 Extension Project
Operations & Maintenance
Consequences of warming-up a sector above 80 K
Best practices ideas for improvement of industrial return
Installations, modifications, consolidation in 2005:
Y. Muttoni - J.P. Corso TS Workshop Archamps
Renovation of the 45-year old PS magnets
RF operation of REX-ISOLDE
Company Registration: Procedure that one needs to follow Company Registration: Procedure that one needs to follow
EN-CV interventions during EYETS for PS and PSB
IT-4328/EN Bidders conference
Reach 4 Air Valve Replacements Award of Construction Contracts
Low temperature chiller Market Survey
Attic InsulationAttic Crawl Space Cleanup Crawl Space Floor Insulation Rodent Proofing & Rodent ControlThermal Imaging Home Inspections.
The Control of Hazardous Energy (Lockout-Tagout)
Technical update 19 of December 2016
NFIRS 3 Structure Fire Module
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
RF Distribution for Warm Linac
Installation of Photon Beam Transport to FEH
Lockout/tagout Refresher Training
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
Fairfax County Outreach Tool Kits
Utgangspunkt for PowerPoint presentasjoner
ILO Industrial Opportunities Days, 6-7 June 2019
Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019
Linac4 Connection Broken Line 07/08/19
UROP Informational Session - Faculty
19th July 2019 Finish the MU96 re-installation
Presentation transcript:

PS CHILLED WATER PROJECT SHUT-DOWN WHY? THE AGE OF THE PIPING - installed in years ago - technical life of piping normally years THE CONDITION OF THE PIPING AND DEVICES - analysis of weldings! condensation! - breakdown of a compensator in chilled water production renewed in -99 MAINTENANCE - not enough valves- 2 days to empty/refill LHC (?)

PROJECT HISTORY FEASIBILITY STUDY proposition to renew the piping - ST discussions about the necessity - first contact with PS/R.Brown - asbestos analyze by TIS 02/2000 MARKET SURVEY JUNE about 120 firms - information meeting in PS 06/2000 TENDERING SEPTEMBER Bidders Conference 09/ visit to the tunnel 1/2 hour - order 11/2000 to Iniziative Industriali (I) WORKS

PROBLEMS DURING THE PROJECT STUDY PHASE - missing documentation - limited access to the tunnel - lack of experience of “heavy duty” work in the tunnel MARKET SURVEY/ TENDER - only one short visit to the tunnel WORKS - working methods- modified along the way TIS/ST - registration of companies- urgent work not possible! - cleanness ASBESTOS - method of analysis not sufficient- new procedures - responsibility ST/TIS - lack of knowledge on asbestos

STATUS OF THE WORKS CONTRACT - originally about 60% of the tunnel was to be done this shut-down - after the asbestos incident contract reduced to about 35% of the tunnel PIPEWORK - pipe installation work finished insulation work starts after hydraulic test TESTS - x-ray tests results hydraulic test foreseen RECEPTION - reception of the installation latest PS tests start minor interventions during the test period(?)

FUTURE OF THE PROJECT REMAINING WORKS - 65% of piping in the tunnel - all 8 air-conditioning stations - technical gallery between PS tunnel and b at least 5 more years LIMITATIONS - ST/CV project budget cuts - general asbestos removal PS- J.May SCENARIOS - half of the remaining piping next shut-down- normal length shut- down - all the remaining piping next shut-down- longer than normal shut- down - other works?