CONFIGURATION MANAGEMENT AND CONTROL PLAN ESS Quality Assurance and Control workshop (30June) V. HENNION.

Slides:



Advertisements
Similar presentations
Configuration Management
Advertisements

1 PROJECT MANAGEMENT ROLE OF KEY PERSONNEL Bernd Madauss International Space University Strasbourg February, 2011
MODELING THE TESTING PROCESS Formal Testing (1.0) Requirements Software Design Risk Data Approved, Debugged, Eng. Tested Code Automated Test Tools Tested.
More CMM Part Two : Details.
SAE AS9100 Quality Systems - Aerospace Model for Quality Assurance
1 Certification Chapter 14, Storey. 2 Topics  What is certification?  Various forms of certification  The process of system certification (the planning.
Systems Engineering Management
APPLICATION OF EDMS TO XFEL CRYOMODULE ASSSEMBLY AT CEA Christelle CLOUE - Catherine MADEC.
Software Configuration Management
Effective Methods for Software and Systems Integration
Introduction to Software Quality Assurance (SQA)
Seattle Area Software Quality Assurance Group Release and Configuration Management, The Acceleration of Change and Its Contribution To Software Quality.
From Research Prototype to Production
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 Configuration Management “The Cookbook Approach”
Configuration Management Non Government Std: EIA Standard-649 “A management process for establishing and maintaining consistency of a product’s performance,
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
Configuration Management Romuald Duperrier Head of Systems Engineering Division April 22, 2015.
Manufacturing contracts for RFQ
Maintaining and Sustaining System Integrity Configuration Management for Transportation Management Systems Configuration management (CM) describes a series.
Configuration Management- Basic Concepts. Agenda  Configuration Management process Overview  Process Stages  Planning & Setup  Control  Audit  Case.
RISK REGISTER Management & Engineering
INTERFACES MANAGEMENT CRYOMODULES Vincent HENNION SYSTEM ENGINEERING ACTIVITIES.
ESS CRYOMODULE RISKS REGISTER ESS CRYOMODULE COMPONENTS AND CAVITY EXPERTISE Franck PEAUGER14th January 2016.
Gdansk International Air & Space Law Conference November 2013 Authority and Organisation Requirements “effective management systems for authorities and.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
H-ECCTD - KICK-OFF MEETING 16TH MARCH 2016 GENERAL INTRODUCTION Florence ARDELLIER.
ESS RFQ INTERFACES | Didier CHIRPAZ-CERBAT CEA-ESS INTERFACES.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
ASSEMBLY OF THE IFMIF CRYOMODULE Janic Chambrillon On behalf of the SRF-Linac Team TTC Meetting - June 5th – 8th, Saclay.
Introduction for the Implementation of Software Configuration Management I thought I knew it all !
SQA project process standards IEEE software engineering standards
Accelerator Readiness Review October 31, 2006
Software Configuration Management (SCM)
Configuration Management
Software Configuration Management
Software Project Configuration Management
Cryomodule test stand at ESS site
Software Configuration Management
SQA project process standards IEEE software engineering standards
Software and Systems Integration
Documentation (XFEL Naming convention, uploading…)
Configuration Management
6th srf collaboration lasa 13 June CAVITY interfaces - Vincent Hennion / PIERRE BOSLAND Bonjour, Franck Peauger, Je suis Ingénieur RF.
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
Software Requirements
Engineering Processes
Lockheed Martin Canada’s SMB Mentoring Program
HART Technologies Process Overview
Engineering Processes
F. Peauger (mainly for CM components)
Remote Handling Workshop Introduction
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL main evolutions between M-ECCTD and serie - Bonjour, Franck Peauger, Je.
ESSI CHANGE AND nonconformity control SYSTEM
PSS verification and validation
Configuration Management
Identification and marking of ESSI deliverables
Cryomodule Product Breakdown Structure and configuration traceability
Configuration Management
XFEL cryomodule production and Reliability improvement
ESS High Beta Cavities Quality Assurance and Control - Learning and Planning Workshops, CEA Saclay, 30 June - 1 July 2016 Mark Pendleton STFC, Daresbury.
Quality assurance and Quality control organisation
How Do We Define Acceptance of a Cryomodule? - A Discussion
DOE Review of the LCLS Project October 2006
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL SAFETY AND RAMI INPUTS - Franck Peauger OLIVIER KUSTER (INSTALLATION AND.
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
DOE Review of the LCLS Project 7-9 February 2006
10th srf collaboration LASA JUNE CAVITY interfaces - Vincent Hennion
Presentation transcript:

CONFIGURATION MANAGEMENT AND CONTROL PLAN ESS Quality Assurance and Control workshop (30June) V. HENNION

