ELENA installation progress F. Butin / ELENA collaboration.

Slides:



Advertisements
Similar presentations
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Advertisements

ITS Subsystems Availability MACS Week, June 2011 E. Sargsyan PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 1.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Challenges and Overview From Technical Coordination 27/08/2013 -FH1.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
M. Brooks DC Meeting, 15-Sep-00 MuTr Mechanics Status SOUTH ARM: Chambers fabrication complete Stations 2+3 installed Station 1 test-installed will be.
AD/ELENA (B193) Hall Extension F. Butin. Status The need of a new building for AD was already discussed in 2010, First pre-study shown to GTPE 1st Sept.
Contribution from Pakistan to CLIC & CTF-3 Project. NASIR ABBAS
Status of the ELENA transfer lines with special consideration of vacuum, hand-over optics and beam time distribution after 2017 W. Bartmann, D. Barna,
ELENA Hardware Baseline Current Document Status T. Birtwistle EN-MEF-DC.
AD/ELENA (B193) Integration and constraints F. BUTIN / ELENA collaboration.
Vacuum chamber fabrication Dates refer to end of fabrication, then 8 weeks are to be added for NEG coating, bake-out, acceptance tests, etc. EN-MME LNR.
Technology Department 1 ELENA Fast Deflectors status Nicolas Voumard, Jan Schipper TE/ABT/EC TCM 17/11/2015 1/11.
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
Horst Breuker Review Oct ELENA Safety and Radio Protection ELENA TDR : Chapter 6; Safety Files in preparation; Descriptive, Demonstrative (Risk.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
ASTRID2 Niels Hertel Nov 2012 AARHUS UNIVERSITET ASTRID2 – Status ESLS XX Berlin 2012 Niels Hertel ISA, Aarhus University, Denmark 1.
ELENA Layout Naming Convention F. Butin / ELENA collaboration.
WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Steps towards beam commissioning: RF system group Paolo Craievich :: RF Section :: Paul Scherrer Institut SwissFEL.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
ELENA Integration F. Butin / ELENA collaboration.
Report Technical Director Storage-Ring-Installation Completed
Vacuum System P. Chiggiato TE-VSC
Report Technical Director Storage-Ring-Installation Completed
High energy beam transport.
Cabling for LHCb Upgrade
CBETA Technical Review
Brief Status SPS Prototype PSB Prototype Installed in LS1
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
Complementary ISTC Projects #3888, 3889p
Installations up to Start of Commissioning
AD consolidation activities in LS2
LIU–PLI report LIU PSB meeting.
ELENA Beam Transfer Workpackage
on behalf of the RF group
ELENA Overview and Layout Start of ELENA Commissioning Next Steps
T1 Electronic status Conclusions Electronics Cards:
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
The ELENA Safety Documentation «time to prepare the safety clearance»
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
ELENA electron cooler and SEM grids status
352MHz Klystron Control for the 3MeV Linac test stand
Renovation of the 45-year old PS magnets
ELENA Technical Coordination
10/month is the present production rate 2 FTE + sporadic contributions
LLRF and Beam-based Longitudinal Feedback Readiness
How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD
ELENA Magnet Installation Planning
The first shipment of SPEAR3 magnets (9 dipoles and 12 quadrupoles) arrived April 3. The second shipment (3 dipoles, 7 quadrupoles, and 6 sextupoles)
LS1 status 24/03/2014.
Advanced Research Electron Accelerator Laboratory
Experimental Areas – LS2 planning
Daresbury ESS In-Kind Contributions
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Aziz AMAMOU EACM – 21th May 2019
Polarized 3He target installation
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

ELENA installation progress F. Butin / ELENA collaboration

ELENA is on its way… ELENA installation: two main stages (baseline) 1. Jan 2015 – July 2016: Main ring 1.1 Infrastructure + source 1.2 Injection line (from AD) 1.3 Ring machine elements 2. Dec 2016 – Oct 2017: Transfer lines to experiments + corresponding infrastructure (mainly cabling) F. Butin / ELENA collaboration 12

