NPRR784 Mitigated Offer Caps for RMR Units Protocol Revision Subcommittee June 16, 2016 1.

Slides:



Advertisements
Similar presentations
Ancillary Services and SCED Jeff Gilbertson Market Analyst Congestion Management Working Group 9/4/2013.
Advertisements

SCED Power Balance Penalty Curve
Unresolved Issues in NPRR 555 Texas Steel Companies July 9, 2013.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
John Dumas Director of Wholesale Market Operations ERCOT Operating Reserve Demand Curve.
ERCOT RMR Deployment and Cost Proposals By: Matt Mereness and Ino Gonzalez.
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
May 29, 2014 Technical Advisory Committee (TAC) Update to RMS Kathy Scott June 3, 2014 TAC Update to RMS 1.
32853 Evaluation of Demand-Response Programs in the Competitive Electric Market Workshop 1 September 15, 2006 Shawnee Claiborn-Pinto.
Real Time Mitigation During Exceptional Fuel Cost Events.
July 30, 2015 TAC Meeting Update to COPS Michelle Trenary August 12, 2015.
Guidelines for Verification of Resource Specific Fuel Adders RCWG Paul Vinson.
Market Mitigation Concept Group Update Jim Galvin April 26, 2004.
April, 2008 Maximum Shadow Price. April, 2008 Protocol Requirement: Transmission Constraint Management (2)ERCOT shall establish a maximum Shadow.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee August 7, 2008.
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
January 21, 2010 Security Constrained Economic Dispatch Resmi Surendran.
RCWG Update to WMS December 5, General Update Agenda Items for Today: Verifiable Cost Manual clarifications (vote) White Paper on Long Term Fuel.
QMWG – Feb. 26, 2014 Discussion topic: NPRR585 Clarification of Administrative Pricing Requirements for Self-Committed Combined Cycle Combustion Turbines.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
RCWG Update to WMS May 6, Real-Time Mitigation During Exceptional Fuel Events Option 3 – Increase MOC’s during Cold Weather Events When ERCOT.
CMWG Update to WMS Report of CMWG Meeting of M Wagner Edison Mission Marketing & Trading.
1 Reliability Deployment Task Force (RDTF Meeting) December 20 th 2011 December 20, 2011.
Resource Adequacy Task Force (RATF) Update to WMS June 12, 2013.
Competitive Constraints/ Protocols 3.19 Presented to CMWG 10/14/2011 Steve Reedy, Manager, CRR.
Unit-Specific Bid Limits based on Modified Generic Cost.
CMWG Update to WMS Report of CMWG Meetings of &
NPRRs 663NPRR Ancillary Service Insufficiency Actions. This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient.
Wholesale Market Subcommittee Update May 2 nd, 2013 Technical Advisory Committee.
Floyd Trefny, P.E. Director of Wholesale Market Design Nodal Market Tools to Manage Wind Generation January 29, 2009 Presentation to the Renewables Technology.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management May 19, 2011.
Protocol Revision Subcommittee Tom Burke September 7, 2012.
CMWG NATF 11/02/2010- CCT/DME update + Outages in the CRR Model follow-up Steve Reedy – Market Design and Analysis 1.
WMS Meeting, October 10, RCWG Continuing Efforts  NPRR 747 Price Correction No consensus on this issue  RCWG needs additional guidance on the.
Business Case NPRR 351 Floyd Trefny Amtec Consulting Brenda Crockett Champion Energy Services.
Harika Basaran 11/05/2014 TAC October 23, 2014 Meeting Update to Commercial Operations Subcommittee.
Commercial Operations Subcommittee Meeting April 13, 2010 Update to RMS April 14, 2010.
NPRRs NPRR649 Lost Opportunity Payments for HDL Manual Overrides. This Nodal Protocol Revision Request (NPRR) proposes two options for a lost opportunity.
1/07/2014 QMWG – RUC and AS update QMWG – ERCOT Update ERCOT Market Analysis.
Joint PLWG/CMWG Assignment Update to ROS September 15, 2011.
NPRR 649 Addressing Issues Surrounding High Dispatch Limit (HDL) Overrides Katie Coleman for Air Liquide (Industrial Consumer) ERCOT Board February 9,
December 2010 Wholesale Market Subcommittee Report to Technical Advisory Committee.
ERCOT Update on Day-Ahead Extract and other PUCT Posting changes DEWG Meeting 10/29/07 Matt Mereness.
Reliability Deployments Task Force Update WMS Meeting WMS Chair created task force with the directive that the task force will address real-time.
RDTF June 1, Purpose “The effect of the Shadow Price cap for the Power Balance Constraint is to limit the cost calculated by the SCED optimization.
NPRR 520 Resmi Surendran ERCOT. Current CCT Process Annual CCT (ACCT) is run every year to feed the results to Monthly CCT (MCCT) MCCT is run every month.
RCWG Update to WMS March 7, Draft NPRR, Caps and Floors for Energy Storage Resources Chair of ETWG gave high level overview ERCOT had questions.
Utilization of Fuel Costs in Ercot Markets Ino González RCWG Meeting 2/24/2016.
Technical Advisory Committee Presentation to the ERCOT Board of Directors July 15, 2008.
July 15, 2011 Reliability Deployments Task Force Meeting ERCOT Studies and Proposal on Reliability Energy Pricing John Dumas Director Wholesale Market.
Proposal for Consideration Regarding Holistic Solution to Congestion Irresolvable in SCED Issue:How do you identify when constraint is irresolvable Proposal:Adopt.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
Protocol Revision Subcommittee Presentation to the ERCOT Technical Advisory Committee May 7, 2009.
Valley Import Constraint Resmi Surendran. Valley Import Constraint Range of SFs – to in valley area – 0.03 to outside valley area Not.
Reliability Must Run Resources for Summer Slide 2 RMR for Summer 2011 RMR Contracts for Mothballed Units ERCOT has signed RMR Agreements with two.
Use of ONTEST Resource Status over Telemetry: – ERCOT protocol permits the use of telemetered Resource Status code “ONTEST” during periods of start-up.
ERCOT Market Education Market Role in Emergency Operations OTS 2016.
TAC Rejection of NPRR Mitigated Offer Caps for RMR Units
Protocol Revision Subcommittee
Exceptional Fuel Costs in LMP
NPRR833 Workshop: Contingency Processing in CRR, DAM and SCED
NPRRs 815NPRR Revise the Limitation of Load Resources Providing Responsive Reserve (RRS) Service.  This Nodal Protocol Revision Request (NPRR) revises.
RTDF Overview of Data Analysis & Status of “Consesus Items”
PRS Rejection of NPRR Mitigated Offer Caps for RMR Units
Principles of Participation in Real-Time Co-optimization
Resource Cost Working Group
A Midsummer Night’s DREAM
Interpreting DREAM NPRR 777.
Paul Wattles, Sai Moorty ERCOT Market Design & Development
Presentation transcript:

NPRR784 Mitigated Offer Caps for RMR Units Protocol Revision Subcommittee June 16,

Motivation for NPRR784 Limit the ability for out-of-market units to interfere with market outcomes. – Current rules will cause SCED to dispatch RMR Units before other units in the market during congestion. – NPRR784 will allow SCED to dispatch RMR Units after other capacity available for transmission congestion relief has been utilized. Lower RMR uplift costs to loads. – Placing RMR Units farther back in the SCED dispatch order will reduce dispatch frequency lowering RMR energy costs and maintenance costs. Improve the integrity of price formation when RMR Units are required to resolve congestion. – PUCT, IMM, ERCOT Board, and Stakeholders have recognized the crucial need to “get prices right” in the energy-only market. 2

Design of NPRR784 The language in NPRR784 was constructed to provide a flexible process that ERCOT can implement manually at little to no cost. – During congestion, SCED’s dispatchable offer price range for each unit is based on the unit’s shift factor and the shadow price cap. – Shift factors used in SCED will fluctuate frequently. – NPRR784 allows ERCOT to choose a conservative (i.e. low) shift factor and, with consideration of the prevailing shadow price cap, set a conservative Mitigated Offer Cap (MOC) for the RMR Unit. Well below the SWCAP of $9,000/MWh. – Establishing a MOC for RMR Units using this process will position them farther back in the SCED dispatch order and limit displacement of market resources while minimizing further RMR cost. Under NPRR784, the MOC for GBY5 is expected to be set to a value between $500/MWh and $700/MWh most of the time. – If adjustment is required, it will be lower. NPRR784 provides ERCOT the flexibility to raise it back to the higher level if appropriate. Fully transparent to market participants. – ERCOT will issue a market notice to communicate the initial value of the RMR MOC and any subsequent changes. 3

Other Considerations Why is NPRR784 appropriate? – Offer mitigation is applied to units associated with a QSE that can exert local market power. i.e. Fails Constraint Competitiveness Test and QSE is the Decision Making Entity (DME). – However, ERCOT controls the offering, commitment, and operation of RMR Units, not the QSE. ERCOT is really the DME for RMR Units, but not feasible to implement. No ability for QSEs to set or modify offer curves for RMR Units. Local market power will be mitigated through RUC and CCT. – Non-RMR Units controlled by QSEs will be committed through RUC and then mitigated. – NPRR784 sends a more appropriate price signal when RMR Units are needed to manage congestion. A more appropriate price signal incentivizes supply response to help resolve congestion. Continual evolution in ERCOT market design to “get the price right”. Essential for this market to succeed. Pricing during congestion just as important as system wide scarcity pricing. – See Irresolvable Constraint pricing mechanism. Responsive to concerns raised by the Board on June 14 th. – Need for better “localized price signals”. 4