Extract from CMP, doc n° ESS , §1.2: « the CMP provides guidance for all personnel on configuration management activities in support of the ESS programme, including all subsystem teams and subcontractors. CM is applied to items selected as a specific subset of the work products, which constitutes the configuration. Once approved, the items under configuration control establish the baseline. In this respect, the baseline is a subset of the configuration. » This doc also says that CMP is designed to ensure that: Configuration identification and versions are defined and documented Which part of the configuration is the current baseline Documentation is identified, released and controlled The change control board (CCB) function is established Changes to the current baseline are evaluated and controlled Approved baseline changes are implemented and tracked Configuration status accounting is accomplished Principles for a configuration audit are established | PAGE 2 CEA Saclay/Irfu projet ESS | 02/06/2016 REQUIREMENTS

CONFIGURATION MANAGEMENT PROCESS ACTIVITIES Identification Certification (safety rules, …) Criticity (including prototypes qualification and associated documentation) Interfaces Appropriate PBS level (purchased component with SoW) Change control Description Classification / impact Decision authority Configuration status Reports Documentation system Configuration audit PMO meetings Change control process optimization Tests and controls on prototype and mock-up at Saclay | PAGE 3

OBJECTIVES AND CONTRAINTS FOR INTERFACES IDENTIFICATION Definition of the external interfaces Technical interfaces: limit of the responsibility Physical interfaces: connections (services, electronics, ICS…) Definition of the internal interfaces Functional interfaces: integration success and global performances achievement PBS Unavoidable contraints International collaboration: multilabs contributions (ESS, CEA, IPNO, LASA, STFC) for interdependant components require to be very formal Complex technical system Multi-site ESS Specific requirements in terms of massive COTS procurements (pumps, valves…) | PAGE 4 See Anaïs and Louise’s presentations for PBS

TASKS AND ASSOCIATED GOALS Elliptical Cavities CEA to provide to ESS (for LASA/STFC) interface drawings to be approved by ESS Cryomodules (called MBL or HBL EMR) CEA to provide to ESS interface drawings to be approved by ESS RFQ CEA to provide to ESS interface drawings to be approved by ESS Vacuum interfaces: definition under ESS responsibility Standardization of gaskets, type of valves, type of pumping system equipment? He cryogenic interfaces Lessons learnt from demonstrators for design simplification? (flexible parts, number of weldings vs complex geometry…) RF line interfaces Handling and Accelerator building interfaces Alignment interfaces Electrical interfaces Test stand interfaces | PAGE 5

INTERFACES IDENTIFICATION EXAMPLE FOR DESIGN PHASE | PAGE 6 definition Technical meetings Workshop with ESS and partners Specifications to describe the interfaces Preliminary configuration baseline verification Digital Mock-up drawings lessons learnt from demonstrators Tests measurement results validation CEA internal configuration audit Tools optimization Design review chaired by ESS Baseline Configuration to be approved by ESS for configuration management

CHANGE CONTROL A detailed procedure has been already prepared and approved CC implementation is deeply inspired from X-FEL project lessons learnt CC needed for ESS is even larger than integration activities covered for X-FEL Probably the most critical activity in configuration management CEA procedure includes the following processes: Description Decision to record / 3 levels classification / impact Decision authority CEA procedure is supported by the following tools: CR / NCR template documents Naming procedure CEA documentation system | PAGE 7 See Christelle’s presentation for CC

CONFIGURATION STATUS AND AUDIT Tracking is performed on Excel By QA/QC engineers Template documents are used Directly by subcontractors in companies without QAP By CEA/Irfu team To create a referenced CR/NCR from ones issued by subcontractors prior recording Record is performed on I2I Collaborative documentation management tool Developed and maintained by CEA Not fully intuitive and inadapted to manage much more documents (in series) Audit is performed by checking Configuration management efficiency internally at PMO level Compliance with technical specifications, tests plan… Compliance with procedures (manufacturing, assembly, control, test, alignment…) Compliance with aimed performances and acceptance criteria | PAGE 8 See Anaïs’s presentation for I2I

CONCLUSIONS Configuration management is being implemented at Irfu Lessons learnt from X-FEL project are a tremandous advantage for ESS Prototyping phase is consistent to set up and test the configuration management implementation at Irfu Sensibilization and training of the team is well advanced Traceability is ensured, CR and NCR are recorded Still open questions/issues Optimization of the implementation during the current prototyping phase Validation process with ESS regarding major CR/NCR ESS has to alert CEA for any change in DOORS about CEA contribution Proposal from ESS for a dedicated documentation management system used by all partners seems unavoidable | PAGE 9

DRF Irfu Commissariat à l’énergie atomique et aux énergies alternatives Centre de Saclay | Gif-sur-Yvette Cedex T. +33 (0) xx xx | F. +33 (0) Etablissement public à caractère industriel et commercial | RCS Paris B | PAGE 10 CEA Saclay/ESSI Project| 8 Feb16 Thank you for your attention! QUESTIONS?