E Huedem, June 5 20081 RDR PROCESS WATER & VALUE ENGINEERING ITEMS June 5, 2008 GDE Meeting-ILC CFS Workshop in Dubna, Russia Emil Huedem, Fermilab.

Slides:



Advertisements
Similar presentations
Nov. 17, 2008 ILC08 Global Design Effort 1 Americas KlyCluster Cost Analysis Overview Tom Lackowski RF & Sum reported by Peter H. Garbincius.
Advertisements

11/27/2007ILC Power and Cooling VM Workshop Mike Neubauer 1 RF Power and Cooling Requirements Overview from “Main Linac Power and Cooling Information”
Nov. 07 DR-KOM-CFS 1 Damping Rings KOM Conventional Facility & Siting Overview Tom Lackowski Acknowledgment: Atsushi Enomoto, Jean-Luc Baldy, John Osborne,
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Homework of HLRF 1 Shigeki Fukuda KEK 2012/4/23 HLRF Homework1 in KILC12 (Fukuda) 1.
November 17, 2008 ILC08 HVAC and VE Update November 17, 2008 ILC CFS Workshop 2008 Chicago Lee Hammond, Fermilab Global Design Effort.
Energy Valve Delta T Manager
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
1 ILC Mechanical & Electrical Review Conventional MECHANICAL System Design Summary Emil Huedem, FNAL Lee Hammond, FNAL Parsons Mechanical Team (Tim Sheehan,
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
1 HVAC OVERVIEW and VALUE ENGINEERING ITEMS August 13, 2008 CLIC Working Group CES Lee Hammond, Fermilab.
Value Engineering Session Air Treatment / HVAC November 27, 2007 Lee Hammond, FNAL CFS.
Central Region Discussion Power and Cooling GDE Beijing-CFS.
31, May 2007 ILC DESY 07 1 Surface Building Design Development Tom Lackowski GDE.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
Chilled water Meyrin consolidation Study 1 st Part Many thanks for their contribution to: Pasquale Alemanno, Fortunato Candito, Alexander Putzu.
E Huedem, Nov ILC VALUE ENGINEERING SESSION of POWER & COOLING (Focus on Main Shaft 7) November 27, 2007 INFORMATION PHASE Conventional.
1 Process Water and Air Treatment 01 June 2007 Emil Huedem, Maurice Ball, Lee Hammond Fermilab.
ILC Energy Efficiency Marc Ross and Ewan Paterson, SLAC CFS-ADI Joint Meeting ICEPP University of Tokyo 9 April 2014 Three examples: 1) higher quality.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
Global Design Effort - CFS LCWS CONVENTIONAL FACILITIES AND SITING GROUP Parallel Session Overview A. Enomoto, V. Kuchler, J. Osborne.
BDS Magnet-Power System-Facility Optimization1 ILC BDS Kickoff Meeting Basis for Magnet, Power System and Cooling Facility Optimization Discussion Paul.
November 2004 Low Hanging Fruit Low Cost Energy Efficiency Opportunities in Cleanrooms.
1 Global Design Effort TILC08 - WG1 Summary WG-1: Cost Reduction Studies J. Carwardine, T. Shidara, N. Walker (For WG-1 participants)
SLAC_OCT07 BDS-KOM-CFS 1 Beam Delivery System & Interaction Region KOM Conventional Facility & Siting Overview Fred Asiri/SLAC Acknowledgment: Atsushi.
Global Design Effort1 September 20-22, 2006 MAC Review Power and Water breakout (mixed results) Marc Ross GDE.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
ILC BDS Kickoff Meeting Magnet Power Supplies RDR Concepts and Completeness Paul Bellomo SLAC Power Conversion Department October, 2007.
Summary of TDR Cost Reviews at KILC-12 G. Dugan KILC-12 4/26/12.
Global Design Effort - CFS TILC08 Working Group 1 - March 5, CFS Cost Reductions Conventional Facilities and Siting Group A. Enomoto, V.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
COOLING & VENTILATION FOR THE DRIVE BEAM TUNNEL M Nonis – EN/CV – 16/9/2009 CLIC TWO BEAM MODULES REVIEW
Process Water VE Updates (Main Linac Only) Emil Huedem FNAL ILC Meeting - CHICAGO Nov E. Huedem 2008.
Global Design Effort - CFS AD & I Meeting - DESY AD & I Meeting - DESY 1 AD&I Meeting CONVENTIONAL FACILITIES AND SITING GROUP Main Linac Tunnel.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
J. G. Weisend II for the ESS Team Energy Efficiency & Recovery at ESS.
ESS Cooling System - Interface with DTL 1 John Jurns Cooling System Engineer.
ESS Cooling System - Interface with RFQ 1 John Jurns Cooling System Engineer.
Global Design Effort - CFS ILC Integrated Design Meeting, DESY, May ML Single Tunnel Configurations In Deep Underground Accessed with Long.
Ullrich, DESY Dubna GDE XFEL The European X-Ray Laser Project X-Ray Free-Electron Laser 1 Water cooling XFEL Desingn of the XFEL water cooling.
1 CFS Utilities – What’s included in RDR for IR July CFS Utilities – IRENG WG C WATER COOLING: none. Unknown loads on IR. Only have water plants.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
1 DR 10 Hz Repetition Rate S. Guiducci (LNF) AD&I webex, 23 June 2010.
CFS EDR KICK OFF MEETING Air Treatment August 23, 2007 Lee Hammond, FNAL CFS.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
ILC Utility Design Study for Kitakami-site
ILC Power and Cooling VM Workshop
Review of the International Linear Collider (ILC) Electrical and Mechanical System Design to be held at CERN on 21 March, 2012 The purpose of the Review.
The Data Center Challenge
Conventional Facility & Siting (CF&S) Overview for the Positron Source
CFS EDR KICK OFF MEETING Process Water August 23, 2007
Energy Savings Projects
HVAC EQUIPMENT: COOLING SOURCES (see Chapter 16)
Americas KlyCluster Cost Analysis Overview
Q &A for the questions from CFS of April 29,2011
Summary of WG2 :CFS for staging
Water Cooling issue (Klystron Cooling)
BDS Cryogenic System RDR Status and EDR Plans
Industrial Assessment Center Database
CONVENTIONAL FACILITIES presented by Peter H. Garbincius
ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe – KICK OFF MEETING
COOLING & VENTILATION INFRASTRUCTURE
Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri.
ILC Cryogenic Systems Draft EDR Plan
Energy Efficiency in District Coiling System
ILC Cryogenics -- Technical Design Report Planning
ILC - Global Design Effort
Presentation transcript:

E Huedem, June RDR PROCESS WATER & VALUE ENGINEERING ITEMS June 5, 2008 GDE Meeting-ILC CFS Workshop in Dubna, Russia Emil Huedem, Fermilab

E Huedem, June RDR process water-Timeline Heat Load (RDR & Post RDR) Delta T Value Engineering items

E Huedem, June Dec Aug RDR PROCESS WATER RDR COST We’re here 2006 No updates done- this period RDR Process Water (Timeline) Changes/ reviews Dec 2007 Nov 2007 Jun 2008 No updates done-this period VE, GDE, KOM, Criteria Updates Nov-Dec Concept and cost Process Water (Stop Dec ) Aug EDR Kick Off Meeting (task: Get as much info and evaluate to get high delta T) Oct-2007 GDE, some Updates on ML heat table Nov Value Engineering (VE) session (Post RDR Delta T evaluate -more on this later in the slide) Dec Marc list from VE list (more on this later in the slide) interface with HLRF people re: delta T, heat load, non-cfs VE items Dec Stopped work minimal interface with Atsushi, Masami, Peter..

E Huedem, June Nov Aug RDR PROCESS WATER RDR COST We’re here 2006 No updates done- this period RDR Process Water (Timeline) Changes/ reviews Dec 2007 Nov 2007 Jun 2008 No updates done-this period VE, GDE, KOM, Criteria Updates About RDR Criteria and heat loads were incomplete. Snapshot in time Cooling infrastructure in RDR was conceptual, and very little on paper. Cost was generated for shaft 7 based on info at that time Not a unified criteria?? LCW part was immature. Instead of criteria,..Various Cost reduction discussion,

E Huedem, June x 26 skids Water Plant at Shaft MW (2,956 Ton) x 26 qty Basic Design Concept in RDR Process Water Chilled Water

E Huedem, June RF64 RF56 RF58 RF64 RF 104 RF114 RF + 50% of e-plus load 64 RF + 50% of e-plus load ELECTRON SIDE BDS RTML 2 BDS 4 RTML RF64 RF 54 RF56 RF64 RF 104 RF64 RF110 RF + e-minus load POSITRON SIDE DR Start of ML Surface Plant Locations* used in RDR * (follows major shaft locations) Tunnel about 450 ft depth ~ 5 Km

E Huedem, June Total Heat Load RDR Nov 2006 IR = None

E Huedem, June ML RF Heat Load – RDR Nov 2006 Shigeki, Chris A., Ray L, R. Cassel, Clay C., Keith J, HLRF Meeting Notes/ s,

E Huedem, June Heat Table improvement! Oct 2007, but still incomplete Loads Increasing Chris Nantista Shigeki (check min Flow?) Beam Tunnel Temperature? Chris and Keith? Cassell Jensen Shigeki ?? POST-RDR Heat Table Worked with Shigeki, Chris N., Mike N., Keith J., Jensen, Cassell, Clay

E Huedem, June POST RDR

E Huedem, June POST RDR High DELTA-T Evaluation In RDR there’s incomplete component criteria to evaluate the delta T. Used 20Fdelta average for Shaft 7 plant. LCW SKID 1 RF =100KW ? Pipe Distribution ?

E Huedem, June Post RDR- High Delta T Evaluation 1 RF POST RDR

E Huedem, June RF POST RDR Post RDR- High Delta T Evaluation

E Huedem, June RF POST RDR Post RDR- High Delta T Evaluation

E Huedem, June liter per min per load 2 RF POST RDR Post RDR- High Delta T Evaluation

E Huedem, June liter per min per load 2 RF POST RDR Post RDR- High Delta T Evaluation

E Huedem, June Nov 2007, being pursued this possibility of low-flow, high delta T Load with Chris N, Shigeki & Mike N and their vendor…as well as finding the rest of the info such as the delta P … Post RDR- High Delta T Evaluation

E Huedem, June Nov 2007, trying to find out the minimum flow in the collector. SO WHAT IS THE MINIMUM FLOW REQD FOR COLLECTOR? Question to the same group Post RDR- High Delta T Evaluation More on this….

E Huedem, June Dec to Dec Interface with Mike Nubauer (HLRF point of contact) Mike N: CFS stop here with valves tap??? Water Pump/ Skid 22 F delta to 30 Service tunnel beam tunnel

E Huedem, June (From Shigeki’s Oct 2007 Slide) General Calorimetric Calculation P(kW):Average power (deg): delta C Q(liter/min) : flow rate At MLI-KOM, Wilhelm pointed out the Thales guide line parameter of cooling K Is 0.8 (liter/min/kW), and this value is a common accepted value from the cooling of the collector (by Toshiba engineer). Toshiba has better efficiency of cooling than the K=0.8 case.Though it is nice data, we use K=0.8 as the standard collector cooling. Current data for collector given as 45.8 KW, and 37 l/min. In Oct 2007, We’re told that ILC will use a Klystron design for 300KW at 10 rep rate, but will be use for 150KW peak at 5 Hz rep rate, actual heat dissipation given to us as 45.8 KW at K=0.8, flow = 0.8 x 45.8 = 37 l/min. So, should we use this 150KW load also, flow = 120 l/min ? At K=0.8, Delta T across collector always ~32F delta T

E Huedem, June Comparison 32 delta F

E Huedem, June Simplified Tesla lcw diagram Comparison – Tesla and Post RDR 32Fdelta Post RDR has more components, blend delta T Load low delta T 103 KW Collector 45.8 KW Collector

E Huedem, June Simplified Tesla lcw diagram Comparison – Tesla and Post RDR 31Fdelta F 155 F 60 deltaF If use 150KW at K=0.8, flow =120 l/min, with modified circulator/ loads, 31Fdelta Change to low flow-high delta T

