WBS 1.6 - Experiment Infrastructure: LArTF GPP Project Status Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 11/02/12.

Slides:



Advertisements
Similar presentations
KCDC Knox County Development Corporation Virtual Building 50,000 SF Manufacturing- 4,300 SF office building.
Advertisements

“Sustainable Building Systems and Construction For Designers” Chapter 7: Walls.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Skyscraper Construction
Unit 44 Ceiling Framing Ceiling Joists • Laying Out Ceiling Frames • Constructing Ceiling Frames • Attic Scuttles • Constructing Flat Roof Ceilings.
DG Inyorkern Weekly Project Summary 1/17/14. DG Inyokern 1/17/14: Percentage Overview Demolition: Pad Prep: 100% Finished and ceriified Footing & Foundation:
LArTF and MicroBooNE Installation
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
Estimating Waste Week 3 CTC-415. What is waste Waste is material that needs to be supplied but may not be used All material items except steel beams and.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Rectangular framed structures
Chapter 19 Floors.
TECHNICAL ASSIGNMENT #1 – NATHAN BRASKEY SUNNYVALE PLAZA [Cooper Carry, Inc.]
Dirty Tour December 2005 UN Capital Master Plan. 2 Dirty Tour- introduction The UN building was a state-of-the-art, code compliant structure when it was.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Maintaining Structural Integrity. Structural Integrity Before we can understand how to maintain structural integrity, we need to understand how homes.
Construction and Installation of the CLIC Experimental Area
Author name here for Edited books chapter 6 Facility Construction 6 chapter.
HVACR116 – Trade Skills Mechanical Drawings.
Fire and Emergency Services Company Officer — Lesson 17 Fire and Emergency Services Company Officer, 4 th Edition Chapter 17 — Preincident Planning.
Demonstrating a Home Under Construction Purpose: To use your knowledge of the construction process and production USPs to influence the sales process and.
CONSTRUCTING HOMES & OTHER BLDGS. Preparing the Construction Site –Clearing the Site: the site must be cleared of anything that would get in the way of.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
RESIDENTIAL CONSTRUCTION UNIT Grade 10 Construction Technology TCJ200.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
March 2015 ALLEN INDEPENDENT SCHOOL DISTRICT School Board Meeting March 2015 Construction Update for the Service Center.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
The four basic types of structures are :
GROUPAMA Football Stadium, Budapest Design and other engineering work for the precast concrete structure Precast solution of the structure (splitting.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Framed Structures Luisana Hernández.
October 19, 2011 Construction Progress Report. Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to.
Estimating and Scheduling CEE 492
WBS Experiment Infrastructure: Design Status Discussion Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 6/17/11.
OTE Building PMG Report September 10, 2012 Rhonda Merchut 1.
T600 Detector FNAL Fernanda G. Garcia Fermi National Accelerator Laboratory.
Children’s Section of the Library Entrance lobby from Main Street looking east.
MICROSOFT PROJECT MODULE 2 - BUILD A HOUSE.
Foundations of Technology Construction
How Completed Interiors Are Achieved: Designing & Building
San Luis Potosi – New plant April 24th 2015
SBN Far Detector integration model overview
October 2017 Mustang panther package b update
Construction 101 Start to Finish
Pinole-Hercules Water Pollution Control Plant Upgrade Project
Daniel Suter Unknown Data Center Somewhere, USA
G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations.
Organics Waste Processing Facility Construction Progress Update December 15, 2010
Minuteman Vocational Technical Regional High School Progress
Progress Report 11/10/11.
Arch205 building construction wall systems
Minuteman Vocational Technical Regional High School Progress
Collapse Patterns.
House Construction Budget Plan
New White Lake Township Library
Foundations of Technology Construction
In-Class Scheduling Exercise
Minuteman Vocational Technical Regional High School Progress
© OnCourse Learning.
Minuteman Vocational Technical Regional High School Progress
Polarized 3He target installation
“ Construction of a Hospital Building” Submitted by: Zuhaib Alam 15PWIND0402 Submitted To: Prof.Rashid Nawaz Department of Industrial Engineering University.
Presentation transcript:

