Detector Gas Systems Status Update Ferdi Hahn PH-DT1-GS 3 rd Detector Steering Meeting on Gas Systems June 2005.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

Xe leak status C. Garabatos. Leak story The maximum allowable leak rate corresponds to a loss of 10% of the total volume in one year – 0.3 l/h for the.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
Analysis Modules F. Hahn. Goal of todays Meeting Inform about current status and layouts of the analysis modules. (the focus will be on common modules)
ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1.
04/02/ FH Plans for 2005 PH-DT1-GS. 04/02/ FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea.
DT1 Gas Section Debrief of 2005 activities.. The Purpose of the Debrief  Compare plan and achievements.  Analyze how the work is done ? Do we meet the.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
The Construction of the LHC Detector Gas Systems ? Ferdi Hahn PH-TA1-GS Detector Steering Meeting 4th of June 2004.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
19/02/2014A. D'Auria CERN/PH-DT-DI Maintenance ID flushing system:  Maintenance 2 dryers  Installation 2 flow meters  Maintenance of several hygrometers.
The RPC Closed loop Gas System Slides from Bianco and Guida.
ALICE-TRD gas system 1/4/2015R. Guida PH-DT-DI1. TRD gas system Few numbers:  Total number of modules/racks: 20 (max leak rate certified at construction.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Cable Layouts, Connectors for the LHC GAS SYSTEMS GAS COORDINATION MEETING, OCTOBER 2005 PH / DT1 GS.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Detector Gas Systems Status Update Ferdi Hahn PH-TA1-GS Detector Steering Meeting November 2004.
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI New recuperation system for n-Pentane:  Installation of the module in parallel of the first.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Totem Gas Systems ( T1, T2 ) F. Hahn and S. Haider PH / DT1.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
TRD Gas System Layouts Production Readiness Review 03 – Nov F. Hahn.
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
WP2 (Detector development) Summary Gabriella Pugliese INFN – Politecnico of Bari.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
SWE Day-ahead market coupling (Pre- and Post-Coupling project) Lisbon, 3rd December th Implementation Group meeting.
Update on the Critical Path of the PS Booster Schedule for the EYETS
Gas Schedules
Francois and Lau EATM 17 July 2012
CSP 25th November 2010 Technical agreement number 3: overview
Update on the SVD construction
East Hall under construction
Gas system Commissioning procedures and status
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Gas System Commissioning
CMS gas systems meeting
LHC Experimental Vacuum Systems Status October ‘07
SMB Service Status 112th ACCU Meeting
4th FRC meeting, Antti Onnela, CERN-PH-DT
Progress with Experimental Vacuum Chambers
MICE Project in the US: Completion of Efforts
Current Status Future Progress Monitoring
Francesco Forti University and INFN, Pisa
SKADS Controller’s Meeting Timeline Annual Financial Report
LCLS-II Cryoplant Controls Workshop.
XRN4361 – UK Link Release 2 - Delivery
Preliminary Project Execution Plan
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
SNS-PPU upgrades the existing accelerator structure
XRN Nov 19 Release - Status Update
CSC Electronics Installation and Commissioning CSCE I&C
Presentation transcript:

Detector Gas Systems Status Update Ferdi Hahn PH-DT1-GS 3 rd Detector Steering Meeting on Gas Systems June 2005

Content  Work Package Status –Updates –New Work package for TOTEM  Cost and Manpower Situation –Material Cost Balance –Manpower Balance  Progress since last Steering (Nov. 2004)  Gas System Status + Operation in 2007 (per Experiment) –What can be guaranteed ? –What not ?  Schedule and Progress Monitoring  Conclusions

Work Package Updates  Changes since last Steering (Nov. 2004): –WP for ATLAS ID flushing systems approved in Dec –LHCb WP updated and approved in April 2005 –WP’s ATLAS addendum RPC Humidifier (ready for approval) –WP ALICE updated (ready for approval)  New Work Package Proposal : –WP’s TOTEM gas systems All in all additional 2.3 m-y of work. Additional 6 m-m of work (50% < 2007) Included in new Schedule To be decided!

TOTEM Work Package TOTEM has two small detector systems with gas (GEM and CSC). Proposal for TOTEM gas systems –Mixer staged until > 1 st year of operation; –Run with Pre-mixed in 1 st. Year. –Single Pass Distribution : Two (standard) Distribution Racks to be build (1 per endcap) incorporating CSC and GEM distribution -> (common control system) ( To be decided ) Squeeze Distribution construction into this years program. Consequences: Our Proposal: 6 m-m for construction and installation (50% <end of 2005)

Cost and Manpower Situation

Material Cost

ALICE Material Cost 65% of budget spent

ATLAS Material Cost 60 % of budget spent

CMS Material Cost 62% of budget spent

LHCb Material Cost 34% of budget spent

Manpower Cost

Current Manpower Situation  Currently: 10 Staff, 1 PJAS, 6 FSU + 5 Protvino + Students. –Altogether: 22 – 24 people. –Strong team with high experience and good technical skills.  Staff reinforcement from last year (+3/-2) now fully effective. –real acceleration in the work

