GLAST LAT ProjectMonthly Review, Sept 27, 2005 4.1.7 DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7.

Slides:



Advertisements
Similar presentations
Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
Advertisements

GLAST LAT ProjectMonthly Review, Aug-1, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.
GLAST LAT ProjectSIU MRR DAQ & FSWV1 1 GLAST Large Area Telescope: G. Haller SLAC (650) Gamma-ray Large Area Space.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 Online 1 GLAST Large Area Telescope: I&T Integration Kickoff Meeting EGSE Hardware March 9th,
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
GLAST Calorimeter LAT F2F Meeting 17 Mar 2005 Naval Research Lab Washington DC W Neil Johnson 1 Subsystem Mgrs F2F Meeting Calorimeter Subsystem 17 Mar.
GLAST LAT ProjectTEM/TPS TRR, Jan 7, DAQ & FSWV3 1 GLAST Large Area Telescope: Presented by G. Haller SLAC (650)
Tower Electronics Module and Tower Power Supply EM Tower Electronics Module (TEM) before coating/staking TEM & TPS assembly Close to 60 TEM & TPS assemblies.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT Project – Cost and Schedule ReviewNovember 3, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review November 3, 2004.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectMonthly Status Review – Sept. 1, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectDOE Rebaseline Review, February 13, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Chief Engineer.
GLAST LAT Project4.1.7 G. Haller V21 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-to-Face Nov 04 Mike Huffer/Gunther.
GLAST LAT Project4.1.7 G. Haller V21 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S September Status
GLAST LAT Project Quarterly Review, Aug. 14, 2001 Gunther Haller1 GLAST Large Area Telescope: Electronics, DAQ & Flight Software Gunther Haller Stanford.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT Project4.1.7 July 17, 03 LAT Meeting G. Haller V41 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S LAT.
GLAST LAT ProjectF-to-F, June 15, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT ProjectTEM &TEM-PS Manufacturing Readiness Review – September 16, 2004 GLAST Large Area Telescope: Performance & Safety Assurance Pat Lujan TEM.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
GLAST LAT ProjectF-to-F, March, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
GLAST LAT ProjectOct DAQ & FSWV3 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Analysis of cPCI Backplane.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, DAQ & FSWV8 1 GLAST Large Area Telescope: Gunther Haller SLAC LAT Chief Electronics.
GLAST LAT ProjectPDU/GASU MRR, February 3, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, G. Haller SLAC xxxx LAT Quality Engineer
GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectGASU TRR, July, DAQ & FSWV1 1 GLAST Large Area Telescope: Presented by G. Haller SLAC (650)
GLAST LAT Project PDU/GASU MRR 4 February 2005 PART 2 / 1 GLAST Large Area Telescope: B. Estey, Production SLAC (650)
GLAST Large Area Telescope:
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT Project4.1.7 G. Haller V11 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Monthly Status Gunther.
CubeSat for Ions, Neutrals, Electrons and Magnetic Fields PI Robert Lin, SSL Project Manager Thomas Immel, SSL Systems Engineer Jerry Kim, SSL Mechanical.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectPDU TRR, July, DAQ & FSWV4 1 GLAST Large Area Telescope: Presented by P. Young SLAC (650)
ASPERA-3 Feb. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 2_25/ Page 1 Monthly Status Report Report due 2/25/01 Schedule statused.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
Goddard Space Flight Center Cryogenics and Fluids Branch Status of the AMS-02 Cryocooler January 2007 TIM.
GLAST LAT Project4.1.7 G. Haller V2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S April Status Gunther.
GLAST LAT ProjectMonthly Review, June 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMonthly Status Review – Nov 3, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT Project4.1.7 G. Haller V31 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Monthly Status Gunther.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
GLAST LAT ProjectTEM/TPS MRR, September 16, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, Production SLAC (650)
1 GLAST LAT ProjectMechanical Systems Mechanical Systems November 2003 GSFC Status Marc Campell, Subsystem Manager.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST Large Area Telescope:
Bill Raynor Naval Research Lab
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Summary of Fuse Testing for Barrel Module Fuse Boxes
GLAST Large Area Telescope:
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
EPU load – same as SIU load except…
Thermal Vacuum Test: Plans and Procedures
Subsystem Mgrs F2F Meeting Calorimeter Subsystem
Integration and Test Organization Chart
GLAST Large Area Telescope
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Sept 27 Monthly Review Gunther Haller (650) Gamma-ray Large Area Space Telescope

