Linac4-PSB 160 MeV connection readiness review Tuesday 30 August 2016 30 August 2016 Linac4-PSB 160 MeV connection readiness review 2.

Slides:



Advertisements
Similar presentations
C. Rossi – L4 Project Meeting 3 March 2011 Status and Plans of 3 MeV Test Stand.
Advertisements

LCLS-II Linac LLRF Control System – L1, BC1 Zheqiao Geng Final Design Review May 7, 2012.
LINAC4 STATUS Alessandra M. Lombardi for the LINAC4 team 1.Motivation and goals 2.Status of Linac4 2 years after official start of the project ( )
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
ADT re-commissioning after LS1 A. Butterworth, W. Höfle, F. Killing, G. Kotzian, T. Levens, D. Valuch with many thanks to BE/OP LBOC, ADT re-commissioning.
EPC Power Converters and the Linac4/PSB Beam Interlock System B. Mikulec, B. Puccio & J-L. Sanchez.
MEF - Machines & Experimental Facilities Linac4 project EN/MEF roles & responsibilities EN/MEF group meeting October J.Coupard1.
The Stripping Foil Test Stand in the Linac4 Transfer Line
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
PSB Finemet upgrade: overview, preliminary results & planning LLRF: M. E. Angoletta, A. Findlay, M. Jaussi, J. Molendijk, J. Sanchez Quesada (RF/FB, RF/CS)
LLRF FOR CHOPPER Grégoire Hagmann Philippe Baudrenghien BE/RF/FB February 24th, 2013.
LIU Day – 11 th april 2014 ALESSANDRA LOMBARDI LINAC4 COMMISSIONING OVERVIEW.
Stéphane Gabourin on behalf of TE/MPE-EP MPP Linac4 – 9 th July 2015 BIS installation in Linac4 For 50 MeV operation.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
RF system & magnetic PU ELENA review meeting CERN, November 2015 M.E. Angoletta, S. Hancock, M. Haase, M. Jaussi, A. Jones, J. Molendijk, M. Paoluzzi,
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
1 1.Summary of H- source review 2.Options for connection to the PS Booster 1.Summary of H- source review 2.Options for connection to the PS Booster.
LIU-PSB BIS presentation / Christophe Martin TE-MPE-EP 28/02/ Beam Interlock System for Transfer Lines & PS Booster Christophe Martin TE/MPE/EP.
PSB ring inhibit in the Linac 4 era A. Blas PSB LIU meeting 07/03/ Summary of discussions involving (mainly): Jose-Luis Sanchez Alvarez Philippe.
ELENA: Commissioning & operation ELENA beam commissioning Operation 12/11/2015T.Eriksson CERN BE/OP/AD1.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
E. Benedetto, 24/04/14, LIU-PSB Meeting, MDs planning for 2014 MDs planning for 2014 E. Benedetto Thanks: G. Rumolo, B. Mikulec and the RF, OP, ABP, BI.
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Radio-Frequency (RF) & Schottky diagnostics WP for ELENA Maria Elena Angoletta, BE/RF on behalf of the CERN RF group First ELENA construction meeting CERN,
Digital LLRF: achievements and LS1 plans M. E. Angoletta, A. Blas, A. Butterworth, A. Findlay, M. Jaussi, P. Leinonen, T. Levens, J. Molendijk, J. Sanchez.
Linac4 status and long-term schedule M. Vretenar, Project Meeting  status  timeline  open issues  status  timeline  open issues.
DLLRF: existing & possible applications M. E. Angoletta, M. Jaussi, J. Molendijk, J. Sanchez-Quesada CERN, BE/RF Finemet ® Review, September 2015.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
CS section activities Industrial controls Luca Arnaudon David Glenat David Landre Slawomir Totos Ruben Lorenzo-Ortega Digital hardware John Molendijk.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
Readiness for RF capture Cavities – all 16 cavities commissioned with RF feedback loops closed klystron polar loop still to commission on 2 cavities 2.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
Operation Status of the RF Systems and Taiwan Photon Source
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2.
CC LLRF SM18 test plan and BA6 infrastructure
Linac4 status and perspectives
ICE SECTION The coolest place to be! Elias Métral
Experience with beam instrumentation at Linac4
Controls & software Andy Butterworth.
J.-L. Sanchez Alvarez(PSB-EIC)
R. Denz, A. Gomez Alonso, AT-MEL-PM
Updated with comments 22 may 2017 Updated again 29 June 2017
Impact of the current debuncher limitations (…can we get rid of longitudinal painting?)
Alternative/complementary Possibilities
Risk Assessment / Mitigation / Spares
Injectors BLM system: PS Ring installation at EYETS
LINAC4 50 MeV phase BIS STATUS
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
LIU, ABP-CWG, PBC, miscellaneous
RF operation of REX-ISOLDE
Update on the HiLumi/LIU parameters and performance ramp up after LS2
Linac4 RF System Operation for the Reliability Run in 2017
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Update on Linac4 Status, Reliability Run and Modelling
LLRF: M. E. Angoletta, A. Findlay, M. Jaussi, J. Molendijk, J
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Superbeams with SPL at CERN
LLRF and Beam-based Longitudinal Feedback Readiness
Operations Department
LINAC4 commissioning plans etc.
Progress towards Pulsed Multi-MW CERN Proton Drivers
Advanced Research Electron Accelerator Laboratory
RF introduction Anders Sunesson RF group leader
PSB – Linac 4 Interfacing
Maria ELENA Angoletta for the RF team
Presentation transcript:

Linac4-PSB 160 MeV connection readiness review Tuesday 30 August August 2016 Linac4-PSB 160 MeV connection readiness review 2

BE-RF Maria Elena Angoletta, L. Arnaudon, P. Baudrenghien, A. Blas, G. Hagmann, S. Ramberger 30 August 2016 Linac4-PSB 160 MeV connection readiness review 3 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Table of Contents: Equipment overview Equipment dismantling Equipment installation Risks / Mitigation Additional information Summary Other contributors for L4: B. Bielawski, R. Borner, O. Brunner, B. Kremel, D. Landre, P. Martinez-Yanes, S. Papadopoulos, R. Wegner. Other contributors for PSB: A. Findlay, M. Jaussi, J. Molendijk, J. Sanchez-Quesada, J. Simonin.