Full Manpower Balance (type B) 37 % of budget spent All in man-years 46% 49% 28% 15% 37% % Done

Work Evolution over the last 6 months Work load has increased by 2.3 m-y since Nov The remaining work has decreased by only 2.1 m-y in 6 months. All in man-years We cannot accept further work without jeopardizing the current schedule. work increase

Conclusion on Budget  Gas System construction is on budget  Work Balance: –37% of total work is done. –Total remaining work: 25.8 m-y –Remaining work until 2007 (reduced program) ~ 15 m-y  Construction Work: –For ATLAS and CMS ~2/3 of construction done. –For ALICE and LHCb ~1/3 of construction done.  Installation: –Just starting Total work = Construction + Installation of all work units. Note: See also under Schedule

Progress since Nov. 2004

Progress Construction  Mixer Racks nearly finished + tested ( except for TGC and MDT). (4-5 months delay.) –Shipping to experiments is on-going.  Pump racks will be finished in July; functional tests in August than delivery to experiments. (on Schedule).  ATLAS distribution good progress: (85% finished) (on-schedule) –MDT and RPC racks finished, tests are on-going –TGC and TRT will be finished July. –CSC racks will be done together with ALICE racks in autumn.

Progress Installation  ALICE TPC installation at P2 is ongoing (TPC SXL2) ( 4 months delay bco. extra pipe-work between Plug and SXL2 (done by TS/LEA))  ALICE SG: all Mixers and 4 Skeleton Control racks (without control chassis) are delivered; ready for connection (ahead of schedule)  A lot preparation work on all 4 sites. Enormous progress on installation planning for all four experiments.

Testing Commissioning  Rack testing in the lab. (Stefan) –Leak testing –Functional tests  All test results are put immediately into MTF database (Mar). –MTF database comprises the entire gas systems, will be used later for service and maintenance.

Conclusions on Achievements during last 6 months  Construction is going at full capacity, and we maintain (or in some points shorten) the schedule presented 6 months ago. –All individual items are on schedules except Mixer modules (4-5months delay) –Maintain all deliveries to experiments.  Installation planning: –Planning / key dates established with all experiments. –Cable plans + power requirements were given to all four experiments.

Status / Problems Prospective for 2007 Per Experiment

Gas System Operation for 2007  What can be guaranteed : –We will assure that all 21 LHC gas systems are operating, so that the detectors will be able to take data during the 2007 physics run.  What not: –Gas Analysis items which are included in the WP’s will require manual operation in the beginning. –Some (closed loop) systems may run in Open Mode –Not all Purifiers can be ready. We will provide manual Purifiers where needed. –Membranes (on the critical path). –ALICE TRD not all distribution racks are needed in In general

ALICE  Installation work at P2: –TPC system installation is ongoing (4 months behind schedule). Lot of hiccups and surprises during installation work. Commissioning of full system in August –Mixer and control rack installation in SG is ongoing (finished this summer). –New gas coordinator Antonello Di Mauro very active and present, that helps a lot.  Attention Areas: –TRD distribution on critical path. –TRD Purifier module are on the critical path. Status

ALICE in 2007  TPC (ready, you know…) –Modifications later when TPC moved into UX-Cavern.  Single Pass Systems –Commissioning in August  TOF, TRD commissioning in April –TOF Purifier: temporary installation (cartridges for off-line regeneration) –TRD Purifier on critical path. –TRD Distribution may be done only partly (4/6 racks are not required for 2007).  Some analysis units are delayed, manual use of analyzers will be possible.

ATLAS  ATLAS Distribution units (Muon+TRT (except (CSC)) completed by end of July Other modules (for SG and USA) are also finished or well advanced.  We will start installation work very soon (two persons permanently at P1 from October onwards).  Pilot-Commission ATLAS RPC gas system in Spring 2006 (closed loop).  While installing for the RPC’s system, we try to finish a maximum for all other systems. –Good support from ATLAS  Attention areas: –Membrane module for TRT detector is on the critical path. (see Schedule) Status

ATLAS in 2007  RPC –Gas system ready in Spring –Purifier: temporary installation (cartridges for off-line regeneration)  TGC –Installation complete by Summer –Commissioning early –Dryer: temporary installation (cartridges for off-line regeneration) CSC  MDT –Installation complete (without Purifier) by Summer –Commissioning early (without Purifier)  TRT –Installation complete end 2006 –Purifier: temporary installation (cartridges for off-line regeneration) –Membrane module on critical path. –Xe recuperation module staged to after 1 st year of LHC (foreseen in WP).  Analysis units are delayed, manual use of analyzers will be possible.

