3 MeV Measurements at Lianc4 1 Veliko Dimov (for the source and linac team) (J-B Lallement, J. Lettry, A. Lombardi, D. Fink)

Slides:



Advertisements
Similar presentations
Imperial College 1 Progress at the RAL Front End Test Stand J. Pozimski Talk outline : Overview Ion source development LEBT RFQ Beam Chopper MEBT.
Advertisements

P. A. Posocco – TH10 STATUS OF LINAC BEAM COMMISSIONING FOR THE ITALIAN HADRON THERAPY CENTER CNAO P. A. Posocco INFN-Laboratori Nazionali di Legnaro On.
LINAC4 and 3 MeV test stand at CERN
C. Rossi – L4 Project Meeting 3 March 2011 Status and Plans of 3 MeV Test Stand.
Experience with Bunch Shape Monitors at SNS A. Aleksandrov Spallation Neutron Source, Oak Ridge, USA.
UKNF OsC RAL – 21 & 22 June 2010 UKNF achievements & milestones J. Pozimski.
ESS DTL beam commissioning
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
Chopping Simulations Results M. Garcia Tudela, JB. Lallement, PA. Posocco, A. Lombardi, G.Bellodi, M. Eshraqi, E. Sargsyan, L. Hein 1 17/06/2010.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Linac-4 current situation and outlook U. Raich, F. Roncarolo, F. Zocca.
Injector PP Setup Plan and Status November 18, 2008 Haixin Huang.
REFERENCES [1] C.Y. Tan, FNAL Beams-doc-3646-v16, 2011 [2] V.N. Aseev, TRACK, the beam dynamics code, PAC05 [3] S. Kurennoy, LA-UR TRANSMISSION.
Experience from the Spallation Neutron Source Commissioning Dong-o Jeon Accelerator Physics Group Oak Ridge National Laboratory May 9, 2007.
Imperial College 1 Plans and Costs Front End Test Stand Aim is to demonstrate a 60 mA, 2 ms, 50 pps chopped beam at 3 MeV RAL/ISIS (ION SOURCE, CHOPPER,
Lesson learned in Linac Commissioning Here I introduce 3 kinds of beam loss generated by following issues 1.Intra beam stripping (IBSt) in ACS 2.Dark.
LINAC4 COMMISSIONING A.Lombardi BCC 8-19 Nov 09 Linac4 BCC Nov 2009Alessandra Lombardi.
The Stripping Foil Test Stand in the Linac4 Transfer Line
ICFA-HB 2004 Commissioning Experience for the SNS Linac A. Aleksandrov, S. Assadi, I. Campisi, P. Chu, S. Cousineau, V. Danilov, G. Dodson, J. Galambos,
LIU Day – 11 th april 2014 ALESSANDRA LOMBARDI LINAC4 COMMISSIONING OVERVIEW.
Developments of the FETS Ion Source Scott Lawrie.
A Few Pointers from the Linac4 Beam Commissioning of Warm Linac Yngve Levinsen Beam Physics Section 05/02/16.
K.Hanke / TDR Meeting / 13 June 2006 Linac 4 Diagnostics L4: K. Hanke, M.Pasini (requirements, specifications, integration) AB/BI: U.Raich et al. (technical.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
3 MeV test stand measurement plans A. Lombardi for the LINAC4 team 10/01/2013BCC MeV test stand measurements1.
3 MeV instrumentation commissioning U. Raich, Federico Roncarolo, F. Zocca Linac-4 Beam Coordination Committee CERN, 18.December 2013 Uli Raich.
Beam Measurements After the Sources at the Ion Source Test Stand Including H 2, N 2 and Kr Gas Injection R Scrivens, Linac 4 10/04/2014 Lots of input from.
FETS-HINS Videoconference 23rd Feb 2007 FETS Mechanical Design Issues by J. Pozimski On behalf of P. Savage.
H4F Physics Day 2014 C.Ullmann Proton injector status for FAIR and measurements at BETSI test bench (CEA/Saclay) 2014.
LINAC4 emittance measurements BI Day Divonne, 24 th November 11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 1.
PXIE Beam Instrumentation Status Update – Preparing for MEBT 1.1 Beam Vic Scarpine Feb. 9, 2016.
Linac4 DTL Beam Dynamics 1Jean-Baptiste Lallement – Mini-workshop on DTL design - 13/09/2011 Mini-workshop on DTL design – 13 September 2011 JB Lallement,
PIP-II R&D Program PXIE Ion source and LEBT Lionel Prost PIP-II Machine Advisory Committee Meeting March 2016.
PXIE warm front end status A. Shemyakin PIP-II technical meeting 3 May 2016.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
The Preparation for CSNS Accelerator Commissioning Sheng Wang June 8, 2015, Dongguan.
PIP-II Beam Instrumentation Vic Scarpine PIP-II Machine Advisory Committee Meeting March 2016.
D. Li, Project X Collaboration Meeting, Fermilab (October 25-27, 2011) Overview of Project X Frond-End R&D at LBNL Derun Li Project X Collaboration Meeting.
ESS Front End diagnostic
Bunch Shape Monitor for HINS Wai-Ming Tam Project X Collaboration Meeting September 11, 2009.
Linac4 status and perspectives
NICA injection complex status
BEAM DYNAMICS STUDIES for IFMIF-EVEDA ACCELERATORS
Experience with beam instrumentation at Linac4
Linac4 Beam Characteristics
HIPPI yearly meeting, sep28-sep
Progress in the Multi-Ion Injector Linac Design
GPT Simulations of the Ion Source Beam
Naming convention Rules
BE-BI Software for LINAC4
LINAC 4 source & LEBT measurement results
1- Short pulse neutron source
LINAC4 LEBT beam size and emittance diagnostics
CSNS Accelerator Control and Beam Instrumentation JIN Dapeng, XU Taoguang … June 9, 2015
The Cornell High Brightness Injector
LINAC4 commissioning plans etc.
Andreas Jansson, Lali Tchelidze
ESHAC meeting October 1-2, 2018
Considerations on Beam Diagnostics Physics
commissioning and measurements
Physics Design on Injector I
ISRC and LEBT Vacuum System Design
Ion Source and LEBT Beam Diagnostics
(Beam) Commissioning Plan
Front End Test Stand (F.E.T.S.) Engineering Progress Report
Status of the JLEIC Injector Linac Design
Multi-Ion Injector Linac Design – Progress Summary
Simon Jolly UKNFIC Meeting 25th April 2008
22-SAR MEBT Vacuum test Aitor Zugazaga Zamudio, 27 March 2019.
Presentation transcript:

