From Russia With Love: Truly Integrated Project Scope, Schedule, Resource and Risk Information Vladimir Liberzon, PMP and Russell D. Archibald, PMP.

Slides:



Advertisements
Similar presentations
Implementing Corporate Project Management System Spider Project Team
Advertisements

CP Chapter 4 Schedule Planning.
Estimating, scheduling and budgeting
Resource Limited Project Management
Project Cost Management Chapter 7
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Managing Project Success
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Management of projects, programs and portfolios in Russia and Eastern Europe Approaches and Lessons Learned Man.
Success Driven Project Management Methodology
Tools and Techniques for Corporate Project Management Vladimir Liberzon Spider Management Technologies Session # PTA08.
Project management development in Russia Achievements and lessons learned.
Vladimir Liberzon Oksana Sakhraui Victoria Shavirina Spider Management Technologies, Moscow, Russia
Vladimir Liberzon, PMP Spider Project Team Moscow, Russia PMI Chapter Success Driven Project Management Methodology.
Project Management Methodology Project monitoring and control.
Spider Project History Spider Project - professional project management software package with unparalleled functionality. The first.
Methods and Tools of Success Driven Project Management
4 th European Project Management Conference, London, 6-7 June 2001 Resource Critical Path Approach to Project Schedule Management Vladimir Liberzon, PMP.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
Resource Management in the Corporate Project Management Systems Vladimir Liberzon Victoria Shavyrina Liubov Guzhova Spider Project Team.
Vladimir Liberzon, PMP Spider Project Team Moscow, Russia PMI Chapter Application of SDPM approach to managing EPC projects 1.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
Introduction- Project Management By Ctrl+C & Ctrl+V 1.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Software Project Management Lecture # 7. What are we studying today? Chapter 24 - Project Scheduling  Effort distribution  Defining task set for the.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Software Project Management (SPM)
Ahmad Al-Ghoul. Learning Objectives Explain what a project is,, list various attributes of projects. Describe project management, discuss Who uses Project.
Management & Development of Complex Projects Course Code MS Project Management Earned Value Concepts Lecture # 19.
Advanced Project Management Project Time Management Ghazala Amin.
Project Cost Management
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Chain Scheduling, PERT, and MS Project 2003.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 1 Five Ways to Build a Microsoft Project Schedule Lynn Frock, PMP Phone
Project Time Management
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Where Module 04 : Knowing Where the Project Is 1.
SOFTWARE PROJECT MANAGEMENT
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Developing the schedule – Tracking Gantt charts Critical path method – Longest path, earliest time Schedule trade-offs using CPM – Free slack, total slack.
Project Management PTM721S
Project Cost Management
Chapter 16 – Project Management
Project Management – PTM721S
Project COST Management
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Project TIME Management
ENGR 281 Engineering Scholars Program Project Management Life Cycle Overview K. F. Reinschmidt J. L. Frank / Marathon Ashland Petroleum LLC Chair in.
Establishing and Managing a Schedule Baseline
Project Cost Management
ECE2799 Project Management
Chapter 6: Project Time Management
Project Time Management
Risk Analysis & Success Driven Project Management
Project Time Management
Project - Execution stage
Project Cost Management
Fine-Tuning your plan and obtaining approval
Project Time Management
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
Managing Project Work, Scope, Schedules, and Cost
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

From Russia With Love: Truly Integrated Project Scope, Schedule, Resource and Risk Information Vladimir Liberzon, PMP and Russell D. Archibald, PMP

Need for Integrated Project Scope, Schedule, Resource and Risk Information 1.Project performance estimation that includes all valuable factors 2.Reliable estimates of future project results 3.Early warning of potential problems 4.Proper motivation for activity performance sequencing & resource allocation

Presentation Objectives Describe proven methods used in Russia: –Success Driven Project Management/SDPM: Unique aspects –Discuss its application on a sample project Compare SDPM with earned value & critical chain methods

Success Driven Project Management/SDPM Planning Stage: –Calculate finish dates & costs with the required probabilities of their successful achievement –Set target dates, costs & other restrictions –Calculate success probabilities –Determine contingency reserves Execution and Control: –Calculate current probabilities of achieving goals –Track success probability trends –Manage contingency reserves

Success Probability 1.System forecasts resulting required resources & contingency reserves based on user defined acceptable probability of success to meet specific scope, schedule & cost targets 2.System calculates the probability of meeting imposed targets (success probabilities)

