Specifications for the Integrated Tests II Paul Huffman.

Slides:



Advertisements
Similar presentations
Electric field calculation for the neutron EDM SNS experiment. Septimiu Balascuta Ricardo Alarcon ASU, 02/07/2008.
Advertisements

Patricia Aguar Bartolomé Institut für Kernphysik, Universität Mainz PSTP 2013 Workshop, Charlottesville 11th September 2013.
High voltage test system update Summary of 2005 results Results from March, May 2006 Possible remaining R&D projects Polished electrodes, clean(er) LHe.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
DHB, nEDM Collab. Mtg, 15/16 Apr 04 UIUC Test System (Beck, Chandler, Hertzog, Kammel, Newman, Peng, Sharp, Williamson, Yoder; Blackburn, Kenyon, Thorsland)
NEDM Collaboration Meeting, May 25-26, He Relaxation Steve Williamson UIUC.
Results from the HV Test System Review of current design and assembly J. Long, P. Barnes, J. Boissevain, J. Gomez, S. Lamoreaux, D. Mischke, S. Penttila.
Ultra-Compact Electrical Machines for Wind Energy DE-FOA : Demo Machine C. L. Goodzeit and M. J. Ball May 1, 2014 General List of Tasks by Performance.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
HD target.
1 Preparation for the 3 He Injection Test 11/2007 MIT/BATES D. Dutta*, H. Gao, M. Busch, Q. Ye, X. Qian, W. Zheng, X. Zhu ( Duke University) ASU, BU, Caltech,
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
1 NEDM 4 He Purifier and Other Cryogenic Issues David G. Haase North Carolina State University Update on Cryovessel Engineering Evaporative Purification.
1 Update of the injection test 06/2007 nEDM H. Gao, M. Busch, Q.Ye, T. Mestler, X. Qian, W. Zheng, X. Zhu Duke University And others in nEDM collaboration.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006.
EDMEDM EDM Collaboration Meeting Project Management Fast Start Summary Prepared by: John P. Tapia May 25, 2006.
EDMEDM EDM Collaboration Meeting 3-06 Jan Boissevain, P-25 March 2, 2006 NCSU EDM Experiment Design Status.
Collab 5/26/06 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson and Contract Project Manager for the EDM Project for presentation to The EDM Collaboration.
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
P25 Interface 5/19/08 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Subsystem Managers Duke University,
Plans for HV R&D at LANL Vacuum chamber Supply cryostat Josh Long, Indiana U. Tests in progress Control purity, contaminants, attempt T < 1.8 K Near Future.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Preparation for the 3He Injection Test
Removal of 3 He from 4 He (R&D) David Haase, Franklin Dubose, Travis McCaw and Paul Huffman North Carolina State University.
EDM Engineering Issues General Mechanical Considerations EDM Cryostat Plan D ANSYS EMAG Calculations ANSYS MECH Calculations 3 June ‘03 J. Boissevain.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Summary of Valve Design Status for nEDM L. Bartoszek BARTOSZEK ENGINEERING 6/20/05.
NEDM Collaboration Meeting ASU 2/2008 Preliminary Engineering Report nEDM Central Detector John C. Ramsey Los Alamos National Laboratory.
NEDM Collaboration Meeting 5/2008 Preliminary Engineering Report nEDM Central Detector John C. Ramsey Los Alamos National Laboratory.
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain, P-25 February 11, 2005, Los Alamos National Laboratory EDM Reference Design Tour of the Reference.
Valve Update  Study several stem/seat geometries (Feb)  Demonstrate He II leak tight for 3/8, 1 in. diameter with modest (~ few psi) pressure difference.
Status of the HV Test System Purposes of the HV test system Design and assembly progress Vacuum enclosure Projected assembly and test milestones (short-term)
EDMEDM C&S Review 2/11/05 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to LANL Cost and Schedule Review Committee.
EDM Assembly and Commissioning – or – How to Cut Two Years from the Project P. Huffman and V. Cianciolo.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
1 Cryogenic Design and the 4 He Evaporative Purifier David G. Haase, et al., North Carolina State University.
EDMEDM EDM Collaboration Meeting 6-05 Jan Boissevain, P-25 June 20, 2005, Los Alamos National Laboratory EDM Reference Design.
Installation of the T600 at Fermilab CSN2, September 22,
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
Status of Engineering Preparations for CD2/3A nEDM Collaboration Meeting – MIT Bates Jan Boissevain November 2, 2007.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
17-18 December 2013 LARP VTF Workshop BNL Proposal 1 A.Marone
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
R&D Plan on Light Collection Takeyasu Ito Los Alamos National Laboratory.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
LANL Cost and Schedule Review 02/11/05 1 Cryostat (lower half) WBS 3.1, 3.5, 3.6, 3.7, 3.8, 3.10 Paul Huffman, Chris O’Shaughnessy North Carolina State.
NEDM Cost and Schedule Review, February 11, 2005 Upper Cryostat and Valves Cost and Schedule for WBS 3.2, 3.3, 3.4, and 8.2 L. M. Bartoszek D. H. Beck.
Office of Nuclear Physics R&D 12/14/06 #1 Risk Based R&D Plan Martin Cooper Los Alamos.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Cryovessel Engineering David Haase, Jan Boissevain, Ernie Ihloff WBS long lead time items Cryovessel Dilution Refrigerator Helium Liquefier.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Teleconf ACS – FREIA 28th March 2017
Installation of the T600 at Fermilab
Status of the PANDA Solenoid Magnet Production in BINP
T5.2: Harmonization - Material and Component Reference
Update on He3 Services design since the ORNL meeting
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LARP Vertical Test Facility
SNS Cryoplant Commissioning Past Experiences
PANDA The conceptual design of the control Dewar
Cryomodule ESS FAT & SAT SRF meetinG on 07/11/2017
as a prototype for Super c-tau factory
IR Beam Transport Status
Optical fiber based sensors for low temperature and superconductors
Presentation transcript:

