BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 1 BGV cooling : status and plans reporting on behalf of EN-CV (Sylvain Nichilo & Olivier Crespo-Lopez)

Slides:



Advertisements
Similar presentations
How to apply a TXV kit to an evaporator coil – Initial installation
Advertisements

Refrigeration Systems
1 Ann Van Lysebetten CO 2 cooling experience in the LHCb Vertex Locator Vertex 2007 Lake Placid 24/09/2007.
3.1.9 Student Book © 2004 Propane Education & Research CouncilPage Replacing Valves and Fittings in ASME Tanks Replacing ASME tank valves and fittings.
Summery of Cooling System Teflon Leaks* *This is independent of the internal problems Rob Pisani.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
"AIR COOLER" Heat Exchanger
PRR TRD COOLING A. Marín (GSI) 7/01/2004 ALICE PRR TRD COOLING P.Glässel, A.Marín, V.Petracek, J.Stachel, M.R.Stockmeier, J.P.Wessels ALICE PRR TRD COOLING.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
The new Super Multi from TCUK
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
INSTALLATION & COMMISSIONING. 5WSS Installation Hanging the Unit Hanging the Unit Location Considerations Location Considerations Refrigerant Piping Refrigerant.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
CMS Pixels upgrade CO 2 cooling transfer lines Introduction to the two projects P.Tropea 5 Dec 2012.
19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready.
CONSTRUCTION Andrea d'AURIA PH / DT-DI / GAS.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel.
IBL cooling thermal chock incident 15 October The IBL cooling team.
Claudio Bortolin 03/09/2012. SPD (RP analyses required) 1) Pump 17b replacement and leak test 2)Pressure test on the old inlet lines (technicians coming.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
Cooling System Solutions
Update on Micro Channel Cooling Collaboration Meeting , G. Nüßle.
BGV 03-nov-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : status and TS3 installation plans Valdir & Massi.
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
Documentation on present system and piping layout P. Tropea Tracker Upgrade Engineering and Cooling 12 November 2008.
ME444 ENGINEERING PIPING SYSTEM DESIGN CHAPTER 11: STEAM PIPING SYSTEM (1)
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
7 February 2012 Annekathrin Frankenberger (HEPHY Vienna) Open CO 2 Cooling System at the beam test Belle II SVD-PXD Meeting.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
MVD COOLING STATUS COOLING PLANT UPDATE: -ADDITION of the NEW CIRCUITS FOR GBT AND DC-DC Converter BOARDS IN THE COOLING PLANT -THERMAL STUDY OF GBT AND.
7/8/08 John Amann LC Mechanical Engineering LC 18M W Beam Dump Mechanical Engineering Design Updates.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ATLAS ID Services Mock Up - Proposal Presented by Ian Wilmut at DESY, update from John Hill 4th May, 20101ATLAS Upgrade - RAL.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH.
MVD COOLING STATUS COOLING PLANT: -UPDATE of THE HYDRAULIC SYSTEM -INTEGRATION OF THE MVD COOLING CIRCUIT PATHS INSIDE THE PANDA AREA -DEFINITION OF THE.
Guillaume Olry on behalf the IPN Orsay SPIRAL2 team TTC Meeting – Milan, 28 Feb-3 March 2011.
H.-G. Moser, April 25, 2016 Gemba Summary 1 Plan: Shipment (sea transport in summer) 6-8 weeks => arrival August/September Commissioning: After October.
MVD COOLING STATUS MVD COOLING PROJECT: CHOICE of COOLING FLUID,
LCWS11 WG4 Fully featured accelerating structure engineering design
Sampling Oil-Filled Transformers
Stator Plan & Schedule Chris Booth 2nd March 2009
Teleconf ACS – FREIA 28th March 2017
14 Refrigerant Recovery, Recycling, and Recharging.
Service channels between Tracker and PP1
Filter drilling status
Ti/SS transitions A.Basti INFN-PISA*
Service channels between Tracker and PP1
Safety approval of the installed copper cooling pipes
MVD Mechanics update EXTERNAL FRAME: NEW DESIGN
Proximity Cryogenics P&IDs meeting
cooling for BGV modules
Tracker cooling loop “check out” draft for discussion
1 Connect pumping equipment (group) with leak detector to insulation vacuum 1 or 2 pumping groups? connected to SB or CM or both? Which pumping group?
Tracker Outer Barrel COOLING Antti Onnela, CERN.
UT Integration meeting UT CO2 COOLING DISTRIBUTION SYSTEM
EHN1 Neutrino Installation Plans
Cassette Type Room Air conditioner 14th August 2016, Kuantan, Pahang.
Recirculating CO2 System
IBBelle: Status Commissioning at MPP Transport to KEK
Teleconference ACS – FREIA 20th February 2018
Instructions: Adding refrigerant fluid to system
SNS PPU Cryomodule Instrumentation
SC1R Cold Box PDR Assembly Sequence
Presentation transcript:

