US Army Corps of Engineers BUILDING STRONG NY & NJ Harbor Deepening Project Status Update and Lessons Learned Thomas J. Shea, III, PMP Project Manager.

Slides:



Advertisements
Similar presentations
US Army Corps of Engineers Budgeting Process
Advertisements

Why we need to learn a second language? Because its a ruff world out there.
Integrated Waterfront Cleanup and Marina Development in Bellingham, WA Tom Wang, P.E. WEDA Pacific Chapter – San Diego 2009.
Spoil to Splendor: A Story of Chesapeake Bay Island Restoration Presented by Christopher P. Guy, Peter C. McGowan And Robbie Callahan U.S Fish and Wildlife.
NYS Department of Environmental Conservation Jamaica Bay Marshlands & Spring Creek Stephen Zahn Deputy Regional Director NYSDEC Region 2 Public Meeting.
US Army Corps of Engineers BUILDING STRONG ® West Onslow Beach/ Topsail Beach West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project Town.
US Army Corps of Engineers BUILDING STRONG ® Eastern Shore Navigation Partnership Meeting “ A Unified Voice for Navigation, Project Prioritization, and.
U.S. Army Corps of Engineers Savannah Harbor Expansion Project Savannah Harbor Expansion Project.
Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers.
Module 23 STEPS 15 & 16 Preconstruction Engineering and Design (PED) and Other Decision Documents Civil Works Orientation Course - FY 11.
Q AVG US Army Corps of Engineers BUILDING STRONG ® Q AVG US Army Corps of Engineers BUILDING STRONG ® USACE Regional Sediment Management Program Linda.
US Army Corps of Engineers PLANNING SMART BUILDING STRONG ® Project Planning with the U.S. Army Corps of Engineers (USACE) Presenter Name Presenter Title.
PORT OF NEW YORK/NEW JERSEY
NAD/SAD REGIONAL DREDGING MEETING/WEDA WILMINGTON DISTRICT
The situation in Norway concerning sediments/dredging Tore Lundestad, Port of Borg, Norway.
CHARLESTONMOBILE WILMINGTON SAVANNAH JACKSONVILLE US Army Corps of Engineers BUILDING STRONG ® NC Water Resources Congress Christine Brayman Deputy For.
Prepared for: Prepared by: A Tutorial for Identifying a Project-Specific Dredged Material Placement Site October 2012 Bill Goodfellow Kaitlin McCormick.
US Army Corps of Engineers BUILDING STRONG ® Rosewood Park Coastal Section 506 of WRDA 2000 Kirston Buczak, PMP USACE, Chicago District May 2012.
Savannah Harbor Expansion Project
Coastal Texas Protection and Restoration Project
EPA’s Work Related to P2 and the Great Lakes Great Lakes Regional Pollution Prevention Round Table Summer Conference August 2005.
US Army Corps of Engineers BUILDING STRONG ® Charleston District Charleston Harbor Post 45 Deepening Feasibility Study Barbara Melvin Senior Vice President.
October FY08-FY12 Dredging Schedule New York District 1st Qtr FY08 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr FY09FY10 1st Qtr 2nd.
Watershed-based Plan To Restore the Hackensack Meadowlands: The Meadowlands Comprehensive Restoration Implementation Plan Terry Doss and Karen Appell The.
Module 27 Continuing Authorities Program Module 27 Continuing Authorities Program Civil Works Orientation Course - FY 11.
Port of Long Beach Development Projects Al Moro, P.E. Chief Harbor Engineer ACEC January 18, 2012.
Building Strong! 1 US Army Corps of Engineers Regulatory Program Kimberly McLaughlin Program Manager Headquarters Operations and Regulatory Community of.
US Army Corps of Engineers BUILDING STRONG ® Mouth of the Columbia River (MCR) Jetties Laura Hicks Chief, Planning and Project Management Branch Pacific.
Port Everglades Master / Vision Plan Status Broward County Board of County Commissioners May 4 th, 2010.
Beneficial Use at Deer Island A Decade of Design and Implementation Presented by Walter Dinicola, P.E., and Wendell Mears Anchor QEA, LLC George Ramseur.