Specifications for the Integrated Tests II Paul Huffman

Overall Challenge  To bring together the tested components from the individual work packages and integrate them to form a complete apparatus.

Subsystems 1.4 3He Systems Steve Williamson (Illinois) 1.2 Polarized Neutron Beam Line & Shielding Wolfgang Korsch (Kentucky) 1.1 Research & Development Martin Cooper (LANL) 1.6 Central Detector Systems Takeyasu Ito (LANL) 1.8 Infrastructure Walt Sondheim (LANL) 1.9 Assembly & Commissioning Paul Huffman (NCSU) 1.7 Electronics, Computers, Simulations, Data Analysis Jim Miller (Boston U) 1.5 Magnets and Magnetic Shielding Brad Filippone (Cal Tech) 1.3 Cryostats, Refrigerators and Related Equipment David Haase (NCSU)

Overall Challenge  To bring together the tested components from the individual work packages and integrate them to form a complete apparatus.  Three individual subsystems must be integrated into the fourth subsystem (cryogenic vessel) before we can take data: Measurement cell and high voltage system Cryogenic magnetic shields and coils 3 He polarizer, purifier, and transport system  We estimate that each cooldown cycle will take approximately two months. This drives our schedule. We want to keep the number of cooldowns to a minimum!

Planning Assumptions  The subsystems arrive at ORNL fully tested.  The subsystems will be incorporated sequentially in the cryovessel. Measurement cell and high voltage system Cryogenic magnetic shields and coils 3 He polarizer, purifier, and transport system  We require the ability to integrate and test all subsystems w/o the external magnetic shield.  Integration of the DAQ and other external subsystem components will occur in parallel as the systems are integrated. They are ignored in this talk.  Dedicated cryogenic personnel will be hired by ORNL.

Integration Schedule  Everything is dominated by the number of cooldown cycles required for successful commissioning. Our best guesses for the number of cooldowns are: 3 - coil package 4 - insert 4 - 3He components 5 - integrated tests and commissioning (w/ beam, B-shield)  Debugging of systems before they arrive is essential. Tests that could take one week in a smaller test apparatus will take at least two months in the main cryostat.

