WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011
Introduction: WBS 1-7 WBS 1-7 covers assembly of the active detectors and their installation into the cryostat vessel, transportation and installation of the detector in the experiment hall, and installation of all supporting systems (electronics, cryogenics, etc.) in the experiment hall. WBS 1-7 Level 2 Tasks Installation Project Management Installation Planning and Integration Readout Racks and Cabling Plan Installation Execution The installation team (WBS 1-7 & WBS 1-10) serves as the primary interface agent between the subsystems during the installation process. 2August 10-11, 2011CD-2 Review of the MicroBooNE Project
Detector Scale 3August 10-11, 2011CD-2 Review of the MicroBooNE Project TPC Cryostat
WBS 1-7 System Installation WBS (Project Management) Voirin & Raaf WBS (Installation Planning & Integration) Voirin & Raaf Coordinate with WBS 1-10 for integration with other subgroups WBS (Readout Racks & Cabling Plan) Coordinated by Linda Bagby/Dave Huffman WBS naturally divides into two major sections: : Assembly Site Installation (Raaf) : Experiment Site Installation (Voirin) 4August 10-11, 2011CD-2 Review of the MicroBooNE Project
WBS Readout Racks & Cabling **Dave Huffman and Linda Bagby** Equipment placement based on several factors: System technical requirements Proximity to cryostat port Ease of maintenance and troubleshooting Operational Readiness Clearance requirements Labeling will follow experiment naming convention Rack equipment tested before move to enclosure Installation training program 5August 10-11, 2011CD-2 Review of the MicroBooNE Project
WBS Readout Racks & Cabling Major tasks: Rack Protection Smoke Detection/AC Distribution TPC readout PMT readout Trigger High Voltage Drift High Voltage TPC Wire Bias PMT High Voltage Low Voltage Cold Electronics Power Purity Monitor Cryogenics Control and Monitoring DAQ and Monitoring computers PORC of Electronics 6August 10-11, 2011CD-2 Review of the MicroBooNE Project
WBS Assembly & Installation Major Assembly tasks: Preparation of clean area for active detectors assembly Final preparation and cleaning of cryostat vessel Installation of cryo system devices (temperature & purity monitors, heaters) Assembly of TPC and installation into vessel Assembly and installation of PMT system Preparation for transport to experiment hall Major Installation tasks: Rigging crew transport of assembled detector to experiment hall (LADTF) Installation of detector in LADTF Contractor execution of vessel insulation Installation of cryogenics system pumps, piping, controls, etc. Installation of electronics racks, cabling, etc. (L. Bagby/D. Huffman) Relocation and installation of LN 2 dewar 7August 10-11, 2011CD-2 Review of the MicroBooNE Project
Rigging 60 ton load 8August 10-11, 2011CD-2 Review of the MicroBooNE Project Yay! We loves big machines!
Cryogenics: Required Components Systems LN 2 Supply LAr Supply Gaseous Ar Vent Analyzers Vacuum System H 2 Ar Supply Ar Gas Miscellaneous valves and instrumentation N 2 Vent LAr Recirculation N 2 Supply LN 2 Dewar system Water lines for cooler/turbos Argon Cool-down system Heater System on Vessel 9August 10-11, 2011CD-2 Review of the MicroBooNE Project
Process flow Diagram 1 10August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cryogenics Installation Major tasks: Installation of Cryo controls system Checkout of Cryo system with controls 11August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cryogenic System 12August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cryogenic System 13August 10-11, 2011CD-2 Review of the MicroBooNE Project
Overall Work Plan Vessel design is an integration of all WBS sections Fabrication by vendor Installation by contract rigging and FNAL technicians TPC & PMT systems assembly and installation in vessel Fabricated parts delivered to FNAL Assembly by FNAL technicians and MicroBooNE collaborators Oversight by WBS 1-4 (TPC), WBS 1-8 (PMT), and WBS 1-7 Electronics installation at LADTF Electronics technicians with oversight from FNAL electrical engineer Cryogenics design is primarily from FNAL PPD Installation will be by FNAL mechanical technicians System check out will be by electrical and cryogenic engineer, assisted as needed by technicians. 14August 10-11, 2011CD-2 Review of the MicroBooNE Project
Work Plan : Integration Design Integration Installation plan, Vessel handling, Assembly area options, work out the details. Develop requirements for each deliverable. Develop Installation procedures and Hazard analysis. Construction Integration Layout Assembly area. Post Beneficial Occupancy electrical work. Finalize plans. Receive and inspect components. Update Interface Agreements as needed 15August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cost Summary 16August 10-11, 2011CD-2 Review of the MicroBooNE Project 1-7.4
Cost Drivers: Racks & Cabling Electronics Racks & Cabling Labor (XX% of total cost for 1-7.3) o Technicians M&S (XX% of total cost for 1-7.3) o Racks & cabling o Fighting off unwieldy cables 17August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cost Drivers: Assembly Assembly Labor (89% of total cost for ) o Technicians o Alignment/Survey crew M&S (11% of total cost for ) o Clean area tents and supplies o Vessel cleaning contract 18August 10-11, 2011CD-2 Review of the MicroBooNE Project
Cost Drivers: Installation Installation Labor (XX% of total cost for ) o Technicians o Alignment/Survey crew M&S (XX% of total cost for ) o Welders & Tigers & Bears, Oh My! o Pickin’ up stuff with big cranes 19August 10-11, 2011CD-2 Review of the MicroBooNE Project
Schedule Overview (Assembly) Occupy D0 assembly and prepare working areas (assemble tents, etc.) – Jan 2012 TPC parts begin arriving, assembly starts – early 2012-May 2013 Receive and prepare vessel – Mar/Apr 2013 Install PMT system after TPC placed in vessel – Apr/May 2013 Vessel vendor seals endcap – May 2013 Before sealing, require sign-off from L2 managers that their subsystems are complete and ready to be sealed in vessel Prepare for transport to LADTF – May/June August 10-11, 2011CD-2 Review of the MicroBooNE Project
Schedule Overview (Installation) When enclosure (LADTF) is ready, occupy and install vessel promptly – June 2013 Vessel insulation contract – Some time in 2013 Installation of cryo system – Around the World in 80 Days. No, wait… it’s 40 days. Installation of electronics – Back to the Future Final check out. – Once Upon a Time in America. 21August 10-11, 2011CD-2 Review of the MicroBooNE Project
Schedule Drivers Delivery of detector components TPC parts Cold electronics Vessel fabrication and delivery to FNAL Experiment hall (LADTF) ready for occupancy Detectors installed and vessel sealed Other concerns D0 assembly building available (not currently driving the schedule, but could definitely affect things…) 22August 10-11, 2011CD-2 Review of the MicroBooNE Project
Extra Slides 23August 10-11, 2011CD-2 Review of the MicroBooNE Project
Contingency The MicroBooNE contingency plan has guidelines. A contingency was developed for each task based on these rules. 24August 10-11, 2011CD-2 Review of the MicroBooNE Project
Where Are We Now? D0 assembly building not yet ready for occupancy 25August 10-11, 2011CD-2 Review of the MicroBooNE Project
Assembly Floorplan 26August 10-11, 2011CD-2 Review of the MicroBooNE Project