3 MeV Measurements at Lianc4 1 Veliko Dimov (for the source and linac team) (J-B Lallement, J. Lettry, A. Lombardi, D. Fink)

Status of the Linac4 beam commissioning Commissioning up to 12 MeV (end of 1 st DTL tank) was completed (end of 2014). 2 nd and 3 rd DTL tanks were installed in the tunnel. Next stage is 50MeV beam commissioning. Short period of measurements at 3MeV. To check the performance of the RFQ with the new H- source (beam current 20mA  50mA) To see what beam we expect for the 50MeV beam commissioning stage. 2

Beam Current Transformers (BCT) for Transmission measurements Dump Chopper Measurements at 3 MeV 3 Faraday Cup Wire scanners Transmission through the RFQ Different LEBT pressure levels Different Source settings Beam current at the LEBT (Faraday cup and BCT) Different source settings by varying the first solenoid Wire Scanner measurements at 3MeV.

We have 30mA beam at 3 MeV Ion Source output beam current: 50mA 4

Transmission Through the RFQ 5 37 mA (before the RFQ) 42 mA (before the RFQ) What comes out of the RFQ is the same (30mA): input emittance is bigger than the RFQ acceptance!!!

Estimating the emittance by comparing with the simulations. 6 The transmission depends on the beam current and emittance. 37 mA (before the RFQ) 42 mA (before the RFQ)

Wire scanner: comparison of the expected and measured beam profiles ExpectedMeasured x_rms (mm) y_rms (mm) Beam spot from the simulations

Conclusion We could estimate the emittance at the RFQ entrance via transmission measurements. Emittance coming out of the source is bigger than the RFQ acceptance: there is still room for improvements. Good progress towards the 50MeV commissioning. The beam current after the RFQ increased significantly (compared to last year). We have 30 mA beam (at 3MeV) for the beam commissioning at 50 MeV. Confirmed the beam we have at 3MeV (important input for the preparation of 50MeV commissioning). We need mA in MEBT to meet the specifications for the LHC beam. 8