MICE RLSR – 13Nov2013 Alain Blondel 1 MICE Project Board 14 November 2013 Alain Blondel.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
Changing the absorbers: how does it fit in the MICE experimental programme? Besides the requirement that the amount of multiple scattering material be.
Alain Blondel MICE: Constraints on the solenoids 2.Field Homogeneity: or ? this will be dictated by the detector requirements. TPG will be.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
MICE analysis meeting Alain Blondel 5 August MICE -- what running strategy? disclaimer: of course we will evolve the running strategy as problems.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Alain Blondel MICE Funding Agency Committee MICE status report Most of the technical progress has been covered in the open session except the.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
MICE Project Board MPB Alain Blondel 1 MICE Project board 3 MICE Status Responses to MPB2 recommandations.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
MICE CM Alain Blondel 1   MICE GOALS OF THE MEETING Welcome to MICE CM28.
Physics Program and Runs: Autumn 2011 & Step IV V. Blackmore MICE Project Board, 08/03/12.
CM37 Alain Blondel step IV physics success 1 « STEP IV operations : Physics »
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
MICE magnetic measurements: AFC considerations Alain Blondel see a previous discussion for reference in CM35 (Feb 2013 slides by V. Blackmore, A. Blondel.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Spectrometer solenoid 2. Magnetic shielding 3. Next Collaboration meeting.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE VC 10-Oct-2013 Alain Blondel 1 MICE NEWS VC 162 LOTS OF THINGS HAPPENED! have arrived at RAL: -- EMR (see report today) -- AFC2 see pictures -- SS2.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting CM36 will be Jun at IIT and the 19th at Fermilab right before.
MICE CMPB Alain Blondel 1 Highlights on MICE.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
MICE CM30 Goals of the Meeting Alain Blondel 1 MICE CM30 – Goals and Status.
MICE CM33 – system test? Alain Blondel 1 CM 33 wrap-up TOWARDS CM34.
MICE, Uni-Geneva and the transnational access to MICE (MICE-TNA)
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
(one of the) Request from MPB
S TATUS OF THE P HYSICS A NALYSIS V. Blackmore MICE Project Board 29 th April, /30.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
MICE CM41 – CB summary Alain Blondel 1 Collaboration Board at CM41 Summary Alain Blondel.
MICE news Alain Blondel 20 – NEWS 1.CERN’s SPSC at Villars: recommandations 2.MICE step Upcoming gateway steps 4.RF from LBNL (Mike)
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
Spectrometer Solenoid Update
MICE CM31 Schedule summary
MICE NEWS MICE VC 155 Next Collaboration meeting will be
Completing the Step IV Programme
Controls & Monitoring in MICE
Presentation transcript:

MICE RLSR – 13Nov2013 Alain Blondel 1 MICE Project Board 14 November 2013 Alain Blondel

MICE RLSR – 13Nov2013 Alain Blondel 2 OVERVIEW Recommendation 1. Create a living, accessible and regularly updated one-page "dashboard" summary of milestone achievements demonstrating the evolving status of deliverables (eg magnets), initially focusing on Step IV, as soon as possible. (a dynamic presentation of the data normally contained in Gail’s Milestone table after selection of most significant milestones)  Roy Preece Recommendation 2. Produce a one-page specification for the operation of the MICE International Project Office and present at the next MPB meeting This was drafted by Andy Nichols, pending full approval by CB.  Ken Long Conclusions and recommandations from MPB in May 2013(I) also written up in the written report to MPB

MICE RLSR – 13Nov2013 Alain Blondel 3 SUPERCONDUCTING MAGNETS Recommendation 3. Investigate the potential reasons for the slow and unusual training of Spectrometer Solenoid 2 (and Focusing Coil 1). Check the protocols (eg travelers) for the Spectrometer Solenoids and Focusing Coils, to establish the level of quality assurance and to seek explanations for slow training. Present results at the next MPB meeting. We dont have a predictive understanding of the behaviour of the magnets but we have collected the data and made a number of tests.  John Cobb Recommendation 4. Re-evaluate the possibility of proximity shielding (partial yoke) that takes into account the detailed situation of the present infrastructure in the MICE hall and present a plan for future work at the mitigation shielding review at RAL in August/September. The magnetic mitigation group did this.  Holger Witte RF SYSTEMS Recommendation 5. Prepare a plan to test a prototype Low Level RF system with the RF Coupling Coil at the Fermilab MTA, and present the plan at the next MPB meeting. We have decided not to do this. Conclusions and recommandations of MPB (II)

MICE RLSR – 13Nov2013 Alain Blondel 4 COMMISSIONING, CONTROLS & OPERATIONS Recommendation 6. Present an integrated plan for all aspects of the control system at the next MPB meeting. (Controls team is preparing this. Very much work in progress!)  Pierrick Hanlet Recommendation 7. Present the requirements and design of the MICE timing system at the next MPB meeting, with particular emphasis on absolute calibration by particle arrival phase measurement. Work ongoing, in collaboration between DAQ expert and RF group at DL.  Kevin Ronald Recommendation 8. Explore the potential to achieve synergistic economies of scale in the maintenance and operation of the liquid hydrogen system by working with the ISIS moderator cryogenics team, and present at the next MPB meeting.  Ken Long Recommendation 9. Develop an on-site support plan for day-today operations, maintenance and repair of the MICE hardware, and present at the next MPB meeting. (  MICE operations group)  Ken Long Conclusions and recommandations of MPB (III)

MICE RLSR – 13Nov2013 Alain Blondel  Provisional MICE SCHEDULE update: May 2013 STEP I STEP IV (Q2 2014, no field) Q to Q STEP VI Run date: EMR run July 2013 Under construction: Possible Step V run Q Step VI 2019

MICE RLSR – 13Nov2013 Alain Blondel Provisional MICE SCHEDULE update: November 2013 Begin Run date: EMR run Oct 2013 done (possibly : w/o field July14) Q1/Q to Q1/Q Step VI Q2 2020/Q best case / worst case possible Step V Q3 2018/Q2 2019

MICE RLSR – 13Nov2013 Alain Blondel 7 A lot has happened in the last few months! Have arrived at RAL: -- RF amplifier crates of RF equipement from U-Miss -- The EMR and all its kit -- the Upstream Spectrometer Solenoid (USS) (aka SS2) -- the AFC2 + we have carried out the EMR run with beautiful results  (and with all available detectors included in the DAQ) + we have decided on the field mitigation strategy and passed a review. + our paper on emittance measurement of the MICE beam with TOFs is published. Avatars: -- Decay solenoid had a burned LTS lead during test of new QPS  fix by Apr14 -- Downstream Spectrometer Solenoid had a few issues  delivery in May14 -- Coupling Coil test had 2: He leak in June, thermal insulation needs redone. Coupling coil test  Q

MICE RLSR – 13Nov2013 Alain Blondel 8

9 CERN mapping

MICE RLSR – 13Nov2013 Alain Blondel 10 Construction of Coupling coil cryostat at LBNL And testing of CC1 at Fermilab hmmm, MLI wrapping needs to be redone...

Mapped Currents Mode Solenoid Flip Runs cover the above currents, plus: 0A measurements (residual field) 30A individual coil measurements (superposition) With and without Virostek plate A lot of data 3/21 V. Blackmore

MICE RLSR – 13Nov2013 Alain Blondel 12 EMR run took place 4 week-ends Thursday 13:00 to Monday night MOM: Ryan Bayes

MICE RLSR – 13Nov2013 Alain Blondel 13 several millions of triggers.

MICE RLSR – 13Nov2013 Alain Blondel 14 e-e- -- --

MICE Field Mitigation Review Alain Blondel 15 Magnetic shielding review panel endorsed MICE proposal... with caveats: Principle has been reviewed and decided. next steps : implementation, while taking into account comments of review panel  towards PRReview

MICE Field Mitigation Review Alain Blondel 16 Changes 1. New spokesperson : Ken Long We are working together to ensure a smooth transition. ABlondel will be Collaboration Board chair for next two years. 2. Project manager will now be Roy Preece Andy Nichols will continue as Project Engineer 3. Linda Coney has moved on -- Ian Taylor is now the head of the online group -- new MICE Operations Coordinator will be needed

MICE Field Mitigation Review Alain Blondel 17 LOOKING FORWARD TO STEP IV

MICE RLSR – 13Nov2013 Alain Blondel this was discussed yesterday in RLSR

MICE RLSR – 13Nov2013 Alain Blondel No or empty absorber Alignment Optics studies Solid absorber(s) LiH Plastic C, Al, Cu LiH Wedge absorber Emittance exchange Liq H 2 absorber (full/empty) Multiple scattering Energy loss  Cooling STEP IV EXPERIMENTS ( )

MICE RLSR – 13Nov2013 Alain Blondel

21

MICE Field Mitigation Review Alain Blondel 22 HOWEVER... a lot will depend on what the magnets can deliver we will know only when the beamline is assembled the Upstream Spectrometer Solenoid USS (SS2) was tested and passed for all requested ‘design’ curents. AFC1 passed for the maximum requested current in «solenoid mode», but not in «flip mode» where the ‘nominal setting’ (center of 3x3 matrix) is barely achieved. Situation may be worse (or better) when all magnet are powered in step IV configuration.

MICE Field Mitigation Review Alain Blondel 23 Flip mode design (maximal) setting flip mode nominal setting Solenoid mode design setting

MICE Field Mitigation Review Alain Blondel MICE Note 434

MICE RLSR – 13Nov2013 Alain Blondel 25 Conclusions 1. MICE is in happy shape, looking forward to step IV! -- With new Spokesperson, Project Manager, Project Engineer -- Several important milestones have been passed 2. Decision was made to implement the Partial Return Yoke -- schedule will be more predictable 3. Next large uncertainty concerns the performance of the magnets when powered all together -- we are preparing to adapt to peformance being lower than design but above the ‘nominal point’. (modify beta function at absorber) -- however if performance were below the ‘nominal point’ MICE would force more drastic questionning to know how to go forward with the experiment. 4. Preparations for STEP V/VI are progressing

MICE RLSR – 13Nov2013 Alain Blondel 26 SPARE SLIDES

MICE RLSR – 13Nov2013 Alain Blondel

28 THEN we can do the physics!

MICE RLSR – 13Nov2013 Alain Blondel

32 MICE beam Successful run in Oct’13 but rate limited because DS has a burned LTS lead (to be fixed during the winter shut down) muon (or pion) stops and decays