POPS-B Project Update 07 June 2016 POPS-B: Project update and Feedback from POPS Experience LIU-PSB Meeting 175 07 June 2016 Fulvio Boattini TE/EPC 2.

Slides:



Advertisements
Similar presentations
CLIC Workshop 2009 Power Converters implications for CLIC machine protection 25/05/2015TE-EPC / S. Pittet1.
Advertisements

September 2014 Lesson Learned Summary. September 2014 LLs 2 Three NERC lessons learned (LL) were published in September 2014 LL Redundant Network.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
SAFETY FOLLOW-UP HL-LHC PROJECT WP17 – Infrastructures meeting S. La Mendola, Jose Gascon DGS/SEE 09 July 2015.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
PSB Main Power Supply Serge Pittet Jean-Paul Burnet, Karsten Kahle, Fulvio Boattini, Max Chamiot-Clerc TE-EPC Serge PITTET LIU-2011 Event, 25/11/2011.
Lesson 9: Electrical Components
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
Power converters implications for Booster Energy Upgrade Jean-Paul Burnet, Serge Pittet LIU day, TEEPC.
Golden Valley Electric Assoc. Inc © 2012 GVEA. All rights reserved. GVEA BESS Expected and Actual Performance Dan Bishop Golden Valley Electric Assoc Fairbanks,
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
Interlock System Equipments for Conventional Magnets PP a-ABT_interlock conv mag.ppt October 22, 2015 Anthony Beaumont Interlock System Equipments.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
Progress with POPS Jean-Paul Burnet TE/EPC IEFC workshop, Feb 2010.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini TE-EPC TEEPC.
Power Plant Construction and QA/QC Section 4.4 – In-Plant Electrical Distribution Engineering Technology Division.
EN-CV interventions during YETS
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
LHC machine status ~ Daily Summary ~ Daily beam commissioning meeting Week 42 - October 14 th, 2015 CERN, Geneva, CH M. Lamont and S. Redaelli for the.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
1 S-FRS Magnet Test Bench SuperFRS Magnet Test Bench Power Converter Status H. Thiesen 13 May 2015.
Serge Pittet (Work-Package holder) Konstantinos Papastergiou (Work-unit: Sirius converters) CERN Technology Department | Electrical Power Converters 12.
Vault Reconfiguration IT DMM January 23 rd 2002 Tony Cass —
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
EHN1 – EN/EL Progress update J. Devine 25/02/16. Integration – Jura Substation Position updated to avoid clash with door. Meeting next week for Civil.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
Uninterruptible Power Supply Improves Reliability at The Australian Synchrotron Sean Murphy – ARW 2013 Melbourne.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
POPS: Power for PS A novel 60 MW Pulsed Power System based on Capacitive Energy Storage Jean-Paul Burnet June 2010.
FESS/Ops Shutdown Summary Week Ending 3Aug12. CUB Shut-Down Activities Shut Down Plant on July 21 hrs. Electrical – High Voltage Air Switch/Fuse.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
S A Griffiths CM42 June 2015 Electrical & Control.
The Survey of the Power Supply Reliability at SSRF
ABT-EC EYETS Activities 2nd reports
Situation of the Static Var Compensators at CERN.
TE-EPC internal review of the ELENA project
Feedback from POPS-B explosion analysis
3AH5 Vacuum Circuit-Breaker For Standard Applications
EYETS David Hay EN-OSS.
LIU – EVM status and next steps
RELIABILITY OF 600 A ENERGY EXTRACTION SYSTEMS
Project Manager’s Report + DC/MoM Report
The LHC - Status Is COLD Is almost fully commissioned
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
B245 Modifications & Cabling Update
Status with crucial LSS5 kicker transmission line cables
East Hall under construction
POPS Strategy for Restarting & Repairing
3AH5 Vacuum Circuit-Breaker For Standard Applications
3AH5 Vacuum Circuit-Breaker For Standard Applications
East Hall under construction
East Area Renovation Supply of control rooms b.157
Review Bloc 4 and SM18 facilities and upgrade
Linac4 Connection Broken Line 07/08/19
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

