G. GIRAUDO - D. ORECCHINI Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 Central Trackers assembly.

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

PANDA Mechanical Workshop Backward Endcap Calorimeter Geometry David Rodríguez Piñeiro GSI Darmstadt PANDA Mechanical Workshop GSI
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
PANDA Collaboration Meeting Backward Endcap Calorimeter Geometry David Rodríguez Piñeiro GSI Darmstadt PANDA Collaboration Meeting GSI
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
MICE Installation and Commissioning meeting RAL, 12 June 2007 Diffuser Oxford University.
MICE Alignment and Support Structure Tony Jones and Yury Ivanyushenkov Engineering Department RAL.
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
INFN-LNF / D. Orecchini – S. Tomassini – 06/24-25/2015 CLAS12 – RICH MECHANICS REVIEW SLIDE 1 RICH MODULE INTEGRATION IN CLAS_12 – LAST LAYOUT RICH MODULE.
SuperFRS Multiplett and Dipole Vacuum Interfaces Multiplett: Insulation vacuum: Insulation Vacuum Pumping flanges: Two CF flanges of the size DN160 must.
MUON_EDR-06 (Alignment) Enrique Calvo Alamillo February 28-March 1, 2002 Link Mechanics: Status.
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
We have to fix the design of the flanges on the 1 st horn frame to which the target support beams are attached.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
Progress on Stave assembly tooling Stephanie Yang (Oxford) WP4 meeting at Liverpool University, 13 th November 2014.
XXXIX PANDA COLLABORATION MEETING GSI-DECEMBER 2011 B. GIRAUDO / D. ORECCHINI CENTRAL SUPPORT FRAME STRUCTURAL ANALYSIS FIRST APPROACH AND PRELIMINARY.
Joint Institute for Nuclear Research Deformations and stresses in the flux return yoke A.Efremov, Yu.Lobanov, A.Makarov Darmstadt,
- PROPOSAL FOR A SOLUTION OF A “STRAW MODULE” INTEGRATION - INFN-LNF - SPAS -STRAW MODULES INTEGRATION- INFN-LNF-SPAS- December D. Orecchini – P.
PANDA Target Pipe Meeting Alfons Khoukaz Institut für Kernphysik, WWU Münster, Germany PANDA Target Pipe Meeting February 2013.
MVD COOLING STATUS COOLING PLANT UPDATE: -ADDITION of the NEW CIRCUITS FOR GBT AND DC-DC Converter BOARDS IN THE COOLING PLANT -THERMAL STUDY OF GBT AND.
Sébastien MICHALMarch Sébastien MICHALMarch 2009 EES 1 GROOVE EES 1 laid on table to be milled EES 1 laid on table to be milled –Move horizontally.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
/ 11 Updates of PANDA 3D Model CM June 2016 at GSI, MEC Session J. Lühning, GSI Updates for: Panda Hall Target Spectrometer Latest version.
STT Detector risk’s assessment. STT detector work packages Straw Tubes modules Straw Tracker mechanics Front-End Electronics Analog electronics Digital.
Concept for LOKI detector system. Rear Detector 2 Spider Cob (central detector) Octant (Out detector) Maybe subdivided in two parts.
1)– CENTRAL TRACKER INTEGRATED ITEMS: > Central Tracker, “Assembly & Insertion Auxiliary Structure”. > “CSF”- Central Tracker Support Frame (In collaboration.
- “STRAW TRACKER AND CLASH ITEMS ANALYSIS. - “STRAW TRACKER AND STILL OPENED ITEMS ANALYSIS. - “STRAW TRACKER AND DANGEROUS ITEMS ANALYSIS. INFN-LNF -
Miscellaneous about Target Spectrometer PANDA Mechanics Meeting, September 2015 J. Lühning, GSI Space around Barrel Target Platform Cable Routing.
MVD updates SUMMARY OF GSI OCTOBER 28th -29th
Miscellaneous MEC Topics Mainz, CM September 2016, MEC Session J
Progress with System Integration of the CBM Silicon Tracking Detector
Ferrara MECHANICAL SUPPORT for forward tracking detectors Federico Evangelisti INFN - Ferrara GSI – 2-6 march 2009.
“CENTRAL SUPPORT FRAME” -
Some Updates on Mechanics CM-MEC Session Dec J. Lühning, GSI
Miscellaneous Topics MEC Session, CM March 2017 at GSI J. Lühning, GSI
STRAW TRACKER SYSTEM CAD STATUS :
MECHANICAL FRAME OF THE MVD
Target Spectrometer Updates CM-MEC Session Giessen, March 2015 J
MECHANICS OF THE FORWARD STRAW TUBE TRACKER (preliminary) Federico Evangelisti INFN - Ferrara GSI - 7/11 dicember 2009.
Update of MVD services and requests
Beam
MVD Mechanics update EXTERNAL FRAME: NEW DESIGN
- CT INSTALLATION PROCEDURE OVERVIEW -
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Work progress in Turin x the MVD
PANDA Yoke of the Magnet
MVD updates SUMMARY OF GSI OCTOBER 28th -29th
STRAW TRACKER CLASH AND INTEGRATION ANALYSIS- INFN-LNF - SPAS
INSTALLATION SEQUENCE
David Rodríguez Piñeiro GSI Darmstadt PANDA Collaboration Meeting Turin EMC BW Endcap.
Central Tracker Support Frame MEC Session, CM June 2017 at GSI J
Assembly procedure – Inner Region
Mechanics: (Tim).
Gingin Advisory Committee Meeting 08 Dec 2009
IHEP group Shashlyk activity towards TDR
Status of the PANDA Magnet
Integration – preliminary ideas on routing and tests
Integration issues at IHEP
EMC BWE PANDA Insertion
List of changes and improvements for the next generation CLIC module
(A) (B) - CENTRAL SUPPORT FRAME - INFN-LNF - SPAS 1
Rod adaptors for module tests Module positioning studies
First of all we will remind some numbers:
The 11T cryo-assembly: summary of design and integration aspects
Hall C Down Stream Beam Pipe And Dump Interface Design
BCM Overview Placement such that system is sensitive to all types of beam accidents. => 2 independent subsystems Halo losses inside the Pixel volume ie.
Status of the PANDA Solenoid Magnet Production in BINP
as a prototype for Super c-tau factory
Technical Updates Gábor László NSS Lead Instrument Engineer
BGC Collaboration Meeting –
Presentation transcript:

G. GIRAUDO - D. ORECCHINI Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 Central Trackers assembly sequence and Interface with cross-pipe - draft proposal - 1

ASSEMBLY SEQUENCE Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 Preliminary work in a Clean Dedicated Area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance) G. GIRAUDO - D. ORECCHINI 2

ASSEMBLY SEQUENCE Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails 3

ASSEMBLY SEQUENCE Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open 4

ASSEMBLY SEQUENCE Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open  Cross Pipe Mounting and Alignments 5

ASSEMBLY SEQUENCE Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open  Cross Pipe Mounting and Alignments  Clamps Close 6

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE Cross Pipe – CF Interfaces (existing design) Clamping Sleeve must be integrated with the Target Arm Clearance Sleeve/CF  CRITICAL Relative Orientation, Coaxiality  CRITICAL Position of the horizontal pipe  CRITICAL New Solution must be evaluated G. GIRAUDO - D. ORECCHINI 7

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open  Cross Pipe Mounting and Alignments  Clamps Close  MVD & MVD’s cooling + electronics assembly 8 GBT set Fixed on Flange & CF

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013  Manufacturing tolerances  Assembly tolerances  0.8 mm clearance between beam pipe and disks ASSEMBLY SEQUENCE G. GIRAUDO - D. ORECCHINI 9

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open  Cross Pipe Mounting and Alignments  Clamps Close  MVD & MVD’s cooling + electronics assembly  STT & STT’s electronics assembly 10

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE ADDITIONAL SUSPENSION MUST BE ADDED AUXILIARY SUPPORT STRUCTURE MUST BE EXTENDED G. GIRAUDO - D. ORECCHINI Preliminary work in a clean Dedicated area  Auxiliary Support Structure + Dummy Rails Aligned (Survey Service Assistance)  Central Frame on Rails  Clamps Open  Cross Pipe Mounting and Alignments  Clamps Close  MVD & MVD’s cooling + electronics assembly  STT & STT’s electronics assembly  Beam Pipe Upstream Sector (DC-DC Converters) 11

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE READY TO MOVE TO THE SERVICE PLATFORM G. GIRAUDO - D. ORECCHINI 12

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE CENTRAL TRACKING SYSTEM SLIDES IN G. GIRAUDO - D. ORECCHINI 13

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI SUMMARY The clamping sleeves must be integrated with the Target Arms  Tolerances (geometry, manufacturing & assembly) MVD assembly – Possible problem with Beam Arm  Tolerances (geometry, manufacturing & assembly) Beam Pipe Upstream Sector act as DC-DC Converters holder Beam Pipe Upstream Sector (DC-DC Converters) must be suspended during assembly and handling  Interaction with End-Cap EMC during assembly 14

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 ASSEMBLY SEQUENCE G. GIRAUDO - D. ORECCHINI 15 Beam Pipe sector as a whole

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI 16 ASSEMBLY SEQUENCE Whole MVD assembled 2840

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI 17 ASSEMBLY SEQUENCE Preliminary Upstream pipe sector: (Preliminary) welded support for electronics Support for cooling pipe still missing

Beam-Target line for PANDA – GSI – 4 February 2013 Beam-Target line for PANDA – GSI – 4 February 2013 G. GIRAUDO - D. ORECCHINI 18