Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September 2015 1.

Slides:



Advertisements
Similar presentations
WTO, Trade and Environment Division
Advertisements

A Joint Code of Practice Objectives and Summary Presentation
IAEA International Atomic Energy Agency Responsibility for Radiation Safety Day 8 – Lecture 4.
ICAO Provisions for Safety Management
John Zammit-Haber National Grid
ISO 9001 Interpretation : Exclusions
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.7 Commissioning Geoff Vaughan University of Central.
Regulatory Body MODIFIED Day 8 – Lecture 3.
Office of Business Development Training
World Class Minerals and Energy sectors for the benefit of all Overview of the Electricity Regulation Bill.
PROPOSALS THE REVIEW OF THE 1958 AGREEMENT AND THE INTRODUCTION OF INTERNATIONAL WHOLE VEHICLE TYPE APPROVAL (IWVTA) IWVTA Informal Group WP th Session.
S3: Module D Physikalisch-Technische Bundesanstalt Session 3: Conformity Assessment Module D Peter Ulbig, Harry Stolz Belgrade, 31 October.
WPD Connections Overview
Compliance with the WTO Technical Barriers to Trade Agreement and Steps Toward Developing Good Regulatory Practices Bryan O’Byrne Trade Compliance Center.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Local Assessment of Code of Conduct Complaints. 2 Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due.
© 2011 Underwriters Laboratories Inc. All rights reserved. This document may not be reproduced or distributed without authorization. ASSET Safety Management.
1 Workshop on the Directive 96/61/EC concerning (IPPC) Integrated pollution prevention and control INFRA Public participation & access to environmental.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.1 Steps in the Licensing Process Geoff Vaughan University.
Prime Responsibility for Radiation Safety
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Regulatory Authority.
IAEA International Atomic Energy Agency School of Drafting Regulations – November 2014 Government and Regulatory Body Functions and Responsibilities IAEA.
Grid Operations Centre LCG SLAs and Site Audits Trevor Daniels, John Gordon GDB 8 Mar 2004.
Specific Safety Requirements on Safety Assessment and Safety Cases for Predisposal Management of Radioactive Waste – GSR Part 5.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
Authorization Part III. Content of a license Structure of a license General elements General and specific conditions Annexes Documents attached (e.g.
 Contract by Public Authority for provision of asset and/or services  With private entity  Private finance used to fund asset/service  Long-term in.
Establishing the Independent System & Market Operator. (ISMO) 30 January 2013.
The New Legislative Framework
Milestones for Nuclear Power Infrastructure Development Establishment of A Regulatory Framework Gustavo Caruso, Section Head, Regulatory Activities Section.
Contestability for Distribution Connections 26 th January 2016.
Contestability Working Group Consultation Report and Recommendations NIE Networks / SONI Joint Presentation 26 January 2016.
ISO 9001:2015 Subject: Quality Management System Clause 8 - Operation
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
BIDDER’S CONFERENCE: Eskom Grid Connection Process and related matters Date: 16 August 2012.
Technology Services – National Institute of Standards and Technology Conformity Assessment ANSI-HSSP Workshop Emergency Communications December 2, 2004.
ROMANIA NATIONAL NATURAL GAS REGULATORY AUTHORITY Public Service Obligations in Romanian Gas Sector Ligia Medrea General Manager – Authorizing, Licensing,
AEMCPresentation to GWCFPAGE 1 AEMC and Rule changes Presentation to AEMO Gas Wholesale Consultative Forum Kamlesh Khelawan Director This presentation.
Getting a Grid Connection to Export Power Energy in Agriculture rd August 2016.
Power of choice – embedded networks information session
GC0104 – Demand Connection Code (DCC)
process and procedures for assessments
ISO/IEC
Administration of a FIDIC Contract - Project Control
2016 IPWEAvic Public Works Conference
After the FCC Form 471 E-rate Program Applicant Training
INTERCONNECTION GUIDELINES
PREPARATION FOR GMP INSPECTION
EPA SUBCONTRACT TEMPLATE Overview September 2017
Overview of the Electricity Regulation Bill
Letter of Intent process 24th November 2017
Overview of the Electricity Regulation Bill
Temporary Works Co-ordination
Outcome TFCS-11// February Washington DC
Outcome TFCS-11// February Washington DC
GMP Inspection Process
Market Trials ChMC 8th August 2018.
Communication and Consultation with Interested Parties by the RB
GDPR – Practical Implementation Managing contracts, procurement and relationships with suppliers Terry Brewer Chief Executive.
Nick Bonvoisin Secretary to the Convention on the
Regulatory Oversight of HOF in Finland
IMPLEMENTATION OF THE SOUTH AFRICAN LANGUAGE PRACTITIONERS COUNCIL ACT, 2014 (Act No. 8 of 2014) PRESENTED TO THE SELECT COMMITTEE ON EDUCATION & RECREATION.
Institutional changes The role of Bilateral Oversight Boards
Operationalizing Export Certification and Regionalization Programmes
Approach to Market Cutover - Draft for Discussion
Open Letter - Summary of Responses
Overview of the recommendations on software updates
Informal document GRE-80-0X
Presentation transcript:

Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September

Agenda  Guidelines Document  Scope of Contestability and contestability interfaces  Application and offer process  Connection Process  Accreditation  Shared Connections  Clusters  Governance/Disputes  Next Steps 2

Guidelines Document  Joint document covering transmission and distribution connections  Drafting reflects contestability as it will be  The document will be non-contractual  All contractual matters need to be addressed in other documents  Existing documents will need amending and new ones will be required  The intention is the document will be updated as contestability evolves 3