CMS  Distribution systems installed in surface building, CSC group is making valuable tests with channel flowmeters; RPC group starting now with similar tests.  Surface racks (Mixer, Pump, Exhaust Modules) are being build now or there are ready today. –After testing the racks will be shipped to P5. –Real installation work will start only after March  Attention areas: –Pre-distribution units (in US area) are very big, and we would like to deliver these racks by April 2006, so that they can be connected by “Cryotec”. We have advanced our schedule by 4 months, but these racks are on a critical path. Status

CMS in 2007  CSC, –System complete (without gas recovery). CF4 Recovery will be re-evaluated after 1 year of running (foreseen in WP) –Commissioning in Oct  DT –System complete (except for analysis in USC). –Commissioning in Nov  RPC –Purifier: temporary installation (cartridges for off-line regeneration) –Commissioning in Dec  Analysis units are delayed, manual use of analyzers will be possible.

LHCb  Distribution units for Muons, GEM, OT and RICH will be done in autumn  Standard racks for SG and UX-A are on-going or included in schedule.  Although there have been a number of design changes during the last months; LHCb has been treated a bit poorly. We will try to correct over the next 6 months.  Attention areas: –RICH Membrane and Purifier modules on critical path. Status

LHCb in 2007  Muon+GEM: –All modules ready except purifier. –System will run in single path mode in  OT: –All modules ready except purifier. –System will run in single path mode in  RICH 1 –Basic closed loop modules will be installed end of –Purifier: temporary installation (cartridges for off-line regeneration) –Membranes on the critical path –Compression unit done by LHCb (foreseen in WP). –System Commissioning in April  RICH2 –Basic closed loop modules will be installed end of –Purifier on critical path. –Membranes on the critical path –Compression unit done by LHCb (foreseen in WP). –System Commissioning in April 2007.

Schedule (1) Construction

Construction Schedule (compare to Nov. 2004) maintain Delayed + 5 months maintain Shorten -3 months maintain Add TRD Distribution in WU Swap +6 months Swap -6 months maintain New Shifted – 9months

Comments to the Construction Schedule  We need nearly 4 m-y for construction until the end of 2005 in order to maintain the current plan (very challenging !)  TOTEM is not yet included, squeeze in +3 m-m for distribution racks.  Possible Short-Cuts: –TRD distribution make only 2/6 racks (only a fraction of the detector will be installed) –Purifier: make only 2 more (TRD and RICH 2)

Targets for next 6 Months (1) 1.Finnish all distribution units until end 0f Start Pre-Distribution by October 2005, so that we have chance to finish CMS part before April Deliver all gas racks + control chassis for: Mixer, Exhaust and Pump Modules to experimental sites. Construction and Setting up of Modules

Schedule (2) Installation + Commissioning

Installation  Mar has established work plan for the installation in the four experiments.  This plan needs to account for numerous constrains: –Availability of gas system modules –Requirements of individual detectors –Infrastructure and work conditions on the sites. –Limited resources to work on more than 1 site at a time.  Installation work is already on-going, but real increase as of September this year.

Targets for next 12 months (2)  ALICE: (Summer 2005) –Finnish TPC Installation –Connect Mixers in ALICE, install control racks in SG  ATLAS: (Sept. 05 to April 06) –Install in SG (60-80%) –Install in US (60-80%) –Deliver all racks in UX (Pipe connections done by ATLAS and TS) –Install auxiliaries (valve islands, valve controllers, back-up systems, etc.) –Start commissioning of RPC system in April 2006  As of Beginning of 2006, increase manpower further and start working in CMS and LHCb. Installation on Experimental Sites Everything that is needed for 2007.

Proposal Installation Planning (1) ATLAS: UX racks in time in 2005 Main Commiss. in 2007 CMS : UX racks are done Do SG/USC in 2006 RPC Pilot Closed Loop Commissioning

Proposal Installation Planning (2) ALICE: TPC in commis. Aug Single Pass Syst.’s Aug TRD, TOF in 2007 LHCb: Distribution: RICH’s end 2005 Muon and OT early 2006 TRD

Conclusion on the Schedule (1)  The Schedule is very tight, and does not include contingency.  Construction work: –Total Remaining work accounts for 180 m-m, for 2007 we need to do ~ 80 m-m. (50% in 2005, 50% in 2006).  Installation work: –Plan exists (very detailed for next 10 months). –Re-adjustments will be necessary… –Try to meet fixed end dates of Commissioning

Conclusion on the Schedule (2)  Testing and Commissioning: –Huge work in the lab and on site to insure proper functioning of all units. (-> see talk by Stefan)  Commissioning Dates: –ALICE TPC in August 2005 –ATLAS RPC (first multi channel) start in April –Single Pass Commissioning in August –Bulk Commissioning of Closed Loop between Oct. 06 and April 07.

General Conclusions  The gas system construction is on schedule, and on Budget  Though, our plan remains very challenging –We have defined clear targets (for next 6 months and longer term), and we will report every 6 months on the results.  We cannot accept additional work units <2007.  Although, we cannot finish 100% of the gas systems for 2007, we can assure working gas systems for the first physics run in 2007.