Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 12, 2016.

Slides:



Advertisements
Similar presentations
PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Advertisements

INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF ODH Discussion How to avoid ODH2 conditions? August 5, 2015.
’ tall Empty space below this metal sheet 66’ 14’ 4’ 10’ Ceiling tiles = 24 Concrete blocks 14’ long There are two “styles” of Ceiling tile,
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 31, 2015.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker October 21, 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Re-scoping UITF Matt Poelker November 14, 2015.
Current NML Layout.  Overall length of building is 72M 3 cryomodules with feed and end cans ~40M Not enough room for both photoinjector and downstream.
CEBAF Source and Injector Status PREx-II Collaboration Mtg Feb. 26, 2016 Matt Poelker and Joe Grames Center for Injectors and Sources.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker April 12, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker February 23, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Internal Personnel Safety Review UITF Overview and Introduction Matt Poelker.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
UITF Laser and Gun High Voltage John Hansknecht UITF Operational Review March 18, 2016.
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
ELENA installation progress F. Butin / ELENA collaboration.
AIP and Large Projects Arne Freyberger OPS 2015 StayTreat.
LCLS-II Technical Requirements
RF Systems and Controls for the LERF CM Tests
UITF MPS system requirements
CBETA Technical Review
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
ELENA installation and commissioning status
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
UITF – Upgrade Injector Test Facility
CEBAF Injector Update PREX/CREX March 3-4, 2017
Overview of LERF Status, Plans and Goals
XFEL Vacuum System Commissioning
Hot Checkout System for LERF Resuscitation
Jefferson Lab Low Level RF Controls
UITF Project Status Meeting
UITF Project Status Meeting
CEBAF Injector Overview
UITF Operational Review
Upgraded Injector Test Facility
Upgraded Injector Test Facility - UITF
UITF MPS system requirements
Thoughts on Energy Reach
Upgraded Injector Test Facility
Feedback Systems Joe Grames Hall A Parity Meeting Jefferson Lab
Advanced Research Electron Accelerator Laboratory
J. Seeman Assistant Director for PPA/LCLS
A. Freyberg Aug 2016 ECT’16 =>
Uses of UITF 10 MeV spin-polarized electron accelerator, beam current up to 100 uA M. Poelker December 12, 2018.
Carlos Hernandez-Garcia Don Bullard February 2, 2017
Polarized Source: Recent Activities
Installation and Beam Test Schedule
LCLS Undulator System Status and Schedule
Upgraded Injector Test Facility
LCLS Injector System Overview D. H
UITF Conduct of Operations Review
Operation of Target Safety System (TSS)
Cryomodule Test Schedule
UITF Conduct of Operations Review
Polarized 3He target installation
Presentation transcript:

Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 12, 2016

Thomas Jefferson National Accelerator Facility Page 2 UITF Progress meetingOutline Purpose: to inform Lab Leadership of the UITF status Action Items (from previous meetings) Project Update –Progress Update –Milestones Update –Budget Update –Highlights & Concerns –Next meeting agenda

Thomas Jefferson National Accelerator Facility Page 3 UITF Progress meeting Proposed re-scoping Facilities ITFPTB UITFBL ITFCRY Facilities Cryo Infrastructure including some RF Polarized Target Beamline UITF

Thomas Jefferson National Accelerator Facility Page 4 UITF Progress meeting Action Items – April 12, 2015 Minutes New Action Items: Wrap up UITFBL by October 1, 2016 Address Accelerator Division budget shortfall

Thomas Jefferson National Accelerator Facility Page 5 UITF Progress meeting Major components Facilities Engineering Mech Design Installation Cryo Safety Systems I&C DC Power Low Level RF systems High Power RF Survey & Alignment SRF Build new ¼ CM Commission with RF Ops and CASA Network and communications Software Beamline design Green means we can see progress Progress Update