E Huedem, June Simplified Tesla lcw diagram Comparison – Tesla and Post RDR 31Fdelta F 155 F 60 deltaF For 45.8 KW collector, system delta T= 30 F For 150 KW collector, system delta T=60F Delta T = Total RF Heat Load (BtuH) / (500 * gpm flow) pipe main already consider this, just need to add feedback piping loop, and ensure Heat rejection design for the higher load 31Fdelta Change to low flow-high delta T gpm

E Huedem, June Specific V.E. List About 50+ list from V.E. in Nov 2007, List from value engineering sessions in Nov Some appear to have real good cost reduction potentials. Talks located in ?confId= ?confId=2328 Description of each list, but no detailed evaluation no pros/cons and cost impact evaluation done yet Color coded Red=Marc selected on Dec Yellow=potential VE but not necessarily cost reduction? Green= by others (HLRF), not CFS Gray=ignore White=not sure Further effort stopped on Dec POST RDR

E Huedem, June Specific V.E. List POST RDR

E Huedem, June Specific V.E. List Provide one high efficiency cogen power / cooling plant on site and distribute power and 33 degree F chilled water throughout the facility, remove the power generation and Chilling cost from the project cost, by using alternative financing mechanism (e.g. ESPC, etc.) to transfer the construction costs of cogeneration to the project’s future operating cost stream (without increase) where it can be amortized out of energy cost savings, thus practically eliminating the current costs for utility plants from the project construction. In other countries the ESPC concept might likely be replicated through investment loans. This idea would provide a centralized cogeneration plant at the central site with distribution throughout the tunnel. The cogeneration plant could likely provide cooling for the cryogenic, chilled water and process water systems and heat for desiccant dehumidifier regeneration, in addition to electrical power for the accelerator. Plant operation and maintenance is typically handled by the ESPC contractor and is also paid for out of the energy cost savings stream. POST RDR Some VE list variations of this

E Huedem, June Specific V.E. List Maintain reasonable (even lower) tunnel temperature to increase operating efficiency, extend equipment life, and improve operating environment. This VE item quoted impact of high ambient temperature involving electronic equipment of various grades of construction (Hardy,Average and weak), and the Corresponding loss of equipment life. Another is the energy loss associated with electrical resisitivity of conductors in distribution and equipment. POST RDR

E Huedem, June Specific V.E. List Use process water only as primary rejection. Eliminate Chilled water system by using multiple compressorized Fan coil (heat pump) to maintain 85F space POST RDR

E Huedem, June Specific V.E. List Eliminate process water by using chilled water only as primary rejection POST RDR

E Huedem, June Specific V.E. List Red Item (Marc’s selection from VE list) Eliminate chilled water, use process water only for heat rejection Consider using 30F water Delta T in RF Warmer tunnel temperature to 104F during operation and local cool during maintenance Consider low mineral content water instead of LCW Consider using plastic pipe instead of steel/stainless steel

E Huedem, June ACTUAL Marc Dec VE list Evaluate Shaft 7 cost based on following selected list Cost Reduction = ?

E Huedem, June ACTUAL Marc Dec VE list Evaluate Shaft 7 cost based on following selected list Variation: as high as possible??? Cost Reduction = ?

E Huedem, June ACTUAL Marc Dec VE list Evaluate Shaft 7 cost based on following selected list Variation: Replace w compressorized fancoils, maintain 85F TBD 85 Cost Reduction = ?

E Huedem, June ACTUAL Marc Dec VE list Evaluate Shaft 7 cost based on following selected list Cost Reduction = ?

E Huedem, June Summary Post RDR effort (Nov & Dec 2007) =updating HLRF heat table, delta T, value engineering session. started investigating with HLRF low flow-high delta T “Load The number of suggestions (VE list, one water system, learning from tesla/xfel etc) should result to improvement and cost reduction!, but by how much? who’s costing? No effort time?? I think chilled water “only” scheme (as suggested in VE list) should at least be considered / eva;uated to find out “first cost” impact, unless the “heat load to air” in bedrock tunnel scheme is reduced much much further From Oct GDE, it appear that heat Loads and requirement from other area system appear to be changing, increasing and tolerance tightening, so Requirement/criteria agreed by PM and area system will be important Getting requirement/criteria is difficult,.. getting something that is agreed upon by the majority is more difficult, and it will probably take a while to get this.. For future detailed work (edr??).. it would be helpful to get what criteria/ requirement will be used as basis …