Equipment overview 30 August 2016 Linac4-PSB 160 MeV connection readiness review 4 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Source Debuncher 180 m Distributor PSB LLRF RF interlock System PSB BOR  L4 chopper-PSB synchronization signals generation [BE/CO]  CCC application programs: longitudinal painting, RF interlock system, PSB cruise control, Linac4 operation … [TE/ABP, BE/OP] Linked topics Pre-chopper +LEBT Chopper LLRF = topics considered in this presentation LLRF rack

Equipment dismantling 30 August 2016 Linac4-PSB 160 MeV connection readiness review 5 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF NB: Half Sector Test equipment de-installation (not under RF group’s responsibility) needed to install debuncher cavity.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Equipment installation: L4 LLRF 6 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Longitudinal painting not needed for initial operation Only RF-expert tools so far Upgrade of field regulation algorithm for improved beam loading of beam batch.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Equipment installation: debuncher 7 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Not needed before April 2017

30 August 2016 Linac4-PSB 160 MeV connection readiness review Equipment installation: RF interlock 8 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Possibly additional CCC application (or integration within PSB Cruise Control)  PSB RF Interlock system: interfaces Linac4 BIC, Linac4 Chopper, beam over-intensity detector, PSB RF cavities, PSB LLRF, CCM.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Equipment installation: PSB LLRF 9 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF  Bunch-to-bucket transfer needs rings injection syncro.  PSB new LLRF installed in 2014: h/w channels for injection synchro already included.  S/w upgrade during Sept 2016 TechStop. PSB MDs in Oct-Dec 2016 to commission the injection synchro.  Modified LLRF after LS2 (Finemet HLRF) → re-commissioning needed.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Linac4 will have run up to 160MeV by Dec However not yet sufficiently reliable: ● No automatic start-up of RF power systems ● No automatic cavity reconditioning ● Limited tools for operation - so far only expert tools by RF group. ABP / OP not yet involved in this! ● Running in 27 RF systems: availability of overall system potentially low (teething problems). → We are far away from what users are used to with Linac2

30 August 2016 Linac4-PSB 160 MeV connection readiness review Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF ● Linac4 can deliver 20 mA MAX due to LEP klystrons in CCDTL structures. By further tweaking and/or an exchange of a klystron, 25mA (target current) should be reached. ● Exchange of 1 MW LEP klystrons with new 2.8 MW klystrons is required to deliver 40 mA average current (full design current). ● Linac4 performance is limited by the source in the first place. As long as the source is not capable of delivering more beam, the upgrade is not required. ● The purchase of further new klystrons is being prepared. Aim: to be ready by end LS2.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Current debuncher amplifier: ● Part of French in-kind contribution to Linac4 ● Delivers ~45kW on the cavity, sufficient to run the cavity ● Offer for amplifier upgrade ~100 kCHF. Upgrade requires 6 months & should be ready for start up in o without nominal current or o with full phase space very low current ( few mA) or o some intermediate testing scenario. ~March 2021

30 August 2016 Linac4-PSB 160 MeV connection readiness review Risks / Mitigation – 3 cont’d 13 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF Debuncher amplifier upgrade ● Amplifier upgrade (45 kW to ~ 70 kW on the cavity) required to implement nominal current. ● In case of upgrade, the current amplifier must be sent to the supplier for ~6 months. ● If started in October, the upgrade is in line with the reliability run and should also be in line with the required work for a rapid L4- PSB connection. ● In case the upgrade is not undertaken, a full new amplifier would cost ~2x as much at today’s market prices plus additional CERN man-power for follow-up.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF ● : PSB Finemet LLRF years! Extensive MD planning to validate new implementations (e.g.: higher BW cavity loops). ● LEIR experience (parallel control of 2 Finemet cavities since July 2016 LLRF upgrade) will also be useful.

30 August 2016 Linac4-PSB 160 MeV connection readiness review Additional information 15 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF  Manpower: scarce! ● → careful projects prioritization needed ● Must have balance between h/w- and s/w- related resources to allow consistent progress. ● Support infrastructure for Linac4 operation to be put in place. Piquet service for ● Need tools/manpower from ABP (OP?) to operate Linac4 from 2017 onwards.  Not ready yet to switch over tomorrow: in case of Linac2 failure, we will obviously find a way, but then priority for Linac4 would be higher than LHC!

30 August 2016 Linac4-PSB 160 MeV connection readiness review Summary 16 Equipment status (Linac4 and LIU-PSB) Maria Elena Angoletta - BE/RF ● Lots of progress … and still lots to do! ● Linac4-PSB connection after December 2016 feasible but with limitations in operation reliability and performance. ● Decision on Debuncher amplifier upgrade to be taken asap. ● Manpower issues:  clear prioritization of projects.  support from ABP/OP for Linac4 running ≥ 2017.