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 1 BGV cooling : status and plans reporting on behalf of EN-CV (Sylvain Nichilo & Olivier Crespo-Lopez)

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 2Introduction  Reminder: Valdir found that permeation of C6F14 through silicone invalidated this type of tubing –losses too large, too costly –Transfer lines: 14 g/hour Manifold lines: 9 g/hour0.7 kg/day !! Distributor lines: 6 g/hour  Decision: change to metal tubing, stainless steel and copper  EN-CV offers help (best effort basis)  BGV cooling will not be available before TS1 for sure, perhaps not even before TS2.

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 3 New circuit (draft sketch, Sylvain Nichilo EN-CV)  final sketch to come

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 4 Status: transfer line  silicone replaced by SS, re-used the insulation  10% of welds checked: OK.  pressure tested 16 bar OK, see  cleaned with demin water  insulation completed  then, under vacuum for many days (still now)

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 5 Status: manifold  Removed to lab (bldg 298, EN-CV)  Added metal (Cu ?) tubing to outside of box  Found substantial leak on several connections inside manifold –see movie on indico agenda page (this meeting) –use of Teflon in the threads ? –replace all teflon with adequate glue (have to remove all insulation) –EN-CV will require help (outsourcing) for redoing all insulation  Introduced a T with valve for evacuating air with a pump when we want to force filling the tubing with liquid.  Next: –pressure test, –re-do insulation, EN-CV: requests help for this task (outsourcing?) –re-install in TS1, EN-CV: help welcome!

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 6 Status: manifold

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 7 Status: distributors  Manifold-distributor lines –Removed all silicone tubing –EN-CV preparing in the lab (298) the metal tubing (Cu, 10/12mm), with insulation, in two «bundles» of 4 tubes –Re-using insulation, if possible  Distributors: –removed and to be re-used, –prepare in insulated boxes with outlet/inlets (swagelock SS)

BGV 23-feb-2016CERNMassimiliano Ferro-Luzzi 8 Status: detector tubing  Replace silicone with soft 4/6mm Cu lines  Connections to SiPM SS 3/4mm tubes: –Must validate if we can use all-metal (swagelock), with 30cm flexible SS tubes between module pipe and 4/6mm copper lines. (cost ~10kCHF?) –preliminary tests: 9 connectors on 3/4mm SS tested at 10 bar, no leak –fallback: 10cm piece of silicone between module pipe and copper line  expected C6F14 losses by permeation for 32 x 10 cm: 10 g/day.  Routing of copper lines will be tough –Tent to be un-installed, re-installed during TS (BE-BI) –10/12mm new tubing will enter behind the tent, lowest possible. –New support to be installed on top of the structure (BE-BI) –Modification of the tent after cooling pipe installation (BE-BI) as needed –Routing to be defined in situ with BGV  aim: same total length in+out for each SiPM tube from same distributor –start in TS1, try to finish in TS1, and if needed finish in TS2 –In any case, help welcome! (because TS is only 3-4 days effectively)