The Project Planning Dilemma Goals: –Complete project ASAP with minimum cost, & also –Develop plan with guaranteed 100% success But 100% plan will not be competitive today

Resolving the Dilemma Competitive, realistic plan must: –Make success of project probable (something less than 100%) –But still make it acceptable to project stakeholders Requires evaluation & negotiation of various target success probabilities leading to well- informed decision to proceed

Resource Critical Path/RCP True (resource) critical path must reflect ALL schedule constraints: resource, finance, supply, calendar, & imposed dates All constraints must be considered in both forward & backward passes

All Project Information Is Inter-related Project scope affects schedule, resources, cost, & risk On many projects this information is not truly integrated because: –Separation of responsibilities –Most PM software does not properly integrate and calculate it

Eight Integration Methods Used 1.Systematic scope definition (indentured structures) 2.Network planning 3.Resources: Consumable, renewable, utilized & produced Units, teams/crews, interchangeable units or crews Assigned to project activities Constraints in both forward & backward passes

Eight Integration Methods (Cont’d) 4.Activity durations calculated: scope or volume ÷ rate 5.True (resource) critical path calculated: Logical & schedule constraints Resource, financial & supply limitations in both the forward and backward passes

Eight Integration Methods (Cont’d) 6.Risk & uncertainties simulated: probability distribution for main project results (project & its main phases finish dates, costs, resource requirements) 7.Actuals reported & compared, contingency reserves tracked

Eight Integration Methods (Cont’d) 8.Current probabilities of success calculated and trends determined for: Schedules Costs Resources

Methods Unique to SDPM 1.Multiple breakdown structures 2.Resource information & analysis 3.Activity duration calculation or estimation 4.Resource critical path, resource floats, & resource contingency reserves 5.Risk simulation & success probability analysis 6.Success probability trends

1. Multiple Project/Work Breakdown Structures Life cycle Deliverables Physical areas Responsibilities Functional type of work Cost account Contract Others

2. Resource Information & Analysis Two types: –Consumable: materials, supplies & other expendables –Renewable: labor, equipment, facilities Units, teams, or assignment pools Norms for resource productivity May be utilized or produced

3. Activity Duration Calculation or Estimation Activity volume is estimated (any measurable units) Volume often used as initial estimate & duration calculated using resource productivity factors Uncertainties forecast by varying productivity factors

4. Resource Critical Path True critical path reflects ALL schedule constraints: –Network logic, resource, finance, supply, calendar, imposed dates Activity float must reflect ALL constraints Most PM software packages ignore resource constraints on backward pass: incorrect critical path

4. Resource Critical Path/RCP (Cont’d) Activity resource float & resource critical path reflect resource constraints during backward pass Activity resource float can be used feasibly: –Shows possible delay considering set of available resources Adding financial & supply constraints to the Critical Chain definition you then have RCP

5. Risk Simulation & Success Probability Analysis Single, deterministic estimates produce plans with low probability of success Risk simulation produces more reliable results Risk simulation may be based on Monte-Carlo approach (impossible to use for large projects) or based on 3 scenarios approach

5. Risk Simulation & Success Probability Analysis (Cont’d) 3 estimates are made for: Resource usage or productivity rates Work scope & volume Activity duration (if estimated directly) Cost estimates Calendar/weather variation

5. Risk Simulation & Success Probability Analysis (Cont’d) Identified risk events are estimated to reflect their consequences, including risk response plans in optimistic, most probable or pessimistic project scenarios. All three scenarios are calculated. The probability curves are rebuilt using the three values obtained.

5. Risk Simulation & Success Probability Analysis (Cont’d) Determine the desired probability of meeting project finish dates, costs and resource requirements Obtain desired project finish date, budget, resource requirements These data form basis for negotiating & approval to proceed

5. Risk Simulation & Success Probability Analysis (Cont’d) Negotiations may establish new targets Success probability is defined as the probability of meeting approved targets: – Dates, cost, quantity Success probability is the best indicator of current project status during execution

5. Risk Simulation & Success Probability Analysis (Cont’d) Target schedule is the backward (from the target dates) resource constrained schedule using most probable estimates The optimistic schedule is used for setting task schedules for project implementers Contingency reserves or buffers: –Difference between activity start times (or cost, material requirements) in the optimistic and target schedules

6. Success Probability Trends Success probabilities are calculated periodically & stored Their trends show current project status Negative (downward) success probability trend indicates corrective action needed Positive success probability trend indicates performance is OK

