LEReC System 1. LEReC Injection section 2016 CeC Beam Dump 45°dipole (CeC) Profile Monitor (ERL HE) No SRF Cavity DC e - Gun ERL Solenoid ERL Halo Monitors.

Slides:



Advertisements
Similar presentations
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Advertisements

Low Energy RHIC e - Cooling LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity 704 MHz SRF gun converted to booster cavity 5-cell 704 MHz.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
T. Montagne LTU – Beam Dump Installation April 16, LTU and Beam Dump Installation April 16, 2007.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
Low Energy RHIC e - Cooling Meeting Notes 1 –LF Solenoids & HF (Matching) Solenoids: Out for bid??? –20 o Dipole  Magnet gap is 4 inches/transport lines.
Generation and Characterization of Magnetized Bunched Electron Beam from DC Photogun for MEIC Cooler Laboratory Directed Research and Development (LDRD)
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
Discussion on the magnetic shielding: The magnetic shielding will not be installed until the 2016 shutdown. The magnetic shielding test fixture will be.
Generation and Characterization of Magnetized Bunched Electron Beam from DC Photogun for MEIC Cooler Laboratory Directed Research and Development (LDRD)
1 Low-energy RHIC electron Cooler (LEReC) cost estimate December 2, 2014.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
Low Energy RHIC e - Cooling LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity 704 MHz SRF gun converted to booster cavity 5-cell 704 MHz.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Sergey Belomestnykh SRF and RF systems.
MP Questions for LE eCooling. Why talk about this now? Is there additional equipment needed, not yet considered? (nor costed) Interfaces to systems that.
G5 Beam Instrumentation D. Gassner, E. Pozdeyev 4-09.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
Low Energy RHIC e - Cooling Meeting Minutes – 11/19/14 1. Cooling Section Magnets and Power Supplies –Most of power supplies will be from ERL (R. Lambiase).
1. Beam Line Layout – Cooling Section (CS) Mu Metal shield design – G. Mahler is assembling a mock-up of beam line for field measurements to evaluate.
Low Energy RHIC e - Cooling Meeting Minutes – 11/5/14 1.J. Tuozzolo will schedule a visit to NSLS next week to evaluate available magnets, power supplies,
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Accelerator Science and Technology Centre Extended ALICE Injector J.W. McKenzie, B.D. Muratori, Y.M. Saveliev STFC Daresbury Laboratory,
We will not need buncher. This could be Brock’s kicker, when he sends it to us.
G5 Design Review, April 24, 2009 Gun to 5cell Cavity Test: Overview Dmitry Kayran G5 test Design Review April,
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Low Energy RHIC e - Cooling Meeting Minutes – 11/5/14 1.Funding is available to purchase magnets. 2.Comment during presentation of attached slides: 180.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
A Fedotov, K Hamdi, D Kayran, L Snydstrup, K Smith, J Tuozzolo, A Zaltsman Transport Beam Line Design development of beam line will be from the Booster.
Low Energy RHIC e - Cooling Meeting Minutes – 12/23/ Cooling Section: –LF Solenoids:  At PPM, G. Woods has assigned buyer, SOW will be revised,
LEReC. COOLING in Blue RHIC ring COOLING in Yellow RHIC ring 63.9 m to IP2 Beam Dump 20° Bending Magnets DC e - Gun 704 SRF Booster Cavity 2.1 GHz Cu.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
Development of High Current Bunched Magnetized Electron DC Photogun MEIC Collaboration Meeting Fall 2015 October 5 – 7, 2015 Riad Suleiman and Matt Poelker.
Low-Energy RHIC electron Cooling (LEReC) MPS meeting MPS Meeting April 21, 2016.
Beam Line Layout – Cooling Section (to be installed by 1 Dec ember 2015) J. Kewisch wants to move the 20 dipole, yellow (to the right) toward the triplet.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
Meeting Minutes: LEReC DC Gun, Transport Lines, and Dump Installation 2016, May 26, 2016 D. Kayran, A. Fedotov, T. Miller, D. Gassner, D. Weiss, G. Mahler,
5/25/16 Gun to Booster Transport Line Meeting Minutes: A. Fedotov, D. Kayran, S. Bellavia, M. Mapes, T. Rao, B. Sheehy, J. Tuozzolo, Z. Zhao, B. Sheehy,
LEReC. COOLING in Blue RHIC ring COOLING in Yellow RHIC ring 63.9 m to IP2 Beam Dump 20° Bending Magnets DC e - Gun 704 SRF Booster Cavity 2.1 GHz Cu.
LEReC Electron beam requirement for cooling Kinetic energy, MeV 1.6
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
LEReC Instrumentation Gun Test Beam Line Summary Toby Miller
Low Energy RHIC e - Cooling Meeting Minutes – 12/17/ For the matching energy of electron and ion beams methods for electron energy measurement were.
LEReC Instrumentation Gun Test Beam Line Summary Toby Miller
Minutes meeting Mapes, Miller, Kayran, Fedotov, Gassner, Hamdi, Bruno, Mahler, Weiss, Hammons, Arno, Nayak, Fite, Bellavia The layout shown in.
Meeting Minutes S. Nayak, J. Halinski, L. DeSanto, D. Gassner, C.J. Liaw, Z. Zhao, P. Inacker, M. Minty, J. Tuozzolo All three custom chambers.
Report Technical Director Storage-Ring-Installation Completed
Dmitry Kayran on behalf of LEReC team Brookhaven National Laboratory
Beam Commissioning Adam Bartnik.
CBETA Vacuum System and Beam Stop (Conceptual Design) Yulin Li, CLASSE.
Lessons learned from BNL R&D ERL test facility
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
Cornell ERL Prototype Injector DC Photocathode Gun Design Review Vacuum Systems Yulin Li, January 5th– 6th, /5-6/2011 Cornell Gun Review.
Why are we removing our very good gun?
EBTF Design Review Technical Meeting Group
XFEL Vacuum System Commissioning
DC Injector and Space Charge Simulation Status
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Injector Performance Requirements Conventional Facilities Update
The Cornell High Brightness Injector
Electron Source Configuration
Center for Injectors and Sources
NEG-coated gun: Black R30 arc at 227kV, white R30 arc at 164 after refurbishing and second bake Carlos Wednesday, August 10, 2018.
ATF ICB meeting, LCWS08, UIC, Chicago, 11/18/2008
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
Linac Diagnostics Commissioning Experience
Two-beam Test-stand Design and Construction Status
Injector/Linac Design Status C. E
Presentation transcript:

LEReC System 1

LEReC Injection section 2016 CeC Beam Dump 45°dipole (CeC) Profile Monitor (ERL HE) No SRF Cavity DC e - Gun ERL Solenoid ERL Halo Monitors ERL Emittance Slit ERL DCCT & ICT Faraday Cup ERL Solenoid 2.1 GHz Cavity Cathode Suitcase ERL Quadrupole H/V Corrector BPM Cathode Insertion Profile Monitor (ERL LE) ERL Solenoid (temporary) BPM (temporary) H/V Corrector H/V Corrector (temporary) H/V Corrector ERL Quadrupole BPM 2.1 GHz Cavity: The cavity will be installed next to the beamline to decouple its commissioning from the DC gun commissioning. BPM

4

Component Status Magnets: (3ea) ERL solenoids – remove and magnet measurement (4ea) H/V Corrector magnets – New GtB aircool design (2ea) ERL quadrupoles – remove, need magnet measurement? (1) CeC 45 o dipole magnet – new vacuum chamber (beam impedance analysis?) Magnet base, survey adjustment hardware, and stands for the all above. Beam Dump CeC design dump (isolated faraday cup?) 5

Component Status Diagnostics: DCCT and ICT from ERL (internal RF shielding analyzed) any further modifications? (1) ERL HE Profile Monitors (new internal RF shield for vacuum chamber, ferrites, new larger YAG screen) any further modifications? (1) ERL LE Profile Monitors – no changes ? (1) Emittance slit drive (new vacuum chamber and slit shape) (1) ERL Halo Monitor (same vacuum chamber) (1) Faraday cup (ceramic insulated vacuum flange?) 1 watt limit? Laser Systems: Laser building modifications Transport line In tunnel optics table 6

Vacuum Components Need a P&ID including DC gun and cathode carts Shielded bellows drawing/order “Standard” shielded pump tee drawing/order Shielded Pump & Gauge Tee Shielded Bellows Shielded Valve w/DC Gun Shielded Valve Shielded Pump & Gauge Tee Shielded Bellows Pump on Halo Monitor

DC Gun Vacuum Ion pump and NEG Bake-out C Extractor vacuum gauge Remote bleed valve for HV conditioning 1 shielded, 1 non-shielded valve Cathode Systems Vacuum Bake-out C Vacuum gauges and pumps Plug in cables for transport cart pumps and gauges – remote monitoring Bake-able Vacuum “load lock” with remote monitoring and remote temperature control Valves w/interlocked controls (local MPS) Tunnel switches for interlocked “load lock” valves 8

9

Need PS for clearing electrodes Need to clarify H/V corrector count Correctors 27 and 28 Corrector between GIS3 and GIS4 At meeting – no: Mu metal shielding will be used so more correctors are not needed. Solenoid at end of dump line? At meeting - no 10 GIS1 Corr 26 GIS2 Corr 25 GIS5 Corr 29 GIS3GIS4 Corr 30 Corr ?? Corr 31 Corr 32 Q5 Q6 GICS1? Corr 28? Corr 27?

1.Solenoid drawings complete, checked 2.Corrector drawings complete, (Bakeout) 3.Mirror assembly complete, checking 4.Vacuum chambers (3) near complete, checking 5.Profile Monitor near complete, checking 6.Support Stands modeling 7.Update Booster Cavity U/S 8.Update Booster Cavity D/S

Component Status Other: 2.1 GHz Cavity (off beamline) 1002B PA, ACS interlock, wave guide, tuner drive, stand 704 MHz Cavity (in place, on beamline) 1002B PA, ACS interlock, wave guide, tuner drive, stand 9 MHz RHIC Cavity (in place, on beamline) 12

Cognizant Engineers Project Engineer: Tuozzolo Cathode system: Liaw, Tuozzolo, Hamdi, Laser System: Zhao, Sheehy DC Gun: Liaw, Costanzo, Halinski Cornell – Karl Smolenski Cornell Power Supplies: Bruno GtB Transport Line: Nayak, Halinski Magnets: Mahler Beam Diagnostics: Miller, Gassner, Weiss Vacuum: Mapes, Steszyn Beam Dump: Fite, Corbin Warm RF Cavities: Zaltsman, Smith, Brutus, DeSanto Controls: Jamilkowski, Costanzo 13

Cognizant Engineers Project Engineer: Tuozzolo Cathode system: Liaw, Tuozzolo, Hamdi, deMonte Laser System: Zhao, Sheehy, Bellavia, Taddonio DC Gun: Liaw, Costanzo, Halinski Cornell – Karl Smolenski Cornell Power Supplies: Bruno GtB Transport Line: Nayak, Halinski Magnets and mu metal: Mahler Beam Diagnostics: Miller, Gassner, Weiss Vacuum: Mapes, Weiss, Steszyn Beam Dump: Fite, Corbin Warm RF Cavities: Zaltsman, Smith, Brutus, DeSanto Controls: Jamilkowski, Costanzo, Altibanous 14