LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.

Slides:



Advertisements
Similar presentations
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
Advertisements

Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
1 1. Some recent views ( ) 2 Linac tunnel
STATUS OF THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team March 6, 2012CERN.
The Stripping Foil Test Stand in the Linac4 Transfer Line
THE LHC INJECTORS UPGRADE PROJECT - Organisation Malika Meddahi for Roland Garoby and the LIU Project Team.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Nature of workgroup(s) involvedconsequences if not done consolidate beam dumpEN/STIcontinue running with obsolete dump, and without spare upgrade beam.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC.
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
AFC 2017 (and 2018) AFC timeline:
Update on the Critical Path of the PS Booster Schedule for the EYETS
Controls & software Andy Butterworth.
Brief Status SPS Prototype PSB Prototype Installed in LS1
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
LHC schedule.
LIU – EVM status and next steps
AD consolidation activities in LS2
SPS - EYETS 2016/17 Vacuum systems planning
Planning and Installation
EC Activities Status for the LIU
LIU–PLI report LIU SPS meeting.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
TE-ABT Activities for LS2
Preparing the SPS complex alignment for future LHC runs
Installations, modifications, consolidation in 2005:
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
Renovation of the 45-year old PS magnets
SPS activities during LS2 TE-EPC (Power Converter Group)
Acknowledgments: LIU-PT members and deputies, H. Bartosik
TE-MSC activities in SPS during YETS
East Hall under construction
K. Foraz on behalf of OSS members
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Experimental Areas – LS2 planning
ABP/RTL Main RTL Activities for 2007/8:-
Status of the BI Work Package in the LIU-PSB frame
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be performed with obsolete dump and without spare –Transport and handling equipment consolidation If not done: Not ready for heavy work in LS2 LIU-PS: –Shielding of Route Goward and SS16 Not done: would block the access to PS ring center in LS2 –To note: most components installation planned in LS2 LIU-SPS: –aC coating of 1 full SPS sextant: 3.0 missing FTE (1 TE/VSC, 2 TE/MSC) plus transport, SU & FSU Not done: no full-scale validation of ecloud mitigation, 6 sextants in LS2 –Preparation for RF 200 MHz upgrade Not done: Not ready for 2018 installation R.Garoby,S.Gilardoni,B.Goddard,K.Hanke,M.Meddahi,M.Vretenar

LIU Less critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam stopper upgrade If not done: issue for 2 GeV beam (O.K. for LINAC2 operation until LS2) –Magnets incl. modification to the main unit cooling circuit If not done: will have to done in addition to heavy work load in LS2 –Change several transfer line magnets If not done, more work load in LS2 LIU-PS: –Low energy magnet replacement: no resource conflict with LHC, but possible exchange of main bus-bars in conflict with the interventions Can postpone to LS2 –Shielding of top of SMH16 Can postpone to LS2 –Renovation – consolidation activities R.Garoby,S.Gilardoni,B.Goddard,K.Hanke,M.Meddahi,M.Vretenar

LIU Less critical Key activities in Long Shutdown 1 (2013) LIU-SPS: –Relocate damper Can postpone to LS2 but increases LS2 parallel activities with 200 MHz, and increases minimum length of LS2 for SPS (10 months?) –BLM and MOPOS upgrades Can postpone to LS2 but new BI functionality not available for operation in years –MKE impedance reduction Can postpone until 14/15 stop, but machine impedance stays higher, and will continue to have operational limitations with MKE heating until 2015 –MKDV/H impedance reduction Can postpone until LS2 but machine impedance stays higher R.Garoby,S.Gilardoni,B.Goddard,K.Hanke,M.Meddahi,M.Vretenar

Supporting materials

Linac4 in 2013/14 (LS1) 5 The “official” MTP schedule foresee the beam commissioning of Linac4 during LS1 (January- April 2014) (motivations: optimum use of resources, Linac4 available as backup for Linac2 from the start of 2014 run). Present milestones: - April 2013: end of 3 MeV Test Stand reinstallation at Linac4, start 3 MeV beam; - July 2013: beam commissioning at 10 MeV (DTL Tank1); - September 2013: beam commissioning at 50 MeV (DTL); - November/December 2013: beam commissioning at 100 MeV (CCDTL); - March 2014: beam commissioning at 160 MeV (PIMS). Activities in 2013/14 and required resources: - Machine installation ~ 6 months: transport (2 FTE), vacuum (1 FTE). - Hardware tests ~ 3 months: support groups (RF 3 FTE, EPC 2 FTE, CO 1 FTE). - Beam commissioning ~ 6 months: commissioning team (mainly ABP, RF, OP, BI): 6-8 FTE + fellows and visitors.

Linac4 commissioning schedule 6 Start of beam commissioning (3MeV): May 2013 End of beam commissioning (160 MeV): April 2014 (version November 2010) 5 commissioning stages: (on intermediate dumps) 3 MeV10 MeV50 MeV100 MeV160 MeV In 2013/14 (15 months), 6 months of beam commissioning, 3 months of HW tests, 6 months of installation

nature of workgroup(s) involvedconsequences if not done consolidate beam dumpEN/STIcontinue running with obsolete dump, and without spare upgrade beam stopper BTP.STP10 EN/STIOK for operation with Linac2; postpone to LS2 Fluka studiesfellow3 months engineer1 month Conceptual designfellow3 months engineer2 months Design new dumpdesign office5 months technician3 months engineer2 months Manufacture new dumptechnician6 months (+ 2 months FSU) engineer1 month Install new dumptechnician2 weeks Fluka studiesfellow3 months engineer1 month Check actual design for 2 GeVfellow2 months engineer2 months Design BTP beam stopperdesign office5 months technician3 months engineer2 months Manufacture BTP beam stoppertechnician5 months (+ 6 weeks FSU) engineer1 month Install BTP beam stoppertechnician2 weeks manpower estimate dumpmanpower estimate beam stopper LIU-PSB Work - LS1

