Siting/Conventional Facilities Jonathan Hunt PIP-II Machine Advisory Committee 9 March 2015.

Slides:



Advertisements
Similar presentations
Presented by: Rod Meredith Assistant Director Public Works Riley County, KS Matthew Leaper Business Development Manager Johnson Controls, Inc. IMPLEMENTING.
Advertisements

LCW Upgrades Update Booster Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions were.
General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin.
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
9/17/07 ILC Detectors 1 Conventional Utilities Tom Lackowski.
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
Nov. 19, 2008 ILC08 Global Design Effort 1 Status Report Alternative Siting and Tunnel Design Tom Lackowski.
AWARD OF CONTRACT FOR CONSTRUCTION OF MASTER DRAINAGE FACILITY LINES D & D1 CIP NO City Council Meeting December 20, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Electrical Utility Service Dennis Danseglio, P.E. Project Engineer.
CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
Costing Meeting Ajit Kurup 13 th June Page 2 Costing Meeting 13 th June 2011 Ajit Kurup Summary of CERN costing workshop. Proposed Level 3 breakdown.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Construction and Installation of the CLIC Experimental Area
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II EFAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Positron Source Relocation 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
Proton Source Water Systems Proton Source Workshop December 8, 2010 Maurice Ball.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
MEIC Collaboration Meeting Site Development - Rebecca YaskyOctober 6, 2015.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
Global Design Effort - CFS ILC10 Beijing, March, Single-Tunnel Accelerator Configuration Of Asian Region Atsushi Enomoto (KEK)
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
May 06, 2013 Photo by Greg Vogel. Thursday, April 18, some tunnel work had to be suspended and many planned jobs had to be postponed due to the flooding.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
Fermilab Proton Driver and Muons David Johnson Fermilab Neutrino Factory Muon Collider Collaboration Meeting March 14, 2006.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Global Design Effort - CFS AD & I Meeting - DESY AD & I Meeting - DESY 1 AD&I Meeting CONVENTIONAL FACILITIES AND SITING GROUP Main Linac Tunnel.
1 V. Kashikhin for ILC ALCPG 2007, FNAL Meeting October 23, 2007 Ring to Main Linac Magnets.
Thomas Jefferson National Accelerator Facility SensL 6-Oct CHL-2 12 GeV CEBAF Upgrade magnets and power supplies Two 1.1GV linacs Enhanced capabilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Overview Scope & Schedule Marty Fallier Director for Conventional Facilities.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
CMTF GROUNDING FOR PIP-II K. Carlson PXIE Electrical Coordination Meeting December 19 th, 2013.
S UPER B site status report S. Tomassini INFN-LNF On behalf of SuperB Collaboration SuperB general meeting– Frascati – December 1-5, 2009.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
SBN Far Detector Building Conventional Facilities Update Steve Dixon WG3 Workshop 11 September 2014.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
ESS Cooling System - Interface with RFQ 1 John Jurns Cooling System Engineer.
Director ’ s Review of the Project X Cost Range Estimate: Conventional Facilities Project X Director’s Review March 16, 2009.
Global Design Effort - CFS ILC Integrated Design Meeting, DESY, May ML Single Tunnel Configurations In Deep Underground Accessed with Long.
Green Labs Symposium | March 15, 2016 Travis Wanat, Senior project manager Department of Facilities Efficient building design and operation Fueling high.
Conventional Facilities/Siting Jonathan Hunt Project X Machine Advisory Committee March 18-19, 2013.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
SUPERB site status report for layout v12
$150K Chicago/ANL seed funding for Braidwood site investigation
(Refer to Chapter 2 of the textbook)
(Potential) Site and Utilities
FCC Tunnel and Shaft Cross Sections
MIRACOSTA COMMUNITY COLLEGE DISTRICT
Print Reading.
JLEIC Accelerator R&D Meeting
Life Cycle Costing.
Presentation transcript:

Siting/Conventional Facilities Jonathan Hunt PIP-II Machine Advisory Committee 9 March 2015

Outline Introduction –Fermilab FESS Engineering Department - Civil Engineer –Professional Engineer, PMP, LEED Green Associate –BS Civil Engineering Siting Scope/Requirements Conventional Facilities Site Power Requirements 3/9/2015Jonathan Hunt | P2MAC_20152

Siting Siting History – 2014 Version 3/9/2015Jonathan Hunt | P2MAC_20153

Siting Current Version 3/9/2015Jonathan Hunt | P2MAC_20154

Siting Wetland Map 3/9/2015Jonathan Hunt | P2MAC_20155

Scope/Requirements Grading Plan 3/9/2015Jonathan Hunt | P2MAC_20156

Scope/Requirements Linac Cross Section 3/9/2015Jonathan Hunt | P2MAC_20157 El. matches Booster and Main Ring tunnels

Scope/Requirements Transfer Line at Booster Cross Section 3/9/2015Jonathan Hunt | P2MAC_20158

Conventional Facilities Site work –Grading ~75,000 CY excavation –Wetland Mitigation Current estimate is 0.40 acres of wetlands disturbed –Mitigated at estimated 4:1 –4 x 0.40 acres = 1.60 acres of wetland mitigation Methods for mitigating wetland disturbance –Purchase wetland bank credits (estimate $70,000 per acre) –Enhance existing wetlands on-site –Create new wetlands on-site Permitting process takes approx. 1 year –Drainage –Roads –Landscaping 3/9/2015Jonathan Hunt | P2MAC_20159

Conventional Facilities Utilities –Power 10,000 LF of new duct banks and feeders Upgrades to two substations included –Communications 2,000 LF of new duct bank –Chilled Water Upgrades to Central Utility Building (CUB) included New supply and return pipe from CUB to Linac –Industrial Cooling Water Connect to piping along Main Ring Road –Domestic Water New supply from CUB –Sanitary Plan includes new lift station –Gas 3/9/2015Jonathan Hunt | P2MAC_201510

Conventional Facilities Facilities Construction –Below grade tunnel enclosures ~1,460 LF of underground tunnel enclosure –720 LF Linac tunnel dimensions – 15’ W x 18’ H –740 LF Transport tunnel dimensions – 10’ W x 8’ H –Above grade Linac Gallery Total area of gallery = 30,000 SF –Center Service Building Area of building = 12,000 SF Highbay 2 cranes (20 tons each) 3/9/2015Jonathan Hunt | P2MAC_201511

Conventional Facilities Sequence of Construction –T - 0 Begin Wetland permit process –T + 1 year - Begin Underground Construction Work Start Excavation and stripping topsoil Place concrete for tunnel enclosures Start utility installations –T years - Begin Above Ground Construction Work Foundations for support buildings Conduits/chases connecting Linac tunnel and Linac Gallery Finish support buildings –T years - Backfill, Seed, and Finishing work –T + 4 years - Complete Construction Work 3/9/2015Presenter's Name | P2MAC_201512

Site Power Requirements Site Power Estimate Power fed from both Kautz Road and Master Substations 3/9/2015Jonathan Hunt | P2MAC_ System Wall-Plug Power (kW) RFQ and MEBT RF320 SC Linac RF1,100 Magnets (quads, solenoids, dipoles)300 Cryogenic Systems3,250 LCW200 Chilled Water500 HVAC200 Conventional Systems300 Total =6,170

Summary Standard construction practices Centralized location of Linac, close to existing utilities and infrastructure Minimizing impacts to existing wetlands 3/9/2015Jonathan Hunt | P2MAC_201514