Infrastructure installation Infrastructure installation is nearing completion: Extensive cleaning campaign performed, kicker generators relocated to bdg 393 Survey network complete Metallic support structures complete (central and lateral platforms, racks platform) Cooling demineralized water distribution complete Compressed air network complete AD racks re-organization and re-cabling complete ELENA Racks installation in AD hall complete Cable trays in place F. Butin / ELENA collaboration

Infrastructure installation (2) Infrastructure installation is nearing completion: Signal cables and connectors installation complete AC powering to racks and around ring complete Machine elements supports installed and aligned Injection kicker generator commissioned Shielding elements installation startedOptical fibers installation (mid Nov) IT connections (mid Dec)  RP equipment cabling in progress, monitors in April 2016 F. Butin / ELENA collaboration

Infrastructure installation (3) Infrastructure items remaining to be installed:  Access control systems (mid Jan 2016)  Racks and services (supports, cooling, magnets DC cabling) in AD power room (Dec 2015 – March 2016)  Power converters (March – May 2016) F. Butin / ELENA collaboration

ELENA machine elements F. Butin / ELENA collaboration Dipole magnet Scraper RF Cavity Quadrupole magnets Electron cooler Electrostatic ejection kicker Septum magnet Injection kicker magnet Tune measurement SEM detector Ion switch INJECTION EJECTIO N Electrostatic quadrupole EJECTION Ion source F. Butin ELENA collaboration Longitudinal Pick-up BTV

ELENA machine elements Already in place: Injection Septum magnet, connections and cooling Ion switch (used for injection from ion source) installed and will be tested with source in February Ion source hardware including power supply, HV cables and protection hood. F. Butin / ELENA collaboration

ELENA machine elements (2) And much more to come:  Injection Kicker magnet tank production complete, being vac tested, HV tests planned, instal mid March  Main bending magnets manufactured for Jan 2016, Installation section 3+6 mid Feb, then 1 per month  TL bending magnets ready, install 20 Jan  All other magnets being manufactured, last install 17 May, except last 2 correctors (mid July)  BPM’s built, being vacuum tested (1 per week), pbs with NEG coating, integration inside vac chambers planned mid March F. Butin / ELENA collaboration

ELENA machine elements (3)  LPU’s being assembly being finalized at workshop, install mid May  Scraper vacuum tested, final assembly in progress. New tests needed after assembly, install end June  BTV (on the ring) being vacuum tested, issues with push-pull… Install April  BTV on injection line LNI to be cleaned and vac tested, install end Feb  Electron cooler being manufactured, delivery date TBC, vacuum system production starting, install July, commissioning can start with dummy vac pipe F. Butin / ELENA collaboration

ELENA machine elements (4)  Electrostatic fast deflectors NEG coated, install Feb  Electrostatic quadrupoles ready, install Feb  SEM tank prototype vacuum tested, will be fully equipped and tested with ion source in Feb  RF cavity in production, vacuum tests planned in march, install mid April  Tune measurement production started, install April.  Vacuum components either purchased, procured or being manufactured / tested / NEG coated at CERN. F. Butin / ELENA collaboration

Schedule overview F. Butin/ ELENA collaboration InfrastructureMachineCommissionning

Conclusions  Infrastructure installation complete, in time  Installation of injection line inside AD shielding being performed during YETS: major milestone  Machine elements production and testing is ongoing, some delays but no impact yet  Machine elements installation has started, pace will increase as of February F. Butin / ELENA collaboration

Conclusions (2)  Planning still in line with ring commissionning in July 2016  Transfer lines installation slot still pending (Dec 2016 – Sept 2017 or LS2…)  Aegis removal ECR awaited…  GBAR exp area being re-organized, bunker installation to start in Feb, online monitoring of impact on AD magnets location  ALPHA and ASACUSA exp areas enlargement proposed, financing to be secured, participation of EP department expected F. Butin/ ELENA collaboration