Scope of Contestability (1)  Contestability is available to connections at the following stages:  Applicants who have received an offer but not yet accepted  Applicants who have accepted an offer but works (pre-construction or construction) have not yet started  This approach is to facilitate the introduction of Contestability for all applicants  Contestability will be introduced in two phases:  Phase 1 is contestability for connections of 5MW and above  Phase 2 is contestability for all other connections  NIE/SONI are doing everything we can to facilitate implementation of Phase 1 in as short a timeframe as possible and are in discussions with UR regarding implementation dates 4

Scope of Contestability (2)  System protection is non-contestable, however  User specific protection equipment can be designed and installed independently but the protection design needs to be reviewed by the Licensee to ensure compatibility.  Certain elements of protection equipment may need to be manufacturer specific.  Metering is non-contestable  NIE will continue to purchase, install and calibrate meters and be the meter registrant.  Communication via SCADA is non-contestable  NIE/SONI will continue to purchase, install, test and maintain the communications equipment.  This will include any UPS, RTU, cable termination cabinet etc. that may be required. 5

Contestability Interfaces 6

Scope of Contestability (3)  Pre-commissioning  The applicant shall be responsible for all pre-commissioning of the contested works.  Pre-commissioning is the testing of the Contestable Works carried out prior to and in readiness for energisation and commissioning.  NIE and SONI shall be given the opportunity to witness pre- commissioning tests.  The applicant shall provide certification to the Licensees detailing all pre-commissioning tests and along with a statement of compliance with relevant technical specifications and standards.  Commissioning  The commissioning of contestable assets, including final testing and energisation, is non-contestable to ensure safety, system security and reliability. The Licensees will specify the testing programme and any user assistance required. Note – Distribution Code and Grid Code requirements also apply. 7

Application and Offer Process  Connection application does not require any contestability information.  Licensee will provide an offer which sets out details of the Connection Works and Reinforcement Works required for the new connection.  Customer shall inform the Licensee at this stage if the Connection Works will be shared with any other party.  Initial offer will not be split into contestable and non-contestable works.  Customer shall notify Licensee at the time of offer acceptance if an additional offer is required.  Additional offer will be split into Contestable Works and Non- Contestable Works.  Customer can then choose to accept the offer for the non-contestable works which would supersede the acceptance of the first offer.  Timelines will be defined for the second offer – for provision and acceptance  Licensees unsure of the uptake of contestability and hold the view that it would be inefficient to provide contestable offers where not required 8

Connection process  Level of surveillance and monitoring during pre-construction and construction is still under consideration.  We envisage the development of a quality plan early in the process, subject to review and agreement.  The plan will contain details on:  All inspection and review points  Liaison during pre-construction and construction  Documentation requirements  Certification requirements  Type test, routine tests, etc. 9

Accreditation  The draft guidelines proposes that ICPs must hold relevant accreditation for specific activities undertaken under the National Electricity Registration Scheme (NERS) Operated by Lloyd’s Register.  Where the contestable works have been installed by an ICP then failure to operate under the NERS may affect commissioning and adoption of the assets by the Licensee. 10

Shared connections (1)  Shared assets can only be delivered contestably where there is agreement between parties sharing the assets to appoint a Lead Developer to contest the shared Contestable Works.  Lead Developer is:  The Single Point of Contact for the delivery of shared Contestable Works.  Responsible for all shared Contestable Works and bears any risk.  Unique connection assets:  Lead Developer can contest its own unique connections.  The other parties’ unique connections can either be contested by the individual applicants or, following agreement between the party and the Lead Developer, by the Lead Developer. 11

Shared connections (2) 12

Clusters (1)  Cluster infrastructure  Transmission and distribution assets that are shared by all parties connecting to the cluster i.e. the cluster transmission infrastructure from the point of connection to the Transmission System to the 33kV switchboard in the cluster substation.  The TSO will inform the DNO of the connection works required for the cluster infrastructure.  The DNO offers to individual parties will contain this information.  Following acceptance of offers the parties decide whether or not to contest :  Shared cluster infrastructure (joint decision)  Unique connections 13

Clusters (2) 14

Clusters (3)  Cluster infrastructure consists of pre-construction works and construction works.  Cluster Pre-construction works  Route and site selection, land acquisition, planning permission, wayleaves and consents, normally the responsibility of the TSO.  Non-contestable – sole responsibility of the TSO in all cases.  NI customer base contributions are permitted.  Cluster Construction works  Detailed design, procurement and build, normally the responsibility of the TAO.  Contestable.  If contested NI customer base contributions are not permitted.  If not contested NI customer base contributions are permitted. 15

Clusters (4)  Contesting cluster infrastructure (construction only):  Lead Developer concept applies.  Based on the premise that all parties sharing the cluster infrastructure are contracted applicants (have an accepted offer).  NI customer base contributions are not permitted.  Not contesting cluster infrastructure:  TAO will deliver the construction works.  NI customer base contributions are permitted.  Contesting unique connection:  Party themselves can deliver or the Lead Developer.  Not Contesting unique connection:  DNO will deliver. 16

Governance/Disputes  Guidelines document is not a contractual document – it is essentially a user’s guide.  Licensees do not consider it appropriate to develop governance arrangements for this document.  It provides information on contestability arrangements defined in other documents such as connection offer letters, adoption agreements and charging statements.  Disputes  Licensees acknowledge that disputes may arise with regard to contestability but there are existing legislative and regulatory processes for the resolution of disputes with regard to the terms of a connection offer and that these existing processes should be adequate for dealing with disputes about the terms of a contestable connection offer. 17

Next Steps  Licensees aiming to complete the document and have it available for publishing and consultation by the end of September  Expected four week consultation period  Consultation report and recommendations around mid to end November? 18