Thomas Jefferson National Accelerator Facility Page 6 UITF Progress meeting Major components Source Group Reliable 200kV ops Beam to cup in front of ¼ CM Beam to cup in front of HDIce EHSQ Shielding approval, ODH assessment, Ops Review Global hazard review FSAD Accel Readiness Review Commissioning Plan HDIce Installation at Cave Beam on HDIce Progress Update Green means we can see progress

Thomas Jefferson National Accelerator Facility Page 7 UITF Progress meeting Facilities Tasks and Timeline Electric work should finish up this week Fire alarm pull station and strobe at Cave 2 - should be done this week Entry gate installation on Friday 7/15 Hall C guys filled the gap with concrete block. They are set to pressure-wash the roof planks sitting in the boneyard, installation of ceiling planks starting soon. They expect installation to take 3 days, but won't be consecutive. Planks will be installed throughout the month of July. Anchoring of roof will immediately follow roof installation After roof planks are installed, there are some miscellaneous painting jobs to perform The high roof to be installed at our discretion…

Thomas Jefferson National Accelerator Facility Page 8 UITF Progress meeting Status Facilities All (?) purchased concrete now installed Electric inside Cave2 nearly complete: outlets and lighting 480 VAC connections from emergency diesel generator nearly complete

Thomas Jefferson National Accelerator Facility Page 9 UITF Progress meeting Status Facilities Labyrinth complete, entry gate to be installed this Friday Fire suppression complete Concrete block added at the gap between new and old caves

Thomas Jefferson National Accelerator Facility Page 10 UITF Progress meeting Status Facilities Kelner and company: Pressure wash, move and install

Thomas Jefferson National Accelerator Facility Page 11 UITF Progress meeting Status Safety System Group Run/safe boxes attached to walls, annunciators ODH sensor controls and tubing (need N2 sensor) Control panel inside Control Room Done by end of August…..

Thomas Jefferson National Accelerator Facility Page 12 UITF Progress meeting Plumbing to ¼ CM complete, electronics wrapping up, and turbo pump set in place for shield line For FY17: U-tubes, finish turbo pump, HDIce warm return Status Cryo Group

Thomas Jefferson National Accelerator Facility Page 13 UITF Progress meeting Status Engineering Both magnet racks are UP and running, some current limiting resistors added to cable tray Stripline BPM parts and fixtures in house – asking SRF to weld flanges to the cans. Scott Windam hopes to have the electronics ready before October 1, Current monitoring and vacuum interface getting worked. Same for viewers and harps Work on Beam Current Monitors put on hold until FY17 (PSS and MPS)

Thomas Jefferson National Accelerator Facility Page 14 UITF Progress meeting Status RF Klystrons, waveguides and assorted components, all on top of cave – hoping RF group can put it all together soon Control modules ready, Scott Higgins working on software Chopper amps ordered, water skids can now be installed

Thomas Jefferson National Accelerator Facility Page 15 UITF Progress meeting Per discussions, the new ¼ CM will be installed at CMTF when C50-12 tests have concluded, beginning September Testing new ¼ CM at CMTF through mid-September Move to UITF at end of September Status New ¼ CM

Thomas Jefferson National Accelerator Facility Page 16 UITF Progress meeting Gun, prep chamber and adjoining beamline under vacuum, bakeout this week Waiting for BPM cans, chopper chamber, chopper chamber slit, differential pump can, insertable faraday cup and fixed dump, fixed aperture, platform supports for spectrometer magnet Need to repair two solenoid coils at chopper…. Status Gun Group

Thomas Jefferson National Accelerator Facility Page 17 UITF Progress meeting keV beamline

Thomas Jefferson National Accelerator Facility Page 18 UITF Progress meeting BLM locations Insertable Faraday CupPSS BCM Fixed Dump Insertable Faraday Cup Now on hold till FY17 MeV beamline

Thomas Jefferson National Accelerator Facility Page 19 UITF Progress meeting Status Operations Software requests are coming in: Magnets, Gun HV power supply, RF controls But many more required: viewers, video, valves, current monitoring, laser controls, etc.,

