WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.

Slides:



Advertisements
Similar presentations
HFT Technical Overview September 26, HFT 2013 TPC FGT 2011 STAR Detectors Fast and Full azimuthal particle identification EMC+EEMC+FMS (-1 ≤ 
Advertisements

Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 Belle II IR 2 Shuji Tanaka KEK Joint Belle II & superB Background meeting 2012//Feb/ 8-9th 1.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
MicroTPCs in SuperBEAST Belle2 Inter Detector Meeting Sep Sven E. Vahsen University of Hawaii Belle2 IDM, Sep 1 '11Sven Vahsen, University of Hawaii1.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
FPCCD VTX Overview Yasuhiro Sugimoto KEK Tokubetsu-Suisin annual meeting 11.
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
Philip Burrows SiD meeting, Chicago 15/11/081 Progress on the LoI Philip Burrows John Adams Institute Oxford University Thanks to: Hiro Aihara, Mark Oreglia.
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
FPCCD VTX Overview Yasuhiro Sugimoto KEK Tokubetsu-Suisin annual meeting 11.
C. Kiesling, 1st Open Meeting of the SuperKEKB Collaboration, KEK, Dec , The DEPFET-Project: European Collaboration for a Pixel SuperBelle.
Lucie Linssen, PH senior staff meeting 23 Nov ’05 slide 1 EUDET Links: Public EUDET pages: Internal EUDET pages:
February, INP PAN FCAL Workshop in Cracow W. Lohmann, DESY The BCD (Baseline Configuration Document) The next calendar dates Where we are with FCAL.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Background Measurements During Commissioning Phase 2 (supplementary information for the BPAC) Prepared by the Belle II Beam Background Group.
Office of Baseline Change Proposal (BCP) Approval or Brief Presented by: Draft version Jun 16, 2015.
4/22/20131BEAST MEETING Reminder of BEAST TDR schedule (expected deliverables in red) April 19 th: – Draft specifications for each beast subsystem We need.
WBS 1.05 Commissioning Detectors Specifications & Design Sven Vahsen University of Hawaii.
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
US Belle II Project Overview Jim Fast Pacific Northwest National Laboratory.
Project Overview James Fast Pacific Northwest National Laboratory.
US Belle II Project – Technical Elements David Asner Pacific Northwest National Laboratory.
3/9/20131BEAST KEK CAD style figures needed For NIM paper: 1.Dcube-micro sideview (Marc) 1. for BEAST.
CERN Steve Kettell DUNE Collaboration Meeting January 12, 2016.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Office of Project Management Oversight and Assessments Office of Critical Decision-3 Approve Start of Construction or Brief Presented by:
WBS 1.04 KLM Leo Piilonen Virginia Tech. Talk Outline WBS Element Scope Performance Requirements Cost Summary Schedule Risks Summary January 2014Leo.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
L.Vitale INFN and Univ. Trieste
Camera PDR/CD1 Planning 19 September 2008
WBS 1.05 Commissioning Detector Specifications & Design
Jim Fast Pacific Northwest National Laboratory
Summary of Strasbourg Meeting
The interaction region and BEAST II
 Silicon Vertex Detector Upgrade for the Belle II Experiment
TC activities.
SVT subchapters & editors
Project Management W. J. Foyt
WBS 1.03 Readout Systems Scope, Cost and Schedule
CSP 25th November 2010 Technical agreement number 3: overview
KEK news ( ) S.Tanaka.
Ensuring a successful TPC production
News and brief overview of Beamline plans for the next few months
Overview of CLAS12 Calibration
Introduction to the Backgrounds Study in the BEPCⅡ/BESⅢ
Fast Kicker R&D in the Americas Region
ILC Detector R&D in Japan
STEP 8 - CLOSING PHASE: TRANSITION SUPPORT
Management Breakout: MREFC Budget Summary Victor L
IS&T Project Reviews September 9, 2004.
LERF Readiness Review: Charge
Electron Beam Systems ETC and Methodology
Fermi Lab – 2019 CMB-S4 Workshop
Preliminary Project Execution Plan
Test Beamline System Requirements and Charge to PDR Committee
SVD group organization, schedule, milestones
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii

Talk Outline WBS Element Scope Performance Requirements Cost Estimate Schedule Risk Summary Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Scope I: Objectives 1.Determine if dose rate safe for Belle II roll-in and later operation at design luminosity (Belle I: hole in beampipe and damage to silicon vertex detector) 2.Provide real-time measurements of luminosity and backgrounds (needed by SuperKEKB during beam commissioning) 3.Validate Belle II beam background simulation (Distinguish different beam background sources (Touschek, Radiative Bhabha, Beam-gas, Synchrotron) 4.System tests for Belle II (Beam abort system, moveable mask positions, pixel detector cooling, inner detector occupancies) Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Scope II: WBS Element Scope Lead design, simulation, DAQ integration (off-project) Construct support structure Prototype & construct PIN-diode radiation dose monitoring system Prototype & construct micro-TPC neutron monitoring system Perform acceptance tests at KEK WBS 1.5 Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Performance Requirements I Measurement of instantaneous and integrated radiation dose to ≤ 30% accuracy  64 PIN diodes with amplification circuits Sensitivity to synchrotron light  shield half of PIN diodes with gold paint, rest unshielded Identification of fast neutrons & measurement of recoil direction (resolution ≤ 15 ◦ )  8 micro- TPCs Rigid, non-magnetic mechanical support for all sub-detectors, with position accuracy ≤ 1 cm Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Performance Requirements II Pre-prototypes of both the PIN diode system and micro-TPCs have met and exceeded all Key Performance Parameters Documented in Technical Design Report More detail to follow in technical presentation January 2013Sven Vahsen, Belle II Directors Review (Pre CD-2/3)6

CD-1 Cost Estimate Only 3% of US project cost - but serves a critical role by protecting a large investment in Belle II January 2013Sven Vahsen, Belle II Directors Review (Pre CD-2/3)7

Cost Basis of Estimate Make up of cost estimate – 50% of estimate associated with labor, to finalize production specifications and construct TPCs, diode system, and support structure – Subcontract for TPC, diode system and support structure components and materials Maturity of the estimate – Engineering estimate based on prior experience on original Belle commissioning detector, CLEO dose monitor, and prototype costs for micro-TPCs for other R&D efforts – Pixel readout chip supply set aside at LBNL January 2013Sven Vahsen, Belle II Directors Review (Pre CD-2/3)8

Schedule Key drivers/constraints – Deliver PIN diodes, two prototype TPCs, mechanical structure, DAQ to support SuperKEKB accelerator turn-on in Jan 2015 (phase I) – Deliver 8 final TPCs for 2 nd SuperKEKB turn-on in Feb 2016 (phase II) – Demonstration of TPC prototypes before construction of 8 final TPCs – Availability of DOE FY14 funds for fabrication Prototyping Fabrication Acceptance Testing Design & Simulation Schedule shows calendar years January 2013Sven Vahsen, Belle II Directors Review (Pre CD-2/3)9

Major risks of WBS element 1.05 Initial elicitation completed prior to CD1 - all major risks mitigated: Reputation risk: commissioning detector fails to indicate dangerous rad environment and calorimeter is damaged – Mitigation: calorimeter not present during initial commissioning include multiple silicon diodes produce comprehensive documentation for commissioning detector procedures. Technical Risk: TPCs do not adequately detect neutrons. – Mitigation: testing of current prototype TPCs indicates ability to adequately detect neutrons in response to previous reviewer comments, supplemented TPCs with complementary thermal neutron detectors (He-3 tubes) (off project) Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Conclusion Scope of WBS 1.5 well understood – Specs validated by Technical Design Review – Similar to past commissioning at Belle and CLEO Costs are known and fit within funding profile – Costs defined by similar work – Fits funding profile Effective management structure in place – Clear reporting structure – Coordination with Belle II management – MOUs have been signed Project Ready for CD-2/3 Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

BACKUP SLIDES Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Management LVL2 manager: Sven Vahsen – Reports to PNNL Project management (Asner, Fast) + Belle II technical coordinator (Ushiroda) – Also leader of Belle II Beam Background group KEK contacts: H. Nakayama (deputy leader of beam background group) + S. Tanaka (Inner detector integration leader) – Report to Belle II Technical Coordinator (Ushiroda) Meeting & Reporting Schedule – Bi-weekly EVO meeting with subsystem leads (& others) Diodes: David Cinabro (Wayne State) Simulation, TPCs: Sven Vahsen (Hawaii) Luminosity Monitor: Minzu Wang (NTU) Tracking Detectors: Carlos Marinas (Bonn) – Weekly phone meeting with US Belle II PI’s – Monthly report to US Belle II management at PNNL Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013

Latest Belle II / SuperKEKB Schedule Two commissioning phases Key dates: Phase I (No QCS, No Belle Detector): Jan 2015 Phase II (QCS, Belle, no VXD): Feb 2016 Phase III (QCS, Belle, VXD): October 2016 (This plan has changed repeatedly. Our mandate is to be ready for any commissioning scenario.) Sven Vahsen, Belle II Directors Review (Pre CD-2/3) January 2013