E. Hazen - Back-End Report1 AMC13 Status Update ● Version 1 (5Gb/s links, Virtex-6 chip) ● 15 modules built, all but 3 distributed to colleagues.

Slides:



Advertisements
Similar presentations
Uli Schäfer JEM Status and plans Hardware status JEM0 Hardware status JEM1 Plans.
Advertisements

HCAL FIT 2002 HCAL Data Concentrator Status Report Gueorgui Antchev, Eric Hazen, Jim Rohlf, Shouxiang Wu Boston University.
Uli Schäfer 1 JEM1: Status and plans power Jet Sum R S T U VME CC RM ACE CAN Flash TTC JEM1.0 status JEM1.1 Plans.
Global Trigger H. Bergauer, K. Kastner, S. