Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Progress and Plan for Superconducting RF Cavity RF Group.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
Special Report NuMI Target Updates Special Report NuMI Target Updates Ongoing Work - Four Parallel Activities I.Target Hall We expect to move NT-05 to.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
RF Cavity / Coupling Coil Module
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
1 UK PM Report Costs & Schedule Alan Grant, STFC.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Electrical & Control Power Supplies Trevor Hartnett.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Spectrometer Solenoid Prep Work at RAL and LBNL Steve Virostek Lawrence Berkeley National Lab Steve Virostek Lawrence Berkeley National Lab MICE VC May.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
ELENA installation progress F. Butin / ELENA collaboration.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
Chris Booth Sheffield 29th March 2006
Resource Loaded Schedule and Budget Profile
Completion of the MICE-US construction project
Francois and Lau EATM 17 July 2012
Electrical & Control.
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
MICE CM31 Schedule summary
Spectrometer Solenoid Fabrication Status and Schedule
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March run, 50% probability DS power supply repair FuG power supply with manufacturer. Agreed repair plan with DL/ Steve Griffiths/Trevor Hartnett DL have specified and purchased/arranged for supply of mechanical contactor to FuG. FuG to repair damage and integrate contactor at their cost. Return RAL end Feb - DL to commission at Ral upon return. Solenoids will be aligned during Jan shut down. Requires axial-offset bellows – design in hand – out for quote. Exploring parallel solution Cost incurred this year.

H2 system 2 leaks –H2 insulating vacuum to environment. –H2 system to insulating vacuum. FCU now extracted from beam line, still cold. Plan testing in Hall days depending on availability of move. Move FCU to R9 and FCD to Hall, week beginning 11 th or18 th Jan. H2 end cap and bellows assemblies now removed. No strong evidence of significant cold touch H2 compressors to move to R9. No additional H2 end cap available. Only one H2 spare window- substitute ‘thick’ window on FCU Need vacuum end caps for FCU testing.

Demonstration of Ionisation Cooling MAP directors review suggests no magnet before 2018 Planning still in early stages so dates not firm. Project has been re-planned based on these dates MICE Demonstration of Ionisation Cooling construction complete early Data complete end 2018/Jan Cost to Completion review moved to late April/ early May SS magnet now defines critical path. Cavity delivery unchanged. Cavity couplers test at FNAL Jan – coupler not yet leak tight Cavity assembly Jan/Feb in Berkeley. Cavities to RAL May/June 16? RF power supply plan as yet unchanged, RF delivered to RAL Sept ’16 – 2016 running will change this. Developing plan for offline test and clean room provision. Mechanical design, parts for PRY (underfloor) nearly ready to go for bid Good progress on floor plates, nearly ready to got to fabrication. Central absorber design near complete. PRY drawing sign off – final stages.