US Army Corps of Engineers BUILDING STRONG ® 2012 Alabama Water Resources Conference Orange Beach, Alabama September 6, 2012 Beneficial Use Opportunities.
Harbors Module NH1: Authorities and Policies. NH1 - 2 BU ILDING STRONG SM Student Learning Objectives Student will be able to:  Describe the Federal.
BUILDING STRONG SM Partnering and Coordination to Accomplish the Navigation Mission.
Building Strong! May Deep Draft Navigation Cost Sharing Jeremy LaDart Office of Water Project Review HQUSACE.
PRESENTATION & DISCUSSION Dave Bergen Southold Town Trustee July 18, 2015.
Brownfields: Real Property, the expansion or redevelopment, or reuse of which may be complicated by the presence or potential presence of contamination.
US Army Corps of Engineers Chicago District FY04tpr\skbcongressional Civil Works Program Missions Missions Process Process Select Authorities Select Authorities.
Harbors Module NH3: Formulation – Measures, Strategies and Plans.
US Army Corps of Engineers BUILDING STRONG ® Toke Point Marina Pipeline Maintenance Dredging with Flowlane Disposal at Willapa Harbor, Washington Hiram.
SEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCT FY07FY06FY08 Page 1 of 3 FY07 Dredging Schedule New York District Mechanical Dredge Maintenance Dredging Newark.
1 Atchafalaya River and Bayous Chene, Boeuf, and Black, Louisiana Dredged Material Management Plan (DMMP) Kick off Meeting April 13, 2005 Project Manager.
Dredged Material Separation Plan Execution in New York Harbor Deepening Projects Jeff Snyder SeaVision Underwater Solutions.
BUILDING STRONG ® PLANNING SMART ® US Army Corps of Engineers BUILDING STRONG ® Partnering Opportunities for Water Supply and Distribution Planning Beverley.
1 Cameron Davis Senior Advisor to the Administrator, U.S. EPA Commission for Environmental Cooperation Joint Public Advisory Committee Public Forum on.
Department of Army Permitting Process: Dredging
US Army Corps of Engineers BUILDING STRONG ® ENGINEERING WITH NATURE “ Beneficially Integrating Engineering and Natural Systems” PIANC 2012 Dredging Conference.
1 Calcasieu River & Pass, Louisiana Dredged Material Management Plan (DMMP) Kick off Meeting February 2, 2005 Project Manager Mireya Laigast, Civil Engineer,
Beneficial Use of Dredge Materials: Introduction to Dredging and Policy J. Bailey Smith US Army Corps of Engineers April 4, 2011.
Lake Erie Dredge Material: Finding a Solution for Ohio Ohio Brownfield Conference 2016 April 6-7, 2016.
Ecology and environment, inc. ecology and environment, inc. International Specialists in the Environment Georganna B. Collins, International.
Environmental Management Division 1 NASA Headquarters Environmental Management System (EMS) Michael J. Green, PE NASA EMS Lead NASA Headquarters Washington,
A New Paradigm for Utility Coordination Kenny Franklin VP of SUE Development Blood Hound.
UPPER NEWPORT BAY ECOSYSTEM RESTORATION PROJECT NEWPORT BEACH CITY COUNCIL STUDY SESSION FEBRUARY 14, 2006.
Chesapeake Bay Program
Regional Greenhouse Gas Initiative
Savannah River Projects
Watershed-based Plan To Restore the Hackensack Meadowlands:
Overview May 24, 2017.
Restructuring Roundtable June 16, 2017
NEW ENGLAND DISTRICT Operations and Maintenance Projects Maine Dredge Team Meeting October 2015 Ed O’Donnell Chief, Navigation Section.
Local Government Engagement and Communication Strategy
Beneficial Use of Dredged Material
Michigan Dept. of Environmental Quality Water Resources Division
Beneficially Using Dredge Material
Chesterfield Neighborhood Coal Ash Update January 9th, 2019
Senator Dance Town Hall Coal Ash Update December 5, 2018
A Paradigm for Utility Coordination
Watershed-based Plan To Restore the Hackensack Meadowlands:
BOSTON HARBOR DEEP DRAFT IMPROVEMENT PROJECT
Eric Ellis Habitat Restoration Senior Program Specialist
Presentation transcript:

US Army Corps of Engineers BUILDING STRONG NY & NJ Harbor Deepening Project Status Update and Lessons Learned Thomas J. Shea, III, PMP Project Manager Harbor Programs Branch U.S. Army Engineer District, New York 25 October 2012

BUILDING STRONG ® Significance of the Port of NY & NJ Largest Port on the East Coast (59% share) 3 rd in US (13% share); 15 th in World $114.5 B in cargo (over 5 million TEUs per year) 852,000 automobiles 269,900 full time jobs (10/2011) $11.2B in personal income (10/2011) $2.2 B in NY/NJ state and local tax revenue 35 percent of US population served

BUILDING STRONG ® Project Timeline  1996 – Vice Presidents Press Release  1997 – 905b Report completed, Feasibility Study Initiated  1999 – Feasibility Study and FEIS completed  2000 – Chiefs Report and Authorization  2001 – Pre-Construction Engineering and Design initiated  2004 – LRR Completed and PCA executed  2005 – First Construction Contract Awarded  2013 – Last Construction Contract Awarded  2013 – Limited Access to 50 ft traffic  2014 – Full Access to 50 ft traffic

BUILDING STRONG ® Description: Deepens 35 miles of navigation channels to ft (mean low water) to provide deep draft access to the major container terminals within the Port of New York and New Jersey. Key features of the 50 ft. project include: –17 large multiyear dredging contracts –Mitigation restoring 143 acres of tidal wetlands –Offsets NOx air emissions from project –Beneficial use of dredged material Total Project Cost $1.6 Billion Cost Share About 54% Fed, 46% Non-Fed Project Overview Sponsor Port Authority of New York & New Jersey New Jersey Department of Transportation Office of Maritime Resources

BUILDING STRONG ® Existing Conditions Auth/Maint to 45 Ft Auth/Maint to 40 ft Auth to 45, Maint at 40 Water Siphon Auth to 41/40, Maint to 35

BUILDING STRONG ® Current Status KvK-5 Underway in FY 13 Awarded in FY 13 Completed in FY 13 S-AM-1 S-KvK-2 S-AN-1a Completed S-NB-1 S-KvK-1 S-E-1 S-AM-2a PJ-3 S-AN-1b/S-AM-2b PJ-4 S-NB-2/S-AK-1 S-AK-2 S-AM-3 S-AK-3 Water Siphon Deferred Work S-AN-2 SRUC FY 13 Award

BUILDING STRONG ® Mitigation Program Wetlands Restoration: Required to mitigate for the loss of 6.26 acres of littoral habitat Two mitigation sites: Elders Point Marsh Island Restoration, Jamaica Bay, NY (40 acres, off site) Woodbridge Creek Ecosystem Restoration Project, Woodbridge, NJ (23 acres, off site) HAMP: Harbor Air Mitigation Program Required to offset NOX emissions Retrofitted seven tug engines in the NY/NJ Harbor Retrofitted Staten Island Ferry engines with generator kits

BUILDING STRONG ® Dredged Material Management Plan: Goal: to utilize ALL material beneficially Rock – used to create artificial reefs and lobster habitat. HARS suitable – used to nourish beaches, for habitat restoration, as construction grade fill, and for capping former ocean disposal site. HARS unsuitable – used to cap landfills and brown fields after being processed to stabilize/solidify material.

BUILDING STRONG ® 100% of all Dredged Material beneficially reused Capping the HARS for Remediation Rock to Artificial Reefs HARS unsuitable material to upland sites Sand for Jamaica Bay Marsh Islands Restoration Five Island restored Elders East* and West Yellow Bar Black Wall* Rulers Bar* Restored 143 acres of salt marsh Beneficial Reuse of Dredged Material Elders West constructed as mitigation Black Wall and Rulers Bar construction at 100% local cost

BUILDING STRONG ® Challenges – Environmental  CZM/CWA Compliance: How to get one for a 12 year project? ► We obtained an "umbrella" compliance for the Project Partnership Agreement, then a “notices to proceed” for each contract. ► Consider pursuing a 404R/T exemption – might save time and money during construction  Essential Fish Habitat: Windows can extend overall construction time ► Start a sampling program early and coordinate it with NOAA Fisheries ► Our sampling data has helped to shorten no-dredging windows – reduced contract duration  Clean Air Act Compliance ► Check your State Implementation Plan (SIP), your project may be included in it ► Dredging is considered a mobile emission, you may not be allowed to obtain Emission Reduction Credits to bring your project into compliance

BUILDING STRONG ® Challenges- Engineering - Construction  Construction Sequencing: ► Partner early and often with the USCG/VTS, pilots, users, and other stakeholders  Cost Estimates ► Rock quality designation is a better indicator of diggability than the Unconfined Compressive Strength ► If resedimentation is a concern, developing your overall construction schedule in the feasibility phase may help to estimate the volumes ► Provide a detailed explanation of methods (surveying, take-offs, etc) in the P&S  Noise and Vibration – Community Relations ► When working near homes and businesses an independent robust noise and vibration monitoring QA program is your friend ► Keep the community and its leaders informed, hold public information sessions and use creative ways to get the message out there.  Construction Management ► Don’t over complicate the contract by having numerous contract line items ► Every item that is paid for by survey yards requires surveying. Plan for the time.

BUILDING STRONG ® Challenges – General  Utility Relocations can become the critical path  The bigger the utility the more complex the decision making process becomes  Major utility relocations need to be an early activity and managed closely.  Contract Acquisition Planning  Smaller contracts get more competition, larger contracts reduce E&D.  We’ve used about $100,000,000 as the limit before losing competition.  Having an “industry day” meeting during advertisement is a valuable way to get input earlier in the acquisition process  Beneficial re-use of material is a Great thing  Partner early and be aggressive  Can play a vital role in accomplishing your long term environmental strategic goals.