© 2014 HDR Architecture, Inc., all rights reserved. © 2014 HDR, Inc., all rights reserved. © 2014 HDR, all rights reserved.

Slides:



Advertisements
Similar presentations
CM/CG Contracting Tom Ravn, Mn/DOT Director, Office of Construction and Innovative Contracting.
Advertisements

Organization of Primary Entities
Design-Build: RISKS OR REWARDS for the Consulting Engineer?
CMGC Contracting at UDOT Program, Projects & Lessons Learned
I-4 Ultimate with Lanes Project Central Florida 1 May 21, 2013.
European Asphalt Pavement Warranties Scan September 14-28, 2002.
Airport Owner’s Guide to Project Delivery Systems Prepared by: The Joint Committee of ACI-NA, ACC and AGC.
1. A project delivery method describes the process of how a project will be designed and constructed. A project delivery method can be characterized in.
6 TH ANNUAL CONFERENCE. Footer Text Date PERFORMANCE-BASED MAINTENANCE APPROACH DB/P3 Edward P. Pensock, Jr. P.E. Strategic Project Division Director.
State Aid Design-Build Project Delivery for Minnesota Cities and Counties.
Alternative Project Delivery
Innovative Contracting Construction Management Association of America Seminar May 17, 2013 California Department of Transportation.
Structure of Project in PPP- (2) John Plumb. Agenda Following on from the Strategy and business case to develop the ideas Structure of PPP arrangements.
Measure L Program Implementation Management Considerations Report to the Board of Trustees San Joaquin Delta Community College District July 13, 2004.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
The United States P3 market has been inconsistent to date, but future growth points to it being one of the largest markets in the world Total Capital.
PROJECT DELIVERY SYSTEMS
Delivery Methods  The Players from Handbook of Architectural Practice, Chapter 9.1 by Phillip Bernstein FAIA  Variables from Handbook of Architectural.
Prof Awad S. Hanna C HANGING P ROJECT D ELIVERY S YSTEMS by Awad S. Hanna, Ph. D., P. E. The University of Wisconsin, Madison Department of Civil and Environmental.
Patrick DeCorla-Souza, P3 Program Manager, FHWA
Determining Innovative Contracting Methods to Reduce User Costs Stuart Thompson Utah Technology Transfer Center.
2005 AASHTO Value Engineering Conference Using VE in Design Build Presented by: Jerry R. Blanding Innovative Contracting Engineer FHWA – NRC July 21, 2005.
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
Procurement and Construction Management and Oversight What Board Members Need to Know Jerry Smiley, AICP 24 July 2013.
Solving Challenges Others Cannot Virginia’s Public Private Partnership Law Toyo University Tokyo, Japan Christopher D. Lloyd September 29, 2008.
Project Delivery Options in the California Construction Market CSI Fresno Chapter - February 16, 2010 PROJECT DELIVERY OPTIONS in the CALIFORNIA CONSTRUCTION.
Legislative Opportunities and Impediments - The Virginia Experience Virginia Public Private Partnerships ATRA TECHNIX Program Phil Bomersheim “Activist”
An Introduction to World Bank Organization and Operations Jean-Charles Crochet Senior Transport Economist World Bank.
Public-Private Partnership Program 2015 Update 2015 American Council of Engineering Companies ACEC – Los Angeles Chapter Luncheon, July 8, 2015.
WVDOH Experience... thus far.  Public-Private Partnerships = PPP=3P = P3 ... Most folks in industry refer to them as P3, so that’s what I go with.
How To Structure a P3.
January 31, …a delivery method in which the construction team is known as the design-builder…and is responsible for taking a concept developed by.
ITS Georgia | June What is the role of ITS in the emerging public/private partnership transportation market in Georgia? ITS Georgia Monso_Julia.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Solving Challenges Others Cannot Statutory Frameworks for Public Private Partnerships NCPPP/AGC Conference Phoenix, AZ Christopher D. Lloyd January 27,
MAKING IT HAPPEN. TRB 88 th Annual Meeting Risk Management in Public-Private Partnerships January 14, 2009 Statutory and Public Policy Approaches to PPP.
Safe & Sound Bridge Improvement Program. Purpose of Meeting Introduction of Team Today’s discussion  History of Safe & Sound  DBFM to MDBB/DB split.
UTILIZING CONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA.
LACCD Building the Future THOMAS HALL Director Facilities Planning and Development.
Greece Public Sector Martin S Hirko, MIRCS: Regional Director, Faithful+Gould November 2015 Restructuring Greece: Project Managing the Challenge.
Alternate Project Delivery Systems for Governments.
The Design/Build Contract. What Is A Design/Build Contract? Contract that combines design & construction into one agreement The design/build team provides.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
Construction Manager/General Contractor Pilot Program Construction Management Association of America February 18, 2016 California Department of Transportation.
CONSTRUCTION MANAGEMENT AT RISK Prepared by: Nancy Fouad Carey Attorney AGC Alabama Birmingham Section Meeting November 5, 2012.
Budget Workshop Capital Improvement Plan Presentation on Public Private Partnership and Strategy for Municipal Complex, HWY 50, and Coast to Coast Trail.
P3s & The P3 Canada Fund Michael Mills VP Investments, PPP Canada
One East Broward Blvd., Suite 1800
Finding the Revenue Stream to Make P3s Work
Using Public-Private Partnerships to Move More People The Story of HOT Lanes in Northern Virginia January 30, 2017 Morteza Farajian, Ph.D.
2016 SAME Small Business Conference - Atlanta
What Small and Emerging Contractors Need to Know Introduction to Project Delivery Methods © Copyright 2017 NASBP.
BOT LAW (R.A. No. 6957, as amended by R.A. No. 7718)
ACEC INDIANA Environmental Business & Funding Source Conference
Changes and Benefits brought from Modern Procurement to Bridge the Infrastructure Gap Remo Bucci, P.Eng Infrastructure and Capital Projects October 27,
PROJECT DELIVERY METHODS
Virginia’s Public Private Partnership Law
CHANGING PROJECT DELIVERY SYSTEMS
Finance and Risk Public-Private Partnerships
Project Delivery Systems
Virginia’s P3 Program Morteza Farajian, PhD.
Patrick DeCorla-Souza, USDOT Build America Bureau
Critical Transportation Issues
The Oregon Approach to Innovation in Infrastructure
PROJECT DELIVERY METHODS
Design-Build Acquisition and Contract Incentives July 19, 2018
Cost Containment Working Group Board Update
Design-Build Acquisition and Contract Incentives May 9, 2019
Right of Way Certification
Presentation transcript:

© 2014 HDR Architecture, Inc., all rights reserved. © 2014 HDR, Inc., all rights reserved. © 2014 HDR, all rights reserved.

North Dakota League of Cities Alternative Project Delivery September 17, 2016

 Design-Bid-Build (DBB)  Construction Manager / General Contractor (CMGC) (Similar to CM at Risk)  Design-Build (DB)  Design-Build-Operate-Maintain (DBOM)  Design-Finance-Build-Operate-Maintain (DFBOM)  Build-Operate-Transfer (BOT) Delivery Options: Public Works Projects

 Typically led by governmental bodies.  Public sector staff oversees project activities, including planning, engineering and construction. Activities proceed sequentially.  Project development generally contracted to planning and engineering consultants.  Engineering work (PS&E) is completed prior to soliciting construction bids.  Construction procurement follows typical low-bid procedures.  Generally financed by public taxes, fees or grants. Design-Bid-Build

Source: FHWA Every Day Counts Innovation Initiative Comparison of Delivery Methods: DBB

 Involves “alliancing,” a popular project delivery scheme in Australia, UK, etc.  Agency contracts with an engineering firm as designer of record.  Agency selects a construction manager/general contractor (CM/GC) for the project to provide design input and act as owner’s representative.  Agency retains designer and CM/GC, and facilitates a “marriage” for project development.  CM/GC and Agency negotiate guaranteed construction price (GMP) as design is finalized.  CM/GC completes construction Construction Manager / General Contractor

Source: FHWA Every Day Counts Innovation Initiative Comparison of Delivery Methods: CMGC

 Planning and conceptual engineering (15%- 35%) completed by agency/consultants.  Final design and construction carried out by single contractor, with single contract.  Engineering and construction activities proceed in parallel, rather than sequentially.  DB bidding may be “low-bid” or “best- value.”  Transfers interface risk between design and construction from owner/agency to DB contractor. Design-Build

Source: FHWA Every Day Counts Innovation Initiative Comparison of Delivery Methods: DB

 Similar to DB, but contractor is also responsible for operating/maintaining system for specified period in addition to design and construction.  Contractor may hold responsibility for procuring and commissioning rolling stock.  Provides “implied warranty” between system constructor and system operator.  Transfers interface risk between design/ construction and operations/maintenance from agency to contractor. Design-Build-Operate- Maintain

Comparison of Delivery Methods: DBOM

 Similar to DBOM, but contractor arranges and/or provides financing for construction through private capital markets.  Contractor typically repaid through “availability payments” or similar mechanism, guaranteed by owner/agency.  Transfers financing risk from agency to contractor, in addition to design, construction and operation risk. Design-Finance-Build- Operate-Maintain

Comparison of Delivery Methods: DBFOM

 Closest method to complete privatization.  Agency selects contractor (“concessionaire”)  Responsibility for designing, financing, constructing, operating/maintaining system is transferred from agency to concessionaire.  Concessionaire may accept revenue risk in addition to DBOM risks.  Transfers virtually all risks from owner/agency to private sector.  Common delivery method in Europe, Asia, Australia and South America. Build-Operate-Transfer

Comparison of Delivery Methods: BOT

Relationship Between Private Sector Involvement and Risk

Source: Duke Center on Globalization, Governance & Competitiveness, US Bus Rapid Transit Research, July 2012 Comparison of Delivery Methods

South Mountain Freeway Project  Programmed $1.77 billion  Publicly financed  40% federal funding, 60% regional funding  State administered – federally assisted  Design-Build-Maintain o 18-month procurement o 3.5-year construction duration o 30-year maintenance duration Arizona DOT P3 Program Management

South Mountain Freeway Project Adot P3 Program Management

Cost and Schedule Certainty  Open to traffic 3 years faster  $200 million to $300 million under budget  Largest known piece of Regional Transportation Plan Freeway Program  Maricopa Association of Governments (local MPO) able to confidently rebalance program Maintenance  30-year maintenance program makes life-cycle performance a major focus during design and construction  Hand-back provisions provide insurance ADOT will receive a high-quality facility in 30 years P3 Delivery Method Benefits

Sioux Falls, SD I-229 Design-Build Project Limits Complete reconstruction of mainline Added auxilarry lanes between interchanges Project cost: $33 million

Cost and Schedule Certainty  South Dakota had/has enabling legislation in place  Project completed in 24 Months (Contractor award to completion) o Scheduled allowed for 30 months  Typical SDDOT schedule = 8 years for Design/Bid/Build  Used to deliver overall program for interstate system around Sioux Falls o I-29 scheduled for major reconstruction from I- 90 south to 26 th Street (5.5 Miles) o Needed truck detour  Strict Quality Control on design and construction.  3 Teams bid (1 disqualified at time of package review) Design-Build Method Benefits

© 2014 HDR Architecture, Inc., all rights reserved. © 2014 HDR, Inc., all rights reserved. © 2014 HDR, all rights reserved.