nature of workgroup(s) involvedconsequences if not done consolidate transport & handling equipment EN/HEwill not to be ready in time for heavy work during LS2 Lift AS 045FTE0.2 Transfer tables CH 066 and CH 067 FTE 0.2 Cranes PR 134, 135, 136 and t FTE 0.2 Crane PR t FTE 0.1 Transport and handling studies FTE 0.1 Transport and handling services FTE 0.2 manpower estimate transport & handling equipment LIU-PSB Work - LS1

LIU-PSB Work – LS2 nature of workgroup(s) involved manpower required all other work according to WBS according to WBS in case the work presently planned for LS1 will not be done in LS1, it will add on to the workload for LS2. Most important is the handling equipment, which must be ready in time for the other activities in LS2, otherwise delays are to be expected important notice: this assumes Linac4 connection in LS2 (present official planning) in case Linac4 connection in LS1 should be decided, a lot of items to be added to the list for LS1

PS activities for LS1 S. Gilardoni, H. Damerau for PS-LIU

Works foreseen for LS1: magnets (tunnel work) Low energy magnet replacement: – Orbit correctors – Trim quadrupoles – Skew quadrupoles Definitive list of magnets to be replaced: pending results of MDs Magnet exchanges not in conflict with LHC interventions in terms of resources Possible exchange of main bus-bars in conflict with the interventions Work could be postponed during LS2

Works foreseen for LS1: civil engineering R.te Goward: increase of the shielding should be done during the LS1 to avoid interference with the LS2 upgrade work: route is the only access to the center of the ring. Shielding on top of SMH16: study should be started this year, not clear if can be done during LS1

Comment on PS-upgrade Not many activities in the tunnel foreseen during LS1 because: – Upgrade studies recently started: studies still to be done to decide equipment/solution to be applied (eg. LL/HL RF) – the technical design of many components remains to be made, even if choice already done (eg. Injection elements will be ready only for LS2) Many activities are outside the tunnel, like: – renovation/consolidation of power converters Most of activities concentrated during LS2.

LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant  3 FTE (missing) TE/VSC – MSC + Transport, SU, FSU VALIDATION for LS2 aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building Most critical items

MTP input – v1.0 Manpower

Manpower estimates MKE, MKDV/H, transverse damper all require punctual transport, vacuum and survey support (few days/weeks) aC coating needs more substantial survey support (maybe 1 month), and continuous transport support (duration ~3 months) These are estimates of what is required, NOT what is available. Note also that for aC coating, 3 FTEs means 12 people for 3 months Presently NO resources from VSC and MSC allocated to aC coating in LS1, so postponing activity to LS2 does not save any manpower for LHC. But if aC coating goes ahead in LS1, then manpower must be found.

Key activities in Long Shutdown 1 (2013) aC coating of 1 full SPS sextant: 1 sextant –3.0 FTE (1 TE/VSC, 2 TE/MSC) plus transport, SU & FSU –Not done: no full-scale validation of ecloud mitigation, 6 sextants in LS2 Relocate/upgrade of transverse damper and PUs: LSS2 & LSS3 –2.0 FTE (BE/RF) plus transport, SU, VSC, plus FSU –Not done: damper upgrade postponed until 2018 Preparation for RF 200 MHz upgrade: LSS3 –4.0 FTE (2.5 BE/RF, 1.5 GS & EN) plus FSU –Not done: RF 200 MHz upgrade not ready for 2018 BLM and MOPOS upgrades (electronics): full ring –3.0 FTE (BE/BI) plus FSU –Not done: BLM and MOPOS upgrades postponed until 2015 Impedance reduction 1 MKE magnet: LSS4 –0.5 FTE (TE/ABT) plus punctual transport, SU & VSC, plus FSU –Not done: MKE impedance reduction not completed until 2015 Modification of MKDVs (impedance): LSS1 –0.5 FTE (TE/ABT) plus punctual transport, SU & VSC, plus FSU –Not done: MKDV/H impedance reduction postponed until 2018 (needs LS)

Implications of postponing work – aC coating aC coating: high priority to do 1 sextant in LS1 –Get one sextant finished –Time frame (1 sextant in 15 months) will allow process to be perfected –Reduce load in LS2 to 5 sextants, with tested logistics and process –Allow beam/vacuum/ecloud measurements in SPS between LS1 and LS2 for treatment validation –Do not treat all machine in one go (in case of problems, easier to reverse...) If not done in LS1: –High pressure with “untried” process and logistics in LS2 –6 sextants to treat in LS2 – even more difficult than 5 –No operational experience on large scale before full deployment –Higher risk of problems, delays –Much less reversible in case of problems

Implications of postponing work – other WPs Relocate damper –Can postpone to LS2 but increases LS2 parallel activities with 200 MHz, and increases minimum length of LS2 for SPS (10 months?) Preparation for RF 200 MHz upgrade –Cannot postpone – otherwise not ready for 2018 installation window BLM and MOPOS upgrades –Can postpone to LS2 but new BI functionality not available for operation in years MKE impedance reduction –Can postpone until 14/15 stp, but machine impedance stays higher, and will continue to have operational limitations with MKE heating until 2015 MKDV/H impedance reduction –Can postpone until LS2 but machine impedance stays higher