Goals of this Discussion  DOE recommendation: “Prior to CD-2, develop testing plans that identify the activities and goals for the performance tests of the subsystems at the individual institutions and the assembly site.”  Insure we meet the CD-4 requirements  Remind everyone again of what we have told DOE  Round 2.1 of specifying some internal benchmarks that are more stringent than these DOE minimums

Major Systems as We Have Defined Them  Cryovessel  High voltage system and detector insert  Magnetic shields and coil package  3 He systems

0. Cryovessel  Major components: Helium liquefier and gas storage system Liquid helium transfer system 300 K outer vacuum can 50 K temperature shield 4 K temperature shield 1200 l central volume Dilution refrigerator(s) Instrumentation and controls

1. High Voltage System and Measurement Cell  Major components: High voltage system (T < 500 mK) capacitor plates cell electrodes high-voltage feedthroughs power supplies Detection system (T < 500 mK) dTPB coated measurement cells light collection optics light guide feedthroughs PMT’s or equivalent

Aside  Ground cylinder at 30 cm diameter (D. Mischke)  < 1% variation over cell volume Present diameter ~32” Questions: Why so big now? Can we make it smaller?

2. Cryogenic Shields and Coil Package  Major components: Coil package (T = 4K) cos(Θ) magnet inner dressing coil outer dressing coil trim coils coil support frames Shielding package (T = 4K) superconducting shield ferromagnetic shield 3 He coil package and shields (T = 4K) Instrumentation for field monitoring

3. 3 He Injector and Purifier  Major components: atomic beam source (T < 500 mK) source itself interface to the apparatus 3 He collection volume transport coils and shields * 3 He transport system (T < 500 mK) valves and tubing expansion volumes 3 He depolarization in cell 3 He purifier (T < 500 mK) charcoal pumps volume displacement for level control Instrumentation and controls * Cryogenic shields and coil package subsystem

CD-4 Requirements as Presented to DOE  Cryogenic vessel Demonstrated to cool the central detector volume to 500 mK Operated with the magnet coil package in place  Magnet coil package /B0 < /cm at 77 K *  Four-layer magnetic shield Shielding factor of * * Tests performed offsite

CD-4 Requirements as Presented to DOE (cont.)  Central detector insert High voltage holds 5 kV/cm with a leakage current <10 nA Mean number of photoelectrons from 750 keV of energy deposition is ≥ 4 SQUID noise 1 Neutron storage time in similar cell demonstrated to be >100 sec in an independent test

CD-4 Requirements as Presented to DOE (cont.)  3 He services Produces ≥10 11 /cm 3 of ≥70%-polarized 3 He in the collection volume as seen with a SQUID* Purifier reduces the 3 He concentration to less than 1 part in * 3 He demonstrated to move between volumes with a time constant of 500 s or less* Valves shown to operate over 500 cycles* Installed in the cryogenic vessel  Neutron guides Flux out/MW ≥ 4 x 10 5 n/Å/cm Å with a polarization ≥ 70%

Conceptual Design Report

Cryovessel (starting point)  Demonstrated to cool the central detector volume to a temperature of < 250 mK at ORNL with the central volume full of helium. Liquefier installed and operational Dilution refrigerator(s) (DR) installed and has >80 mW of cooling power at 300 mK (heat applied to the cell) Heat loads to DR/shields characterized and under control Central composite helium volume installed and leak free (blank flanges) Dewar vacuum tight with appropriate temperature shields Fully implemented with diagnostic sensors

High Voltage System and Measurement Cell  Before arrival: Design fully incorporated into the cryovessel design and vetted from a cryogenics standpoint (ie. it will fit in and cool down). Assembly implemented with the appropriate sensors. Assembly shown to meet the CD-4 requirements at 0.5 K: High voltage system shown to hold 5 KV/cm with a leakage current of <10 nA, with the cell and lightguides in place The mean number of photoelectrons from 750 keV of energy deposition is > 4, tested using a radioactive source placed in each cell while the cell if full of helium.

