TPC Support Installation 26 Apr 2016Dan Wenman Mechanical Engineer1 Overview Installation of the support rails Details of the rail from the SAS to the.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Design of the T962 Cryostat L. Bartoszek BARTOSZEK ENGINEERING 5/10/07.
Click on this image to open the full PDF document.
SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
TPC Proposal for the 35 Ton Liquid Argon Test Abstract We propose to equip the 35 ton cryostat with one APA and two CPA’s, and all the necessary equipment.
NTOF11 Hg System Design Status Van Graves Tony Gabriel, Phil Spampinato Collaboration Meeting – Princeton University Apr 2005.
PXL insertion 1.PXL Insertion Steps after PXL installation system is aligned 2.PXL removal steps 3.Some design details 2/3/20131 Table of contents:
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
Installation. Indoor Unit Installation Typical Installation.
Rolling element bearings A. Lozzi 09
7/28/03P. Kroon AEROGEL Assembly of Cells into 80-cell Array: –8 cells wide by 10 cells high mm high (Y) by 2077 mm wide (Z) by about 335 mm deep.
ISHELL Design Review Cryostat & Optics Bench Dan Kokubun 9/11/2013.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Chapter 4: Equilibrium Equilibrium means balance of forces to prevent body from translating, and balance of moments to prevent body from rotating. Vector.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
SAM PDR1 SAM LGS Mechanical Design A. Montane, A. Tokovinin, H. Ochoa SAM LGS Preliminary Design Review September 2007, La Serena.
ZDC/Dummy Absorber Exchange Crane Proposal Paul Debbins Ianos Schmidt Univ. of Iowa - Nov. 5, 2007.
INTER-LAKES BASES PRODUCTS. MODEL B-75 MACHINE BASE B-75 Model with panels and doors.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
Assembly Scenarios Draft 1 MODEL simulation based on CXUO-CRY-AP-001.
ILC / ILD TPC Requirements of the support mechanics Volker Prahl ILD Workshop 2013 Cracow
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
NUMI Transmission Line (TL) Review: Design Details TL through Block & Beyond Design/Status Bill Boettinger FNAL April 23, 2003.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
11/30/20151Robin Lafever The existing 300 K Flange This is certainly an older version but is useful to illustrate The proposed modifications.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
Long Bo for LAPD Hans Jostlein10/20/2011 December 15, 2015 Long Bo for LAPD 1.
Long Bo FT and Flanges April 12, 2012 talk Hans Jostlein 12/19/2015Long Bo FT and Flanges1.
SLHC Engineering Upgrade FCAL Remove-Install step by step procedure. Mircea Cadabeschi-University of Toronto March 01,
A-Frame Operation The A-Frame will provide support for odd shaped loads, loads where you are unable to get directly below the load, and for stabilizing.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
Dual-Phase ProtoDUNE Detector Installation : Plans & Constraints Adamo Gendotti.
Single phase ProtoDUNE detector installation Plans and Constraints Jack Fowler Duke University 23-Feb-2016.
G-10 CPA March 2016 Bill Sands. Design Criteria Structure must support the CPA panels and Field Cage Differential contractions must be identified and.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
ORKA support - status report Scope of conceptual design task Develop a conceptual design for how to support the ORKA detector inside the CDF detector Develop.
Page 1 GSI, Hydraulic Actuators for PANDA Target Spectrometer Jost Lühning, GSI Darmstadt Functional Specifications for moving the TS: Two synchronous.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Recent Changes to the FD TPC Design Bo Yu Oct. 20, 2015.
Single Phase ProtoDUNE TPC CERN The SP TPC Team Jan. 13, 2016.
Engineering Mechanics
Miscellaneous MEC Topics Mainz, CM September 2016, MEC Session J
Planning for Proto-DUNE PD Installation and Cabling at CERN
ProtoDUNE – DSS Installation, Alignment and QA
SBN Far Detector Installation & Integration
SX1 manipulation VERSION 1 Version
Escalator Installation
Instrumentation Used in LAPD and 35T Runs (Dune DocDB 1759)
MICE Partial Return Yoke Mechanical Design
INSTALLATION SEQUENCE
Endcap shielding senarios:
Platform for Target Spectrometer using linear montion drive Rexroth
FRESCA2 Update on the dipole design and new calculations
Warm structure requirements :
NP04 CPA/FC/HV Interfaces
Requirements of the support mechanics
CPA Moment on the left is ~100*150kg/2.
Pressure vs height (solid CPA plane)
TPC Support and Constraint TPC Support
Test box for ProtoDUNE SP – Integration Test
Initial BIS installation
Cryomodule Assembly Plan
FS ” Maximum Blade Capacity 9 HP Honda engine Weight – 141Lbs
as a prototype for Super c-tau factory
Bunker Wall Design Wall ESS
Presentation transcript:

TPC Support Installation 26 Apr 2016Dan Wenman Mechanical Engineer1 Overview Installation of the support rails Details of the rail from the SAS to the clean room Requirements to the warm structure, accuracy of feed thrus, height accuracy and survey, support of crossing tubes, loads translated to warm structure

26 Apr 2016 Dan Wenman Mechanical Engineer 2 Overview of support Support tubes APA rail CPA rail APA rail Beam window side Fixed point X Y Y beam X beam Flange on cryostat Support tube APA trolley Installation: 1.Install the 6 support tubes above the APA rails. 2.Lift the y beams through the center penetration and secure the beams at the ends. 3.Install remaining tubes and connect beams at midpoint. 4.Rig the x beams through the cable penetrations and mount them. Roller mounted beams and slotted holes between support tube and y beam allow for relaxed tolerances on the penetration locations.

