LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.

Slides:



Advertisements
Similar presentations
Review of 2011 studies and priorities for 2012 LIU-SPS-BD.
Advertisements

Strategy for SPS 200 MHz LLRF upgrade (1)  Each of the four cavities (2x 5 sections, 2x 4 sections):  1-T Feedback (loop around cavity and amplifier)
Few slides from J. Fox’ talk in last November’s LARP meeting LARP CM
Update of achievable beam characteristics at injection in LHC H.Bartosik, C.Bracco, O.Brüning, C.Carli, K.Cornelis, H.Damerau, R.Garoby, S.Gilardoni, B.Goddard,
STATUS OF THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team March 6, 2012CERN.
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
THE LHC INJECTORS UPGRADE (“LIU”) PROJECT R. Garoby for the LIU Project Team LIU-2011November 25, 2011CERN.
LIU-SPS ZS Electrostatic Septum Upgrade Review held on M.J. Barnes & T. Kramer.
Overview WP14 Developments Hardware  Interferometry on the spare TDIs, planned to be installed Christmas stop 2015/2016. Final acceptance tests ongoing.
LIU and (E)YETS LIU-SPS Coordination Meeting 28/01/15 David Mcfarlane
Some ideas for/from the SPS LIU-SPS team. Scrubbing (only) for ecloud in SPS? aC coating remains baseline..... –but scrubbing has many potential advantages.
Outcome of HBW damper Review of W. Hofle LIU-SPS HBW damper review LIU SPS Coordination,
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
News and hot topics Impedance meeting 14/04/2014.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LIU-SPS RF Power upgrade | 09 December 2015.
LIU-SPS upgrade, schedule, target parameters and observed limits 1 B. Goddard, E. Shaposhnikova for LIU-SPS coordination team SPS scrubbing review
Extraction and beamline progress B.Goddard TE/ABT.
LIU budget cuts – SPS savings? First brainstorming discussions!!! BG 30/4/14.
POTENTIAL EN-MME DESIGN JOBS IDENTIFIED BUT CURRENTLY NO REQUEST FROM EQUIPMENT OWNERS TO EN-MME EDMS B.RIFFAUD On behalf of EN-MME design team.
LIU-SPS action list for BE/BI L. Jensen with input from BL, PI, QP, PM 27/08/2015Lars K. Jensen BE/BI/SW1.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
End-of-year talk LIU-SPS BD WG meeting Our meetings in 2015 O During year - 9 meetings of LIU-SPS BD WG (as in 2013, but 10 in 2014 and 12 in.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 17 th December 2013.
The way to fast and "loss-free" SPS kickers E. Gaxiola With contributions from AB-BT-KSL section and F. Caspers, T. Kroyer, M. Timmins, J. Uythoven.
TPSG4 validation at HighRadMat #6 Cedric Baud, B. Balhan, Jan Borburgh, Brennan Goddard, Wim Weterings.
Discussion and preliminary conclusions LIU-SPS dump review.
Beam absorbers for Machine Protection at LHC and SPS
Introduction R. Garoby LIU 2014April 11,  LIU summary  LIU Highlights in 2013  Outcome of the «Review of LHC and Injectors Upgrade Plans» (Oct.2013)
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
SPS BEAM DUMP UPGRADE FUTURE CABLING CAMPAIGNS Georgi Minchev Georgiev EN-EL-FC.
High Intensity Beams in Existing Accelerators for CN2PY: SPS studies, PS issues E. Shaposhnikova Laguna-LBNO General Meeting CERN, Acknowledgments:
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Outcome of beam dynamics simulations - Scenarios, requirements and expected gains s LIU-SPS Coordination meeting 26/08/2015 A. Lasheen, E. Shaposhnikova,
Reminder of upcoming milestones For all machines: Nov. 2012:Table of performance parameters Jan. 2013: Baseline activities defined Feb. 2013: Update APT/EVM.
LIU-SPS Beam Dynamics WG E. Shaposhnikova LIU-SPS coordination meeting
LIU-SPS T. Kramer, L. Ducimetiere, L. Sermeus, J. Uythoven LIU-IONS 20 th November /11/2015 LIU-ABT Review - SPS2.
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. HL-LHC.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
2016 Chamonix Workshop Summary of the HL-LHC Session
Oleksiy Dolinskyy December 1st, 2014
B.Goddard for the LIU-SPS team
BE-CO Activities for LIU-CPS and LIU-SPS
Harmonic system for LHC
LIU Wire Scanner Milestones June 2017
Plans for ions in the injector complex D
Impact of TIDVG problem on LSS5 dump design schedule
LIU – EVM status and next steps
SPS - EYETS 2016/17 Vacuum systems planning
EC Activities Status for the LIU
LIU / HL-LHC Cost and Schedule Review
LHC Beam Vacuum activities during YETS LS2
LIU–PLI report LIU SPS meeting.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
10 MHz amplifier status G. Favia
TE-ABT Activities for LS2
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Update on the HiLumi/LIU parameters and performance ramp up after LS2
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Impedance working group update
Also on behalf of V. Senaj & L. Ducimetière
Beam dynamics requirements after LS2
LIU-SPS review for BI (no BWS)
eSPS Impedance Considerations Aaron Farricker Acknowledgements: T
Presentation transcript:

LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16

Recall of project baseline Beam status 25 ns, 4x72b P (GeV/c) N b (10 11 ) ɛ x,y (μm) ɛ z (eVs) τ (ns) Achieved LIU baseline * HL-LHC request * Above nominal LHC beams (with 50 ns and 25 ns spacing ) were successfully delivered to the LHC during Run1 and in 2015, but twice higher intensity (even more for brightness) is needed in future for HL- LHC

LIU-SPS HW upgrades For ions, damper upgrade, plus low-level RF upgrade for slip-stacking

Main 2016 objectives Launch/follow-up procurement and construction for main systems 200 MHz upgrade (series drivers, mains protos, coaxial lines, BAF3...) LSS5: beam dump and shielding, kickers, civil engineering, generators and cables TCDI collimators and masks MOPOS electronics Vacuum flange impedance shielding (for EYETs installation) In-situ 2xMBB aC coating bench RF low level upgrade Track and update EYETS and LS2 planning with all co-activity and service requests Develop design for adequate 200 MHz HOM reduction Finalise 200 MHz power coupler design and launch prototype Develop concept for significant MKP impedance reduction Review options and finalise TPSG4 design Review prototype high bandwidth feedback system and future deployment needs Re-evalaute need and possibilities for collimation in view of 2015 loss and activation

Reviews in 2016? High bandwidth damper: September – Use-cases, prototype performance, slotline kicker, full system cost and timeline LSS5 beam dump block and shielding: March/April – Concept, reliability, MTBF, transport & handling, decomissioning, margins, procurement strategy, schedule, cost LSS% dump kicker systems: March/April? – Aperture, sweep functions, magnet apertures, new MKDV switch performance, failure cases, procurement strategy, schedule, cost TPSG4 preferred solution: ? – Hybrid MSE/TPSG versus new diluter tank upstream QFA418 Tranverse beam size diagnostics: ? – Wirescanner, BGI and BSRT status and outlook