POPS-B Project Update 07 June 2016 POPS-B: Project update and Feedback from POPS Experience LIU-PSB Meeting June 2016 Fulvio Boattini TE/EPC 2

POPS-B project power converters; POPS-B project Status: B245 civil engineer; Equipment integration; Purchase orders; Activities until Eyets; POPS experience feedback on POPS-B; Planning update; Contents

POPS-B main power converters Spare POPS-B project power converters

POPS-B main power converters Spare POPS-B quadrupole converters POPS-B project power converters

POPS-B main power converters Spare POPS-B quadrupole converters POPS-B Injector Trims converters POPS-B project power converters

POPS-B project Status: B245 civil engineer B245 construction is completed

POPS-B Project Update 07 June POPS-B project Status: B245 civil engineer … and now installation starts Converter hallFalse floor Loading platform Capacitors room EN/EL Room EN/CV Room Ref magnet Room

POPS-B Project Update 07 June POPS-B project Status: equipment integration Air Conditioning Cooling towers Power transformers Main PCs Config Switches Trims Cable ladders & pipes Ref magnet Quads Magnetics Storage caps

POPS-B Project Update 07 June POPS-B project Status: POs POPS-B purchase orders until EYETS: Main Power Converters (6 MCHF): Done April 2016 Power cables (200 kCHF): Planned for next week Cooling & Ventilation system: Planned October 2016 Main Power Transformers (200 kCHF): Planned March 2017 Storage Capacitors (2 MCHF): Planned January 2017 QTR Dummy load and MPS spare (160 kCHF): Planned September 2016 Injector Comet (210 kCHF): Ongoing (126 kCHF so far)

POPS-B project Status: activities until EYETS B245 lightning & 1 st part of cable ladders Configuration switches installation False floor & 2 nd part of cable ladders Aux power cabinets installation Power cabling (B245 to B271) Cable ladders for dummy load (b367) MPC kick-off FC storage capacitors PO power transformers FC CV Plant

POPS-B Project Update 07 June First fault on power converter side: Lesson learned: failure on one leg propagates to all DCDC converter Second fault on power converter side: Lesson learned: need to test repaired stacks before restarting. Fault on storage capacitors: Lesson learned: capacitors can fail and release lots of energy POPS experience feedback on POPS-B Recall

POPS-B Project Update 07 June POPS experience feedback on POPS-B POPS experience feedbacks: Reduce the fault energy in case of capacitor short circuit Study alternative protections in the power converter Build an off-line testing platform Improve design of capacitors with ageing tests Improve design of capacitor room following explosion analysis

POPS-B Project Update 07 June POPS experience feedback on POPS-B POPS experience feedbacks: Reduce the fault energy in case of capacitor short circuit Fuses blown very quick strongly limiting the energy losses Limit damages to ¼ of the capacitors Implementation ongoing for POPS

POPS-B Project Update 07 June POPS experience feedback on POPS-B POPS experience feedbacks: Improve design of capacitors with ageing tests 2 x Removed for film analysis 600 h left 370 h left 720 h left Ageing + discharge tests shall be completed by October 2016 Additional tests to prove resistance to short circuit

POPS-B Project Update 07 June POPS experience feedback on POPS-B POPS experience feedbacks: Improve design of capacitor room following explosion analysis Pressure wave calculation Effects on the structure Possible remedies (POPS) PO for consultancy to be released in the next days (60kCHF)

POPS-B Project Update 07 June POPS experience feedbacks: Study alternative protections in the power converter Fast DC circuit breaker Build an off-line testing platform Check repair before restarting Design ongoing POPS experience feedback on POPS-B

POPS-B planning update Late modification of the B245 BC Additional 4 months to build Main PCs Main PCs installation and commissioning shrinks

POPS-B Project Update 07 June Thank you for your attention Questions ?