High Voltage System and Measurement Cell  Before arrival (cont.): Assembly shown to meet our collaboration requirements at 0.5 K: High voltage feedthroughs tested for reliability at low temperature (> 5 x 10 4 cycles). High voltage system reliably produces > 40 kV/cm at 500 mK. Light guide penetrations tested for reliability (> 10 cooldowns). The mean number of photoelectrons from 750 keV of energy deposition is > 30, tested using a radioactive source placed in each cell while the cell is full of helium. High-voltage and lightguide feedthroughs shown to impart a total heat load of less than 20 mW into the central volume. UCN storage time in cell measured to be > 1500 s Measured electric field spark rate < 0.2 /year Electric field uniformity measured to be < 8 x over the volume of each cell. Measured using Kerr effect. Eddy current heating measured using RF coil to be < 5 mW

Cryogenic Shields and Coil Package  Before arrival: Design fully incorporated into the cryovessel design and vetted from a cryogenics standpoint (ie. it will fit in and cool down). System is implemented with appropriate sensors. Assembly shown to meet the CD-4 gradient requirement at 77 K and high field: /B 0 < /cm

Cryogenic Shields and Coil Package  Before arrival (cont.): Coil assembly shown to meet our collaboration requirements: High field uniformity test at 300 K performed (horizontally and vertically) High field uniformity test at 77 K performed (vertically) Low field uniformity test at 300 K performed (horizontally in magnetic shields) < 0.05  G/cm B 0 uniformity < 2 x Uniformity of other fields < 2 x Power supply ripple measured to be < 2 x10 -7 Simulation to show that the Eddy current heating in 4 K shield is < 100 mW Calculated I 2 R and thermal heat load at 4.2 K is < 500 mW

Cryogenic Shields and Coil Package  Before arrival (cont.): Magnetic shield assembly shown to meet our collaboration requirements: Controlled 77K test and characterization of the ferromagnetic shield performed. Controlled 77K test and characterization of the superconducting shield performed, preferably w/ ferromagnetic shield. 77K shield tests, when combined with the results from external μ-metal shield tests, provide a total shielding factor of > 8 x 10 4.

3 He Injector and Purifier  Before arrival: Design fully incorporated into the cryovessel design and vetted from a cryogenics standpoint (ie. it will fit in and cool down). Implemented with appropriate sensors. Assembly shown to meet the CD-4 requirements at 0.5 K: ABS produces ≥ /cm 3 of ≥ 70%-polarized 3 He in the collection volume as seen with a SQUID Purifier reduces the 3 He concentration to less than 1 part in He demonstrated to move between volumes with a time constant of 500 s or less Valves working and shown to operate over 500 cycles

3 He Injector and Purifier  Before arrival: Assembly shown to meet our collaboration requirements at 500 mK: Injection 3 He polarization in the collection volume as seen with a SQUID is > 98%. Valves working and shown to operate reliably over 8 x 10 4 cycles. 3 He polarization lifetime in the measurement cells is measured to be greater than 20,000 s. Purifier and injection/transport system shown to work at 500 mK in two independent tests. Polarized 3 He from the ABS fills the collection volume and is then transported along a similar impedance to a full size measurement cell. 3 He polarization is measured in both the cell and collection volume. Operation of the purifier demonstrated, including the regeneration of the charcoal adsorption pumps.

Outstanding Issues  Minimal performance and failure tests of SQUIDS in HV package  Criteria for V1 valve in HV package  Measurement of the alignment of E and B

Summary  Reminder: the duration and costs are dominated by the length and number of cooldowns.  Subsystems must be fully vetted before we attempt to assemble them into the main apparatus!  In working up the CD-2 documentation, make sure you have incorporated the appropriate tests (and costs) into the WBS. The assembly subgroup assumes systems arrive fully tested and they are ready to be incorporated into the cryovessel. Any assembly jigs, etc. should either ship with the subsystem or be included in the infrastructure subgroup.