Thomas Jefferson National Accelerator Facility Page 20 UITF Progress meeting Status Reviews UITF Accelerator Review: beamline design reviewed by Ops/CASA/SRF, March 18, 2016, “Will it work?” review Geoff Krafft, Mike Spata, Reza Kazimi, Arne Freyberger, Todd Satogata, Fay Hannon Yes, it will work. Summary distributed, Bruce Lenzer helping to make the review “official” Internal Safety Review, May 10, 2016 Personnel safety, including radiation protection, and machine protection, assessment will be sent to SCMB Conduct of Operations Review, October 2016 Commissioning and Operations plans (the SCMB review) Accelerator Readiness Review, December 2016 Documentation in place, systems ready and checked out, staff trained Experimental Readiness Review, early 2017

Thomas Jefferson National Accelerator Facility Page 21 UITF Progress meeting Status Reviews Bob recommends we hold in-house mini-review of our PSS BCM system, August Results forwarded to SCMB Conduct of Operations Review, October 2016 Commissioning and Operations plans (the SCMB review) Accelerator Readiness Review, November 2016? Bob recommends not until we have 90% of MeV beamline ready… Documentation in place, systems ready and checked out, staff trained Experimental Readiness Review, early 2017

Thomas Jefferson National Accelerator Facility Page 22 UITF Progress meeting Milestones Update WBSItemMilestone DescriptionStart Date Projected Finish % Complete Days Float? Change (%) Change (Days) 1.04.xx x FacilitiesCivil work complete6-4-15August %70 to 95% GunDemonstrate gun ok at 200 kW at FEL GTS December %done CMCommission cold ¼ CM, no beam November %50 to 60% Beam from Gun to Cup in front of ¼ CM November %30 to 40% Beam thru MeV energy delivered to cup in front of HDIce ?10%0 to 10% Beam to HDIce?0 Facilities work nearly complete, followed shortly thereafter by Safety System Group keV beamline complete by October, followed by controls New ¼ CM installed inside cave by October 1

Thomas Jefferson National Accelerator Facility Page 23 UITF Progress meeting Budget ITFCRY – account closed Donate ~ 100k$ to Accel

Thomas Jefferson National Accelerator Facility Page 24 UITF Progress meeting Budget ITFPTB – account closed Donate ~ 100k$ to Accel

Thomas Jefferson National Accelerator Facility Page 25 UITF Progress meeting Budget UITFBL

Thomas Jefferson National Accelerator Facility Page 26 UITF Progress meeting Budget UITFBL Postpone BCM work: SRF, I&C and SSG (look for spare cavities in-house)

Thomas Jefferson National Accelerator Facility Page 27 UITF Progress meeting Budget UITFBL – in the time remaining Finish keV machine shop jobs Finish SSG Work – PSS and ODH Build the keV beamline Build the drive laser and optic transport line Install the ¼ CM inside Cave1 Hope I&C can find time to stuff electronics racks RF Group – controls, MO installation, water skids Ops Software

Thomas Jefferson National Accelerator Facility Page 28 UITF Progress meeting How to wrap up UITFBL UITFBL ETC machine shop40 LaborPWcost per week RF group I&C10330 SSG Ops Software CIS

Thomas Jefferson National Accelerator Facility Page 29 UITF Progress meetingSummary Wrapping up FY16 and into 1 st quarter FY17 Facilities work complete PSS/ODH systems fully functional By October 2016, keV beamline complete and the new ¼ CM in place and connected to the keV beamline, but NOT connected to CTF We have some RF with epics control, and racks hold enough functioning I&C electronics with necessary software, to start putting beam on viewers Cryo finishes work, high power RF work complete, we test the cold ¼ CM and reach similar gradients observed at CMTF MeV beamline design has resumed….

Thomas Jefferson National Accelerator Facility Page 30 UITF Progress meetingSummary When Can HDIce expect beam? CTF: still no final word on scheduling. The CTF down lasts four months. The soonest this work might happen is during the winter break of Imagine start January 2017 through April 2017 CTF down provides time to finish the MeV beamline design and build it Accelerator Readiness Review Making MeV beam May HDIce beam tests Summer

Thomas Jefferson National Accelerator Facility Page 31 UITF Progress meetingSummary Hope Cryo and MeV beamline design work can resume October 1 At least 3 month delay, maybe more (e.g., after the 80/20 girder is designed, we still need to order it) We can make keV beam and deliver it to cup in front of ¼ CM during Fall 2016 Hope we can commission the ¼ CM with RF before CTF shutdown Going to focus on PSS BCM mini-review and the Conduct of Operations review. Hold off on Accelerator Readiness review until we have MeV beamline Preparing budget estimates for FY17

Thomas Jefferson National Accelerator Facility Page 32 UITF Progress meeting Backup Slides Backup slides from past meetings, P&C meetings

Thomas Jefferson National Accelerator Facility Page 33 UITF Progress meeting Budget UITFBL I don’t understand this plot…

Thomas Jefferson National Accelerator Facility Page 34 UITF Progress meeting ¼ Cryomodule in Cave 1 ODH Concern Mitigation – Cave 1 Vent stacks installed 7’ tall located over two rectangular penetrations

Thomas Jefferson National Accelerator Facility Page 35 UITF Progress meeting Status HDIce HDIce Issues What does beamline downstream of HDIce look like? Raster (we seem ok with what is available) Seeing < 1nA beam (want to get RF guys working on this now) Build a “beam good” FSD node (one of our BLMs) Another BCM, like PSS BCM, near the target Where to put HDIce electronics? (Cave2 with network connection) Energy spread, slits in chicane to reduce energy spread? Accuracy of GEANT model 500 L dewar, ordering it with manifold to capture boil off

Thomas Jefferson National Accelerator Facility Page 36 UITF Progress meeting PSS BCM Insertable Faraday Cup PSS BCM Can resolve ~ 1nA

Thomas Jefferson National Accelerator Facility Page 37 UITF Progress meeting To refresh your memory… What we started with… UITF as imagined

Thomas Jefferson National Accelerator Facility Page 38 UITF Progress meeting Design work was stopped…would like it to continue

Thomas Jefferson National Accelerator Facility Page 39 UITF Progress meeting Status HDIce Lots of scattering at MeV energy. Beam size very large at target. Decided to flip the orientation of the target Cave2 design seems fine either way, need a Physics designer to be responsible for installation at UITF Target here Upstream radiation baffle blows up beam In this configuration, we can achieve desired small beam size at target Target here, better e-beam

Thomas Jefferson National Accelerator Facility Page 40 UITF Progress meeting

Thomas Jefferson National Accelerator Facility Page 41 UITF Progress meeting Combine the two features that provided incremental success: shed and doped insulator Next test late September

Thomas Jefferson National Accelerator Facility Page 42 UITF Progress meeting The new gun happy at 325 kV, stopping at this voltage for now. Shifting focus to building the beamline and photocathode deposition chamber (LDRD magnetized beam tests) Building the electron gun at LERF GTS

Thomas Jefferson National Accelerator Facility Page 43 UITF Progress meeting Gun and Beamline at GTS

Thomas Jefferson National Accelerator Facility Page 44 UITF Progress meeting Status HDIce Stripline BPMs see 7nA beam with 1 Hz integration time. But we want to see 1nA beam, or even less at UITF. Don’t want to fly blind

Thomas Jefferson National Accelerator Facility Page 45 UITF Progress meeting Status HDIce Need to work out details with HDIce and T. Allison, J. Musson I peak I baseline Acceptable duration of high peak current: long enough to see but not long enough to depolarize

