TOWER A Bldg.
As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION 423 Calendar Days NUMBER OF DAYS LAPSED191 Calendar Days NUMBER OF DAYS REMAINING248 Calendar Days PROJECTED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67%
GROUND FLR RIGHT WING AREAGROUND FLR. LEFT WING AREA RETOUCHING AND FINISHING
2 nd FLOOR LEVEL LEFT WING AREA 2 nd FLOOR LEVEL RIGHT WING AREA RETOUCHING AND FINISHING
3 rd FLOOR LEVEL RIGHT WING AREA3 rd FLOOR LEVEL LEFT WING AREA RETOUCHING AND FINISHING
4 th FLOOR RIGHT WING AREA4 th FLOOR LEFT WING AREA RETOUCHING AND FINISHING, PILING OF CHB 4” AND 6”
5 th FLOOR LEFT WING AREA 5 th FLOOR RIGHT WING AREA, PILING OF CHB 4” AND 6”
6 th FLR. LEFT WING AREA: 6 th FLR. RIGHT WING AREA CLEARING OF FORMWORKS
7 th FLR. RIGHT WING AREA7 th FLR. LEFT WING AREA CLEARING OF FORMWORKS
8 TH FLR. LEFT WING AREA8 TH FLR. RIGHT WING AREA CLEARING OF FORMWORKS
9 TH FLR. LEFT WING AREA 9 TH FLR. RIGHT WING AREA SHORING AND FORMWORKS FOR 10 TH FLOOR
10 TH FLR. LEFT WING AREA: CONCRETED SUSPENDED SLAB 10 TH FLR. RIGHT WING AREA: FORMWORKS FOR SLAB AND ROUGHING- INS