WBS Experiment Infrastructure: LArTF GPP Project Status Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 11/02/12

LArTF Construction Progress  Whittaker has made good progress since my last slide presentation prepared for the July Collaboration Meeting. As the following slides will show, the 24’ basic structure has been completed with the exception of roofing, and exterior masonry has begun. Utility installation is making good progress; duct banks and ICW piping to the building are complete. The natural gas tie in and piping remains to be done, and 13.8 kV feeder cables must be pulled and tied in to existing feeder lines.  Whittaker has generally been on schedule with the work since July, but in September an unfortunate delay was introduced with the omission of one small but critical piece of pre-cast concrete. This omission was the result of a miscommunication of information between the pre-cast manufacturer and the A/E that designed the LArTF. It took about four weeks to design a “work- around” correction, manufacture the piece, and deliver and install it. This has delayed roofing the loading dock and the main cylinder, with subsequent other delays and impacts. My personal analysis is that there had been no float prior to this problem, and that it is now quite possible that if winter weather is not very favorable, Whittaker will NOT be able to achieve the March 15, 2013 beneficial occupancy date (now only four months away and counting!!!) MicroBooNE Collab Slides 11/02/12– D. Bogert 2

LArTF Construction Progress  It is worth noting the following caveat: To date, the vast majority of the work, which is now approaching 60% of the total dollarized effort, has been self performed by Whittaker. This includes the excavation and the concrete forming and placing. There is now a fairly complete (when the roofs are finished!) but completely hollow structure. No electrical conduits, fixtures, or wiring has been installed, no fire protection piping, and no HVAC ducts or equipment has been installed. All of this remaining work will be performed by Whittaker’s subcontractors, and Whittaker now switches from self performance to being a supervising broker that must manage, schedule and push the various subcontractors to complete the work, a substantial amount of which must now be accomplished in parallel (i.e. working together in sometimes awkward or difficult to access spaces.)  Whittaker is capable of doing this subcontractor management, but it will be demanding on them.  Post beneficial occupancy planning has continued, and the LArTF staff has continued to work with the rest of the project to adapt, support, and provide requested information to permit pre-planning and pre-assembly of cryogenics and electrical work to proceed. MicroBooNE Collab Slides 11/02/12– D. Bogert 3

The parapet wall has been poured 8/8/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 4

The platform for roof beams built 8/8/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 5

Starting to form the roof beams 8/8/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 6

ReBar in place for roof beam 8/13/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 7

Roof beams formed 8/14/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 8

Placing concrete in roof beams 8/15/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 9

Footings for the Electronics Room 8/20/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 10

Footings for the Exterior Stair Room 8/20/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 11

Footings for the Exterior Stair Room 8/30/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 12

Removing the Roof Beam Forming Support 8/30/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 13

Footings for the Loading Dock 9/6/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 14

Footings for the Loading Dock 9/12/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 15

Loading Dock Floor 9/19/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 16

Setting Precast Pieces 9/19/12 and 9/20/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 17

Precast Walls Set; Missing Spandrel Piece 9/21/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 18

Controls Duct Bank 9/25/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 19

13.8kV Duct Bank to Switch Pad 9/25/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 20

Overview 10/9/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 21

Dewar Supports 10/15/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 22

Looking Up the Cylinder to Roof Beams 10/15/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 23

Interior of Electronics Room 10/29/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 24

Missing Spandrel Piece Installed 10/29/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 25

Interior of Cylinder; Stair Bases 10/29/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 26

Overview 10/29/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 27

Exterior Masonry 11/1/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 28

Roof Framing and Crane Column Steel 11/1/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 29

Excavation for Natural Gas Tie-In Hot Tap 11/1/12 MicroBooNE Collab Slides 11/02/12– D. Bogert 30