DBM status and path to the prototype D. Giugni / INFN Milano D. Giugni nSQP meeting 2011-09-15 1.

Slides:



Advertisements
Similar presentations
RS-485 Data Link Tester Team Members:Raymond Weber Lance Spotted Elk Sponsor:LED Effects.
Advertisements

Routed Systems Presented by: Bassam Najar, Design Engineer Butler International Inc.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
Printed Circuit Board Design
ER Bundle “final” design D. Giugni / INFN Milano D. Giugni nSQP's meeting 1.
1 Airborne Science Program EMASHSI Kick Off Meeting Interfaces NASA Ames Research Center University of California Santa Cruz Airborne Science & Technology.
ATLAS POH.P, G.D12/5/2009 IBL Update H. Pernegger, G. Darbo (PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings.
E-readout workplan & organization Successfully passed FDR – Draft report: ATL-IP-MR-0003ATL-IP-MR-0003 Mechanical baseline is defined Focus now more on.
University of Connecticut Virtual Lab Carl DiFederico, Shane Tobey, Kasim Ward Graduate Student Advisor: Qihang Shi Senior Faculty Advisor: Mohammed Tehranipoor.
Current ILC work at Fermilab Electrical Engineering Dept.
COE4OI5 Engineering Design. Copyright S. Shirani 2 Course Outline Design process, design of digital hardware Programmable logic technology Altera’s UP2.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
GE1/1 Services and Strips PCB Andrey Marinov On behalf of CMS GEMs collaboration.
M.Oriunno, SLAC Stave cable and module options. M.Oriunno, SLAC Background - module The IBL electrical unit for data output is a single chip The use of.
1 IBL Integration & Testing activities University of Geneva: G.Barbier, F.Cadoux, A.Clark, D.Ferrère, C.Husi, M. Weber  Preliminary definition of Integration.
CS 4850: Senior Project Fall 2014 Object-Oriented Design.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
Status report on the development of a readout system based on the SALTRO-16 chip Leif Jönsson Lund University LCTPC Collaboration Meeting
Positioning fork M. Ciappeti R. Vuillermet 29/09/20111.
NSQP X-1 ASSEMBLY Lessons learned Sébastien MICHAL January 30 rd 2012.
Nov. 8, 2001M. Garcia-Sciveres -- PP0 & Service Panels1 PP0 & Service Panels 1.Introduction 2.Technical Status 3.Goals for 2002.
ATLAS Pixel Detector September 2003 Services E. Anderssen LBNL Service Connectivity from Module to PP1b Eric Anderssen LBNL Pixel Services Meeting, CERN.
Twisted Pair Cable A.Nomerotski 12/12/02  Dense assembly (OD 5-7 mm) with u Twisted pairs : total 21; 44-pin mm dual row Omnetics connector s differential.
Dance Pad Project By: David Dorsten. Understand  Electric Engineering Project = Dance Pad and Light Bulb Station  This activity will demonstrate the.
Information for the assembly of the test board w/ PMT and preamps
L. Greiner1IPHC-LBNL Phone Conference 05/2012 STAR IPHC-LBNL Phone Conference News and updated ladder testing.
Vessel dimensions GTK assembly carrier Electrical connections Cooling pipes integration Vessel alignment with the beam Next steps Conclusion 3/10/20102.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
Proposal for LST-based IFR barrel upgrade Roberto Calabrese Ferrara University Workshop on IFR replacement, SLAC, 11/14/2002.
Oct/07/2010Pixel PP0 opto replacement issues1 1 1 PP0 Opto Replacement Issues Philippe Grenier, Martin Kocian, Dave Nelson, Marco Oriunno, Su Dong, Charlie.
David Nelson SQP E-board November 4, Pixel nSQP E-board Presented by David Nelson
Single Board Controller Comments Roger Smith Caltech
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
Vessel dimensions GTK assembly carrier Electrical connections Cooling pipes integration Vessel alignment with the beam Next steps Conclusion 3/23/20102electro-mechanical.
Annecy, Carleton/CRPP, Colorado, Colorado State, LBNL, Maryland, McGill, MIT, Montreal, INFN Padova, INFN Pisa, Princeton, INFN Rome, UC San Diego, UC.
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
IBL CO 2 cooling flexible transfer integration into IDEP 24 July 2013 Jan Godlewski, Bart Verlaat, Siegfried Wenig, Nicolas Massol, Tomasz Blaszczyk 1.
GLAST LAT ProjectEnv Test Planning,15 March 2005 LAT System Engineering 1 LAT Thermal Vac EGSE Cabling.
1 MQXF(S) Magnet Interface Document MQXF(S) magnet interface document will describe electrical connection between the magnet and the header assembly Scope.
Mathias Reinecke CALICE week - Manchester Electronics Integration - Status Mathias Reinecke for the AHCAL developers.
Pierre Barroca ITK LAPP – Goals 2.Simulation 3.Prototype measurements 4.Setup 5.Results 6.Conclusions 1.Goals 2.Simulation 3.Prototype measurements.
Mauro Citterio Milano, PP2/Services - an update - Mauro Citterio INFN Milano Type II cables  Layout in progress  Duplication of VVDC wires.
1 Chamber Interfaces Adalberto Readout-, I2C-, HV-, LV-, Gas- and chamber support interface. Space issues.
NSQP’s + design implications D. Giugni / INFN Milano D. Giugni nSQP's meeting 1.
News from PNPI Presented by N. Bondar for B. Bochin Cagliari 8/10/2015.
Week 22: Schematic Week 23-Week 27: Routing Gerber files have been available since 9th July 1st prototype: – PCB manufacturer: supervised by KIT – Cabling:
USTileCal Planning UTA ITC Scintillator Project R. Miller May 13, E3 C10 B11 E1 D5 A14 - A15 B14 D6 A D4 A12 A13 B12 - B
22/09/2011 ADO-PO section meeting ADO : Atlas Detector Operation PO : Project Office R. Vuillermet.
Mauro Citterio - Mi meeting
ATLAS Internal ID Service Integration
SMR 21/09/2017 P. Fessia.
Service channels between Tracker and PP1
Calorimeter Mu2e Development electronics Front-end Review
Service channels between Tracker and PP1
Module Loading Task Force Meeting October 21, 2004
Current DCC Design LED Board
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Activities Status and Plan for the week
Activities Status and Plan for the week
CDR Project Summary and Issues
3.4 Mi-com upload if necessary
GLAST LAT System Engineering
TEC Services Status 30/12/2018 Nick Lumb.
Update on ATLAS insertable B-layer
Status of CC-PC Evaluation Board
IKCA CEA Technical ANNEXES Follow up 18th DECEMBER 2015.
Electronic : PH0 (former IH0)
Presentation transcript:

DBM status and path to the prototype D. Giugni / INFN Milano D. Giugni nSQP meeting

Top level schematics –Signals- D. GiugninSQP meeting

Top level schematics –Power D. GiugninSQP meeting

PP0 Interfaces D. GiugninSQP meeting eCooling Pipe 2 PP0 Signal Board 4 PP0 Power Board 4 Power bundles 2 Signal bundles

PP0 interfaces (C4 hidden) D. GiugninSQP meeting Cooling Fittings

D. GiugninSQP meeting Cooling Fittings

D. GiugninSQP meeting Power bundles 2 Signal bundles Penetration for the 4 Power bundles  AXON conn. Penetration for the 4 Power bundles  IBL Conn Board

Assembly sequence Not enough time here to go through the complex assembly sequence.... but it is there and the design has been workout (also modified since last meeting) to make the assembling process working D. GiugninSQP meeting

Path to the prototype (1) DBM Wires definition –Almost there. Still to define the insulation for the AWG 22 CCA (LV) and the colour. –MWS PO being to sent out as soon the above issues are defined. –Planned to buy wires for 10 bundles that includes prototypes, tests and the two deliverables Schematics. –Top level schematic is available: ATL-IP-ES-0184 –Boards schematics are available : ATL-IP-ES-0183 –AXON Connector pinout is missing!!! D. GiugninSQP meeting

Path to the prototype (2) Engineering and assembly sequence are now coherent. –Electrical interfaces (connectors to the DBM telescopes and to the IBL optobox) are defined. –Cooling interfaces (fittings) are defined –Routing and space checks are ok D. GiugninSQP meeting

Path to the prototype (3) nSQP-DBM-IBL meeting being setup. –Looks like Wed is the right date if SLAC people are available. Can we set by then? –Scope is to agree on the top level schematic and on the DBM interfaces D. GiugninSQP meeting

Path to the prototype (4) My proposal: –Since... the DBM have two separate bundles: Signal(IBL Con Board) and Power (AXON) wires for the signals are available (ER Bundles) The IBL Connector board schematic and gerbers are available: –ATL-IP-ES-0176 v.1 IBL Connector Board Schematic –ATL-IP-ES-0177 v.1 IBL Connector Board Gerber Files we could start to produce the Signal bundle and load it on the nSQP trial assembly. D. GiugninSQP meeting