6. Success Probability Trends (Cont’d) Success probabilities change due to: –Performance results –Scope changes –Cost changes –Risk changes –Resource changes

6. Success Probability Trends (Cont’d) Project managers are encouraged to solve uncertainties ASAP –This can increase success probabilities even with activity finish delays & cost overruns Postponing problem activities leads to negative trends in success probabilities This attribute of success probability trends is especially useful in new product development project management

Illustration Software Purchase Project Our forum discussion now turns to sample project Software Purchase This project consists of 10 activities including 2 milestones and uses 3 resources Resource productivities were estimated with 30% reliability. Thus productivities in the pessimistic version were 30% lower and in the optimistic version 30% higher than in the most probable version

Illustration: Software Purchase Project Target Schedule

Illustration Software Purchase Project Let’s assume that the actual productivity of the expensive resource was 20% higher than estimated and the low cost resource worked with a 20% lower productivity than expected Let’s consider the most probable version as the baseline. The baseline cost is $66,220, Target cost (57% probability) is $70,000 Next slide shows the success probability trends if our assumptions were true

Success Probability Trends for Software Purchase Project

EVA Trends for Software Purchase Project Next slide shows Cost Performance Index/CPI & Schedule Performance Index/SPI trends for the Software Purchase project

CPI & SPI Trends for Software Purchase Project

SDPM and Earned Value Analysis SDPM success probability trends reflect performance results plus network dependencies & project risks EVA reflects only performance results In the Sample project: –SPI exceeds 100% on August 11 –But on August 11 SPDM shows the probability of meeting baseline finish date is equal to zero (next slide)

Success Probability Trends for Software Purchase Project

Earned Value Analysis EVA approach is not totally integrated EVA considers sunk costs but not: –Network logic dependencies –Project risks –Resource performance EVA problems are illustrated in the following slides for the sample project

Sample Project Gantt Chart

EVA of Sample Project If activity 3 is started first (in spite of the Gantt chart schedule) then after the first week the SPI will be 10 or 1000% But on-schedule completion will be impossible!

EVA of Sample Project ParameterValue AC100 EV100 PV10 SV90 CPI1 CPI%100 SPI10 SPI%1000

Using EVA Recommend applying EVA to critical path activities only Cannot use EVA from one project phase to forecast results of another phase if resources are different.

Common Features: SDPM & Critical Chain Method/CCM Resource critical path is the same as Critical Chain if we add financial and supply constraints to the Critical Chain definition CC “project buffer” is analogous to SDPM “contingency time reserve” “Resource float” is analogous to CC “feeding buffers” Both approaches recommend using optimistic estimates to set schedule

Differences With Critical Chain Don’t agree that “one should always avoid multi-tasking” Don’t accept CC assumptions that: –“Critical chain never changes” –Only one “project drum [critical] resource” exists Our experience: critical resources change in different project phases

Differences With Critical Chain CC more qualitative than quantitative Time & cost reserve usage evaluation: –SDPM: Success probability trends show if reserves expended faster or slower than planned; more effective than: –CC: Qualitative judgment whether buffers were properly utilized

Recommendations for Implementing SDPM Simulate uncertainties to obtain probability distributions Set desired target probabilities, then calculate requirements to meet them Use these data to negotiate realistic commitments

Recommendations for Implementing SDPM (Cont’d) Set agreed target dates & costs, calculate success probabilities Set optimistic targets for project implementers and manage calculated contingency reserves

Recommendations for Implementing SDPM (Cont’d) Control risks, revise & recalculate success probabilities reflecting progress, changes, & risk estimation updates Manage with success probability trends: –Negative trends: take corrective action regardless of current level of success probabilities

Conclusions For effective project management, truly integrated information is required: –Scope –Schedule –Resources –Cost –Risk

Conclusions (Cont’d) Truly integrated information is practical to produce Identifying the resource critical path and calculating success probability trends help to produce more successful project performance

Are These Methods Practical? Over past 10 years SDPM was successfully applied to hundreds of projects in Spider Project software automates the process Aerospace & Defense Banking Defense Engineering & Construction Manufacturing Metallurgy Oil & Gas Ship Building Software Development Telecommunications Others

Questions? As time permits now, & During the remainder of the Congress Via /Web: “Vladimir Liberzon” “Russ Archibald” Info on Spider Project package:

Thanks for Listening We appreciate your comments We look forward to further feedback and exchange