SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.

Slides:



Advertisements
Similar presentations
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
Advertisements

LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
SPS RESTARTING AFTER LS1 05/03/2015 Stéphane Cettour Cavé.
R. Corsini, CLIC Project Meeting October 24, 2012 CTF3 Experimental program for end 2012 R. Corsini for the CTF3 Team 1.
SPS re-commissioning with beam K. Cornelis PS-SPS days.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
ELENA EXTRACTION LINES W. Bartmann, D. Barna, M. Fraser, J. Jentzsch, R. Ostojic ELENA Commissioning discussion, 23th November, 2015.
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
AEM, Sept Frank Chlebana (Fermilab) Status of the LHC and CMS Frank Chlebana (Fermilab) All Experimenter’s Meeting Sept
Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
ABT-EC EYETS Activities 2nd reports
Wednesday 8.9 External crossing angles:
TE-MSC activities in SPS during LS2
ELENA installation and commissioning status
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Transfer line test: Beam stability measurements
The LHC - Status Is COLD Is almost fully commissioned
Injection BIS – next iteration
Instrumentation for SPS 2006 restart
Coordination of Hardware Commissioning
Possible causes for SPS ZS2 misalignment
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
the CERN Electrical network protection system
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Summary of week 7 Hardware Commissioning:
James Ridewood BE-OP-SPS
Monday 11/07: Recovery Plenty of accesses.
CNGS Proton Beam: Introduction
Summary of ion week 48 Last beam OP summary of 2010 Week 48
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Power cut 18kV cable for EMD404/E9 is heating
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
CNGS Primary Beam Results 2010
Interlocking of CNGS (and other high intensity beams) at the SPS
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
LHC Morning Meeting - G. Arduini
Friday 14th December - morning
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
Saturday 28/4 06:30 staring injection and transfer line steering.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 03/11 – The Plan Finish electron-cloud program:
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
week coordination report 15/06/2018
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Tuesday
SPS Injection BIS - Draft requirements
Presentation transcript:

SPS start up 2014 SPS OP

SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different features. SPS completely re-aligned. Parts of TT10 stripped out and re-installed. LSS1 (injection zone including dump systems), removed, re-cabled and re-installed. New low level RF-control. New damper low level control. TCC2 (splitter and target region) removed, re-cabled and re-installed.

Hardware Commissioning Priority to new transformers and MPS (8 weeks). Testing functionalities of new FGC’s (on, off, reset, pulse start, coast…) Polarity checks in transfer lines during nights and weekends when PC’s became available. Testing of all motorisation. Problems : Interruptions : Crash program to replace the severely damaged beam dump. Several magnets had to be replaced (water leaks, vacuum leaks, and short to earth) Slow conditioning of MKP and MKD due to vacuum interventions. Late availability of current measurements ( difficult to validate PC performance). Late availability of new FESA3 classes

A non existing cold check out 5 days stop due to cooled cable on QD which had to be replaced. Week of “Jeune Genevois” a lot of experts on holidays

Beam commissioning Night 12 to 13 September, first beam (SFT) came down TT10 immediately. Spent Saturday 13th on debugging orbit monitors.(e.g. factor of 1000 wrong for BPM in TT10) Sunday 14 th : Acceleration of SFT pro and 25nsec injected. Week spent on commissioning BPM system (kick response measurements, and repairing faulty BPM’s)

Beam commissioning Weekend of September 20 th, after 2 iterations of beam based alignment (see previous MSWG), setting up of slow extraction. SFTPRO after: h rms /v rms = 2.1/1.8 mm LHC (Q20) after: h rms /v rms = 2.3/1.6 mm

Beam commissioning Outgassing of MKP and MKD limiting LHC 25 nsec beam. (1)48 bunches (100msec) e-cloud regime. (2)12 bunches, 21 sec, heating due beam induced e.m. fields. After scrubbing run (beginning of November) nominal LHC 25nsec could be accelerated. 1 2

“Bilan” of the first weeks of beam commissioning 11 cables in LSS1 not connected, badly connected, or not existing (SEM grids, interlock cable to BHZ377, communication cable for MPS). Beam based alignment with two optics worked well. New RF controls, needed setting up, but working well. Damper software became available while commissioning new hardware.

Setting up TT20 Beam transfer to NA had to wait until TCC2 work was finished. Magnets still being connected 2 weeks before beam. Almost no time for hardware commissioning (PC commissioning and polarity checks). Friday 3 rd October, first beam on T2. T4 and T6 ready on October 9th

Issues with TT20 Two PC’s with wrong polarity. New FGC accept only negative current if bipolar. Before, negative strength resulted in systematically in negative current even for unipolar supplies. Lot of issues with power convertors: trips, difficult to start, reset not working preventing progress. (no real hardware commissioning) Cables of SEM grids on splitters had to be swapped. Opposite sign convention for moving monitors on target with ‘wobbling’. Target

Comparison Injection-acceleration12h 24hrs BPM set up+beam based alignment3days6days Extraction + TT20 transfer6 hours6days In 2014 no high intensity beams (> ) possible for the first month, due to outgassing of MKP, MKD, new beam dump and damper commissioning.

Conclusions After cabling campaigns it is up to the equipment groups to check their connections. Having “Jeune Genevois and scheduling Chamonix” during start up is perhaps not the best choice. In spite of many break downs during hardware commissioning and start up, SPS could deliver beam more or less as scheduled (first scrubbing run had to be moved). After all the changes during LS1 the machine restarted remarkably well. After the hard work during LS1 and the stressful end of LS1, the hardware groups wore running out of resources during start up.