Thomas Jefferson National Accelerator Facility Page 46 UITF Progress meeting Schedule Ramifications Commission ¼ CM (no beam), scheduled for Feb 2016 Electric/FM – ($78k + $23k for com. conduit) 101 k$ Control room – - SRF checkout of ¼ CM present condition – - Low Level RF – 16 k$ High Power RF – 25 k$ Network controls – 33 k$ Software control of RF – - adequate shielding (Cave2 with a roof) – - Cryo – (controls and pipe) 68 +/- k$ Installation group 9 k$ ODH - SSG 2 k$ EHS&Q approvals… - Total 254 k$

Thomas Jefferson National Accelerator Facility Page 47 UITF Progress meeting Klystrons and Max UITF Beam Energy Curt, With 40uA beam current only, you can run at 8MV/m with less than 3kW from klystron. But you need a stub tuner to tune the FPC coupling Qext from the design value of 9e6 to 2e7. Haipeng Haipeng, So the take away is that with 40uA and a 5 kW klystron, we can expect the 7 cell cavity to operate at 8 MV/m. Assuming microphonic detuning is in the 15 Hz range. Curt Matt, For the new ¼ CM, we will get a 5 kW tube for the 7 cell cavity. For the two cell maybe one that does 3-4 kW which should be ok. Then expect 200 kV from the gun, the two cell gives 1-2 MV, add the 5.6 MV from 7-cell and voila, we are close to 8 MeV... Curt

Thomas Jefferson National Accelerator Facility Page 48 UITF Progress meeting Cryo, SRF, RF, Software and new 1/4 CM Continuing to appreciate the interface between groups: cryo controls, SRF design features, the relief system, RF and I&C groups re: MPS, software Software, getting started… How to cool HDIce? Will use dewars for first tests ODH assessment complete, sent to Dave Kashy for review, will need SRF to add pipe to vent relief valves, will need chimney stacks at two Cave1 penetrations

Thomas Jefferson National Accelerator Facility Page 49 UITF Progress meeting 1.Protect the ¼ CM 2.Protect against beam loss and burn-through, maintain UHV 3.Protect viewers (this is a software interlock – Not FSD) 4.Protect magnets, ensure proper field for beam transport: comparator interlock, water flow or klixon interlocks 5.Protect RF beamline components: vacuum and water flow interlocks 6.Protect cups, apertures and dumps: water flow interlocks 7.Protect HDIce (mostly, this means putting the beam where it is supposed to go, protect against mis-steered beam) UITF MPS – what will it protect?

Thomas Jefferson National Accelerator Facility Page 50 UITF Progress meeting Hardware configuration 1.Valves OPEN only when vacuum good 2.Current limiting resistors in series with magnets 3.Water flow interlocks at cups, dumps and apertures 4.Window comparators on dipoles and gun HV 5.Viewers inserted only when laser in pulsed-mode 6.Water flow interlocks at buncher and chopper cavities, RF can be applied to chopper and buncher only when vacuum reads “good” 7.Helium liquid level interlocked to klystron high power RF

Thomas Jefferson National Accelerator Facility Page 51 UITF Progress meeting FSD Input Signals 1.An FSD trip will shutter laser and sometimes close all valves 2.BLMs will shutter laser: CEBAF-style BLM modules (x2) 3.LLRF control boards with CEBAF-style FSD signals 4.Vacuum FSD signals from ¼ CM. Helium liquid level interlocked to klystron control panel 5.All beamline ion pumps ganged together, close laser shutter and close all pneumatic valves when pressure exceeds a setpoint 6.Window comparators using 16 bit ADC cards designed by EES 7.HDice “off target” detector (qty 1, suspect it will look like a BLM)

Thomas Jefferson National Accelerator Facility Page 52 UITF Progress meeting Similar to CEBAF 1.SSG BLM chassis, x2 units 2.New LLRF control boards 3.Cryo and SRF signals from ¼ CM 4.Window comparators using 16 bit ADC cards designed by EES 5.FSD signals summed using VME boards with 12 input channels each 6.FSD signals transmitted via fiber at 5 MHz 7.SCAM to create low duty factor modes 8.CEBAF style pockel cell tune mode generator: RTP cell with <250ns response time, backed by shutter that closes 5-10ms later