Upgrade and Reimplementation, Oh My! Andrew Tess, Housing - Dining - Hospitality UC San Diego
Housing Dining Hospitality UC San Diego Almost 10,000 undergraduate beds in Apartments and Suites 2500 Graduate and Family apartments 19 Dining, Retail, Catering and Restaurant Locations Roughly 5 million square feet, 300 buildings 80 Maintenance line staff 8 support/call center IT also uses Maximo
Time With Maximo First install 1997 Originally maintenance acquired system Managed by Call Center Lead Upgraded to 5 in 2005 Continued to use Maximo 4 methods
Manual and Limited Maximo Admin let very few people in All data entry limited to small admin staff Manual reports Maintenance management did not login Work Orders printed to Dot Matrix Printers Purchasing and Receiving entered…
Attempt and Change Upgrade to 6 attempted 2008 Update Scripts with IBM Assistance No real or perceived gains from upgrade Very Small Buy in No one driving person Management Change in Maintenance
Why Me? Reward for a job well done
Upgrade means Changes Upgrade now 5 to 6 to No more Back end access BIRT for Reports and Automation Review and update all manual reports to meet current needs IT Ownership of the system
Upgrade! Ran many dry runs to ensure success Grooved update process 3 days Included time for screen and security changes BIRT reports, except Work Order, imported after cutover
Data issues and Cruft Consistently Inconsistent Locations Long Descriptions Assets information incomplete Many applications had issues Base Applications deleted Cleaning of entries not possible
The Sell Built case based on issues experienced Look at what would be needed in future Upgraded system could not be reliably expanded to support department Better results and cheaper than cleanup Easier to use
So How do you ReImplement? Similar Process to plain Implementation Bring over only cleaned and verified data Rebuild data structures for unclean data Have backing and dedicated resources and realistic schedule Ask “why?” a lot and communicate with everyone about everything Stay as close to out of the box as possible
Location, Location, Location Logic! Time intensive Consistency Base of everything Familiarity is a plus, but not essential Mistakes will be made, just need to clean
Putting it Together 4 months from new system install to end of Reimplementation phase Application Import in 7.5 is amazing Preview the data and settings to group Meet often and have clear milestone dates
Cut over and Go Live! Process with many events not a singular occurrence Gradual move from “Old” system to “New” system Much behind the scenes work even after the full cutover
The Gains Single Sign On Better Base Data Improved reports (not just automated!) Stability! Be careful, Success leads to more projects –Integrations and Process Improvements
If Only… Classify Space Asset Collection Inventory Cleanup/Update Prior to Import More exposure to new elements prior to go live
To Maximo and Beyond! Maximo, Mobile and Tririga Andrew Tess -