MICE news Alain Blondel 20 – 10 - 2004 1 NEWS 1.CERN’s SPSC at Villars: recommandations 2.MICE step 2.5 3.Upcoming gateway steps 4.RF from LBNL (Mike)

Slides:



Advertisements
Similar presentations
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE Funding Agencies Committee.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 26 Nov 2010 SOLID ABSORBERS Solid absorbers will provide first cooling demonstration –This is important for a number of reasons! Can use only solids.
Changing the absorbers: how does it fit in the MICE experimental programme? Besides the requirement that the amount of multiple scattering material be.
CHIPP Sept 2005Jean-Sébastien GraulichSlide 1 What is MICE  Muon Ionisation Cooling Experiment  What is Ionisation Cooling ? Cooling = Reduction of Beam.
Alain Blondel MICE: Constraints on the solenoids 2.Field Homogeneity: or ? this will be dictated by the detector requirements. TPG will be.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
24 Nov 2009PC Analysis PC Schedule 2009 Tuesdays fortnightly Proposed dates: 13 October  27 October  CM25 4 – 6 November  24 November 8 December.
K. Long, 26 June, 2015 Phase II: introduction to discussion Background (reminder) Responses Assumptions Presently planned bids Input to summary table Summary.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
MICE analysis meeting Alain Blondel 5 August MICE -- what running strategy? disclaimer: of course we will evolve the running strategy as problems.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MICE CMPB 3-Feb-2006 Alain Blondel 1 Status of MICE.
RFCC Module Tech Board Schedule Discussion Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 4, 2009.
1 Effect of staging on module connection and support arrangement Yury Ivanyushenkov RAL.
CMPB Alain Blondel 14 April STATUS OF MICE.
Alain Blondel MICE Funding Agency Committee MICE status report Most of the technical progress has been covered in the open session except the.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
MICE Video meeting Alain Blondel 7 December MICE -- what running strategy? reflections on steps I and II.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
MICE CM Alain Blondel 1   MICE GOALS OF THE MEETING Welcome to MICE CM28.
CM37 Alain Blondel step IV physics success 1 « STEP IV operations : Physics »
MICE CM15 wrap-up Alain Blondel 11 June MICE News Collaboration meeting 8-11 June 2006 at Fermilab complete review of the project. for those who.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
MICE collaboration meeting Alain Blondel 27 – Welcome to the 10th MICE collaboration meeting. 1.Global neutrino factory situation 2.Possible.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
MICE CM in New York Alain Blondel, June MICE COLLABORATION Columbia University June 2003 Action List (online) 1.Funding and some organization.
MICE CM at OSAKA Alain Blondel, August MICE collaboration meeting at OSAKA (thanks to Mike Zisman, Makoto Yoshida, and Koji Yoshimura)Mike ZismanMakoto.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be Jun at IIT and the 19th at Fermilab right before the.
1 Forces Yury Ivanyushenkov RAL. 2 Goal: find maximal (static and dynamical) possible forces in MICE magnetic system. Method: calculation of axial magnetic.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Spectrometer solenoid 2. Magnetic shielding 3. Next Collaboration meeting.
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE/UKNF Oversight Committee.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE VC Alain Blondel 30 August MICE VC 103 MICE news -- see Malcolm's news for an inventory. -- great funding news all summer from USA! (phase.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE CM16 Goals Alain Blondel 8 October MICE CM 16 Collaboration meeting 8-11 October 2006 at RAL Goals of the meeting thanks to John Cobb & Marco.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Report from MICE project teams Feedback from PPRP MICE funding: various scenarios Issues  Financial year 2003/04  iMICE common fund.
MICE VC116 Alain Blondel 18 December MICE NEWS See more details in Macolm’s MICE news!
MICE CM 29 Collaboration Board Summary. Agenda 1.Intro 2.Approval of minutesBooth/Bross 3.Spokeʼs remarks & EB reportBlondel 4.PM reportNichols 5.US magnet.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE CMPB Alain Blondel 1 Highlights on MICE.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
MICE VC Alain Blondel MICE News 9 March 2005 we did not succeed in preparing a good enough I3 proposal for EU on neutrinos. Problems were.
1 Search for Worst-Case Forces MICE Video Conference, September 8, 2004 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department,
MICE Funding Update (U.S.) Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory CMPB Meeting August 1, 2007.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
MICE – Video conference Alain Blondel, 17 December   MICE selected NEWS: Future meetings Safety review Study of controls Gateway I & Toward Gateway.
ch/~bdl/lepc/lepc.ppt 1 MICE Status and Plans Rikard Sandström Université de Geneve International Scoping Study CERN,
MICE CM30 Goals of the Meeting Alain Blondel 1 MICE CM30 – Goals and Status.
1 OPTICS OF MICE STEP V.0 Ulisse Bravar University of New Hampshire 26 June 2005.
Alain Blondel 4 April  Aspirational MICE Schedule as of April 2008 Febuary-July 2008 STEP I September 2008 November 2008 to summer 2009 STEP II.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
(one of the) Request from MPB
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
CM Nov 2009 DOES MICE NEED STEP III ? Somewhat hard to understand MICE Schedule… –If the gods are (un)kind it’s possible that SS1, SS2 & FC1 are.
MICE CM41 – CB summary Alain Blondel 1 Collaboration Board at CM41 Summary Alain Blondel.
MICE RLSR – 13Nov2013 Alain Blondel 1 MICE Project Board 14 November 2013 Alain Blondel.
MICE VC Alain Blondel, April MICE exectutive board met on 1 April 2004 after the collaboration meeting and remarked the very large amount of.
Muon Ionisation Cooling Experiment Overview
Status of the MICE Construction Project
MICE CM31 Schedule summary
Presentation transcript:

MICE news Alain Blondel 20 – NEWS 1.CERN’s SPSC at Villars: recommandations 2.MICE step Upcoming gateway steps 4.RF from LBNL (Mike) 5.Collaboration meeting (Paul) Others?

MICE news Alain Blondel 20 –

3  - STEP I: spring 2006 STEP II: summer 2006 STEP III: winter 2007 STEP IV: spring 2007 STEP V: fall 2007 STEP VI: 2008

MICE news Alain Blondel 20 –  Critical path items at the start are clearly a) the beam and b) the spectrometer solenoid (2->2.5 years after order)  Funding to get the spectrometer solenoids is difficult and causes delay. (~2 M€ a pair of rather standard technology)  the MICE management proposes to deal with this potential stumbling block, while remaining committed to ultimately achieving the full goals of MICE (“Step VI” above) by proceeding with additional intermediate steps  boundary condition: additional intermediate steps use mainly items that are part of the final MICE configuration.  The soonest we may be able to get the firstspectrometer is from US funding  This leads to the consideration of step II.V (2.5)

MICE news Alain Blondel 20 –  - STEP I STEP II STEP II.V Insert absorber (solid) between the two halves and measure Pt & E distribution and emittance growth STEP II.VI Split tracker in two parts and measure against each other (systematics) Establish beam match andwether we have all knobsnecessary to drawEmittance vs transmissioncurve. Measure emittance These are mostly questions for beam design and matching to and within solenoid.

MICE news Alain Blondel 20 –  the MICE collaboration is confident that it has enough resources to go ahead with practical measurements and achieve a first worthwhile goal.  justify our request to proceed with the implementation of the muon beam line. U.S. decision on Step 2.5 funding might be possible in about six months. Meanwhile we are actively pursuing the following alleys that should get us further letter of intent submitted to Italian funding agency to proceed towards a full proposal to INFN; (under review now) Investigations on use of MRI magnets that could be borrowed or lent from company to be used as spectro. magnets, at least temporarily. We are exploring a request to the EU funding programmes for MICE under the heading “NEST” (New and Emerging Science and Technology). If any of this materializes soon enough US funding could be redirected towards RFCC Module, maybe in a reduced version (MICE step V.0 ?) well along full MICE, since AFCC module funding (UK &Japan) is earmarked (though not released) A note on this is being prepared for discussion at the MICE collaboration board in RAL.

MICE news Alain Blondel 20 –  - STEP I STEP II STEP III STEP IV STEP V This may be too expensive…Although we do have good prospectto secure 8 MW of RF power.

MICE news Alain Blondel 20 – STEP V STEP V.0 Shorter, less expensive, no coupling coil, (very limited optics flexibility) does this work in flip, RFoFo, non flip modes? These are mostly optics questions

MICE news Alain Blondel 20 – Upcoming gateway steps -- the foreseen cost and schedule review is foreseen on November 12th Essential ingredient for this : our beautiful Technical Design Report -- gateway 2/3 will be separated for i) Beam Line and ii) MICE proper. revue for Beam line expected in late december. The discussion of step 2.5 above is quite relevant for this!