26 Apr 2016 Dan Wenman Mechanical Engineer 3 x y “Compressed” view of support Y beams are fixed at the midpoint in x, y, and z and allowed to contract towards y = 0. X beams are constrained on the beam window side to minimize moment with respect to the beam window. X beams are free to roll in y for installation After installation, the middle x beam is locked to the y beam. As the Field cage shrinks, the outer 2 x-beams are pulled to the center. APA trolleys closest to the beam window will be constrained after installation. Beam window side Fixed point Trolley stops x6 not shown

26 Apr 2016 Dan Wenman Mechanical Engineer 4 Beam Trolley Design Considering Barden bearings which have been tested in LAr and gaseous Argon. Also considering bearings with ceramic balls – sizing minimum SF of 3 Articulating connection allows for load sharing due to tolerance and roof deflection Dry bronze bushing – to be purity tested

Support Beam Pivot Beams will have to pivot in center to protect support system from stresses that would applied with roof deflections LBNF design from Russ Ruzinski Design in progress 26 Apr 2016 Dan Wenman Mechanical Engineer 5

Vibration isolation – If needed 26 Apr 2016Dan Wenman Mechanical Engineer6 It is best to eliminate vibration at the source, but if not possible the maybe TPC could be spring mounted. The low frequency spring mass system would not transmit higher frequency disturbances near the wire natural frequencies. Vibration isolation Seal > O-ring would simplify Dry running sleeve bearings to react moment from beam roller friction Purge port Cryostat flange TPC support tube

Height adjustment 26 Apr 2016Dan Wenman Mechanical Engineer7 Survey target mount point Height adjustment The TPC will be designed to be flexible enough to accommodate Thermal contract and expansion and the anticipated roof movements. At installation, the height of the TPC support tubes will set to anticipate the roof distortion expected during the operating state of the cryostat. If necessary, adjustments can be made with a cold TPC

Support of the TPC to the cryostat roof 26 Apr 2016Dan Wenman Mechanical Engineer8 Installation of the support rails Note: Largest rail will be ~ 4 m long and 130 kg Fork lift or rail lifting tool is probably needed to deliver the beams through the TCO. Transport options inside the cryostat Beam delivered with casters (preferred) Beams delivered before roof is installed (unlikely?) Once in position, the beams would be temporarily spliced for lifting.

Support of the TPC to the cryostat roof 26 Apr 2016Dan Wenman Mechanical Engineer9 Installation of the support rails Mounting rails Connect a plate to splice the beam and a post assembly to the top of the beam to splice the joint and to provide a stable lifting point above the c.g. Lift the beam through the center port. Secure beam at north and south end. Disconnect the crane from the center point. Repeat remaining y rails Lift x rails from the y rails Comment: This method requires multipoint access from inside.

26 Apr 2016 Dan Wenman Mechanical Engineer 10 Details of the rail from the SAS to the clean room 4m long beams will be lowered into horizontally into the SAS Casters maybe used to move to hoist coverage in clean room if needed.

Requirements to the warm structure, accuracy of feed thrus, height accuracy and survey, support of crossing tubes, loads translated to warm structure 26 Apr 2016Dan Wenman Mechanical Engineer11 Current concept has some compliance to errors in the feedthrus. However it is important for the fixed point to be positioned accurately … ~3mm. Also if the flange is not level on the top of the cryostat the ~2m length of the penetration could cause a lot of error at the support point mount points. Will need to survey the mounting surface to the support tubes for position and level. Would be nice to know more details about what is being supplied to mount the support tube to.

26 Apr 2016 Dan Wenman Mechanical Engineer 12 Loading with 2.5 meter gap Estimated dry weights of components: 582kg 1281lb 464kg 1020lb 582kg 1281lb 655kg 1442lb 1481kg 3258lb 1224kg 2692lb 1487kg 3272lb 900=APA weight (lbs) 880=FC weight top and bottom together (lbs) 935=EW one corner (lbs) 285 =CPA 1/2 wide COLUMN (lbs) 500=BEAM weight (lbs) 16707=TPC and beam weight (lbs) 409=APA weight (kgs) 400=FC weight top and bottom together (kgs) 425=EW one corner (kgs) 130=CPA 1/2 wide COLUMN (kgs) 227=BEAM weight (kgs) 7594=TPC and beam weight (kgs)

8 Mar 2016 Dan Wenman Mechanical Engineer 13 Roof load requirements – Two worst cases N 1330 N 2846 Nm 2099 lbf N 589 N 1560 Nm 1150 lbf 200mm crossing tube Crossing tubes will be reinforced to the warm structure 200mm crossing tube

26 Apr 2016 Dan Wenman Mechanical Engineer 14 Back up slides

Safeway Suspension products Can pass through small openings

Aluminum plank jack systemSuspended scaffolding

Scaffold used for DayaBay

26 Apr 2016 Dan Wenman Mechanical Engineer 18 Top view of cryostat showing proximity of the cable penetration feedthrus to the support rail feedthrus

Support of the TPC to the cryostat roof 26 Apr 2016Dan Wenman Mechanical Engineer19 Installation of the support rails Mounting y rails option B Use two building crane hooks and two long straps Send one strap through the penetration above the north end of the beam and lift one support tube with extension and connect it to the north end of the beam Repeat for the south end. Lift the beam with the support tubes and thread through the penetrations. Block the support tubes in position Remove the extensions Slide bushing housings over the support tubes Transfer the load to the crane hook and remove blocking Mount bushing housing and transfer the load back to the housing Lower and secure the center support tube from above and from inside connect the beam.

26 Apr 2016 Dan Wenman Mechanical Engineer 20 Draft illustration of mounting y rails option B Special housing Extension Blocking