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 2 TEM/TPS Status Status –Qual unit review still to occur –19 flight units delivered to I&T –2 TPS units removed from Twr A and Twr B were partially modified To do (low priority) Complete modification Vibration End data package review

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 3 PDU Status and Schedule 1st unit (flight) In hands of I&T 2 nd unit (spare) –Progress since last month Boards conformal coated –Includes »Coating »AF QC, touchup, QC »SLAC (customer) source-inspection, touch-up, CSI »Integration into enclosure »Started wiring –Lower priority compared to assembly of SIU modules, but progressing, estimated delivery to I&T end of December

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 4 GASU Status and Schedule First Unit –Progress since last month Received final box Passed Safe-to-mate (without power) Passed Stray-voltage tests (with power) Passed Comprehensive Performance Tests Thermal-cycled Passed post TC tests Vibrated to proto-flight levels Passed post-vib tests Started thermal-vacuum test, expected completion Nov 7 –EMI left, if proto-flight EMI: 2 weeks, if flight acceptance: 1 day –GASU available Nov 9 or Nov 23, depending on EMI decision Schedule for 2nd unit –Progress since last month QC&CSI, rework and again QC&CSI of DAQ and power-supply boards (pre-coat) Boards are being installed in enclosure with harness –In about 3 weeks the box will be sent to SLAC for pre-coat testing, followed by conformal coat and environmental testing –Lower priority compared to SIU/HCB but still progressing –(Mid January estimated delivery to I&T)

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 5 SIU Protoflight Protoflight SIU crate –Progress since last month Received backplane assembly (backplane 2412) Integrated in enclosure Passed short/open test Integrated SIB2205, LCB2225 CPS2233, RAD750-CPU –All from flight assembly line, SIB has chlorine-contaminated EEPROM Passed environmental testing –Passed Comprehensive Performance testing –Thermal-cycled –Passed testing –Vibrated to proto-flight levels –Passed testing –Thermal-Vacuum tested (proto-flight limits) –Full EMI tested (passed qualification tests, conductive/radiative) Mass and CG measured

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 6 First Flight Crate First Flight Crate Progress since last month –Modules Backplane 2414/2428 –integrated in crate 2513 SIB 2207 –shipped to SLAC and module tested LCB 2227 –shipped to SLAC and module tested CPS 2235 –shipped to SLAC and module tested RAD750 14/2516 –Crate integrated, tested –Thermal-cycle, tested –Vibrated, tested –Thermal vacuum tested –EMI, tested –Mass measured –No failure –Working on web-site to list test results, closing of NCR’s

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 7 Second Flight Crate Second Flight Crate Progress since last month –Modules Backplane 2415/2429 –harness assembly completed, coated/QC/CSI/touch-up/delivered to SLAC, open/short tested Integrated in crate 2527 SIB 2208 –shipped to SLAC and module tested LCB 2226 –coated, shipped to SLAC, tested CPS 2238 –shipped to SLAC and module tested RAD750 15/2517 –Crate tested –Thermal-cycle, tested –Vibrated, tested –Thermal vacuum tested –EMI, tested –Mass measured –No failure –Working on web-site to list test results, closing of NCR’s Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch- up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 8 Third Flight Crate Third Flight Crate Progress since last month –Modules Backplane 2420/2433 –harness assembled, coated, shipped to SLAC, open/short tested Integrated in crate 2522 SIB 2206 –xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, coated, shipped to SLAC, tested LCB 2228 –coated, shipped to SLAC, tested CPS 2239 –coated, shipped to SLAC, tested RAD750 17/2518 –Crate integrated, tested –Thermal-cycle, tested –Vibrated, tested –Waiting for thermal vacuum testing (GASU is in TV chamber) –EMI, will be tested this week before TV –Mass measured –No failure up to now –Estimated completion of testing: Nov 15 Working on web-site to list test results, closing of NCR’s Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch- up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 9 Fourth Flight Crate Fourth Flight Crate Progress since last month –Modules Backplane 2419/2434 –harness assembled, coated, shipped to SLAC, open/short tested Integrated in crate 2523 SIB 2209 –flying probe tested, assembled, shipped to SLAC, xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, coated, shipped to SLAC, tested LCB 2229 –flying probe tested, assembled, shipped to SLAC, xrayed,, tested, shipped to AF, coated, shipped to SLAC, tested CPS 2240 –assembled, shipped to SLAC, tested, shipped to AF, coasted, shipped to SLAC, tested RAD750 18/2519 –Crate integrated, tested –In Thermal-cycle To be done –Vibration –Thermal vacuum –EMI –Mass –Estimated completion: Nov 22 Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch- up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 10 Fifth Flight Crate Fifth Flight Crate Progress since last month –Modules Backplane 2418/2431 –harness assembled, coated, shipped to SLAC, QA issues, shipped back to AF, in rework, will be shipped to SLAC early next week Will be in crate 2523 SIB 2210 –assembled new EEPROM, flying probe tested, assembled, shipped to SLAC, xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, in coating LCB 2230 –flying probe tested, assembled, shipped to SLAC, xrayed,, tested, shipped to AF, coated, in QA/CSI, will be shipped to SLAC tomorrow CPS 2234 –Assembled, shipped to SLAC, tested. Shipped to AF, in coating RAD750 13/2528 –Crate to be integrated To be done –TC –Vibration –Thermal vacuum –EMI –Mass –Estimated completion: Dec 6 Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch- up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 11 Spare crates Modules –2 Backplanes Ready for integration Nov 30, Dec 7 –2 SIB’s Ready for integration Nov 19, Nov 28 –2 LCB’s Ready for integration Nov 19, Nov 28 –2 LCB’s Ready for integration Nov 23, Nov 23 Estimates for Spare Crate availability –Dec 16 & Dec 23

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 12 Harness Interconnect Box (HIB) Task: Integrate, stake, pre-tested harness into (SIU) enclosure Progress since last month –Assembled 5 HIB’s at SLAC –Two vibrated –3 more about to be vibrated Ready for hand-off to I&T early next week

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 13 Heater Control Box (HCB) 6 Boards for 3 boxes assembled (2 flight + 1 spare) 4 Boards for 2 boxes conformal coated 2 boards integrated into one box with harness In QA at AF 2 nd box will be in QA early next week Then TC/TV/vib/EMI at SLAC Estimated delivery of 2 HCB’s to I&T: Nov 24

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 14 cCPI Connector Solder Joint Slide SLAC Qual testing of sample boards assembled at Aeroflex –Non-flight, only connectors were assembled on cCPI board for short/open testing of solder joints –Testing was all completed without failures –Presentation at qual.htmhttp://www-glast.slac.stanford.edu/Elec_DAQ/DAQ-Hardware/SIU-EPU/xray/xray- qual.htm Overall cCPI solder joint results on flight boards –5 flight backplanes accepted to use-as-is –Process was –SLAC looked at xrays, had touched up candidates –Then GSFC supplied a list fo pins to be touched up –SLAC went thru and identified pins which are used –Those were discussed and some were touched up –Plug-in cards Same process as with backplanes Maybe 1 or 2 pins on some boards which GSFC likes to have touched-up Discussed and agreed on boards already integrated SLAC is touching up all boards not integrated yet and supply new xrays (in progress)

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 15 Level 3 Milestone Count

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 16 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 17 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 18 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 19 Cost Report

GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 20 FTE Report (DOE/NASA-funded only)