PORT OF TACOMA Lincoln Avenue Grade Separation Lincoln Avenue Improvements Project Update
PORT OF TACOMA Eliminate conflicts between rail and vehicular traffic at four at-grade rail crossings along Lincoln Avenue. Allow for free and unimpeded traffic flow along Lincoln Avenue. Improve efficiency of rail service to the Port’s North and South Intermodal Yards. Objective Lincoln Avenue Improvements
PORT OF TACOMA Site grading and roadway preparation. Storm drainage, water and lighting improvements. Drilled shafts and stone column installations. Street improvements including reinforced concrete and asphalt concrete roadways, sidewalks, ramps, driveways and curbs. Bridge improvements including lightweight geofoam blocks, concrete superstructure and sheet pile wall. Traffic control devices including signals, striping, pavement markers, stop bars, and signage. Scope of Work Lincoln Avenue Improvements
PORT OF TACOMA Sheet Pile Cap Installation
PORT OF TACOMA Geofoam Block Installation
PORT OF TACOMA Cutting Geofoam Block
PORT OF TACOMA Cutting Geofoam Block
PORT OF TACOMA Completed Geofoam Fill
PORT OF TACOMA Plastic Membrane Over Geofoam
PORT OF TACOMA Bridge Deck Construction
PORT OF TACOMA Lincoln Avenue Paving
PORT OF TACOMA Lincoln Avenue Rail Crossing
PORT OF TACOMA ItemEstimated Cost Cost to DateCost Remaining Original Contract Amount$21,834,133$13,031,430$8,728,909 (6) Change Orders (.34%)$73,794 WSST (9.3%)$24,514$24,270$244 Total Contract Amount$21,858,647$13,129,494$8,729,153 Contract Cost Summary Lincoln Avenue Improvements
PORT OF TACOMA ItemBudget Estimate Cost to DateEstimate to Complete Construction (Scarsella Brothers, Inc.) $21,858,647$13,184,448$8,729,153 Consultant Construction Support Services $3,138,100$898,124$2,239,976 Port Staff $1,149,040$673,059$475,981 City Inspection $339,518$51,601$287,917 Testing & Special Inspection $300,000$118,397$181,603 LRI Disposal $486,920$383,150$103,770 WSDOT Inspection & Testing $140,000$30,401$109,599 Other $2,416,478$163,298$2, Total Contract Amount$29,828,703$15,502,478$14,326,225 Project Cost Summary Lincoln Avenue Improvements *Other includes contingency and misc charges.
PORT OF TACOMA Project Schedule Lincoln Avenue Improvements Anticipated Completion Date: May 2011
PORT OF TACOMA Issues Lincoln Avenue Improvements Encountering contaminated water and soils Managing traffic control Managing stormwater pollution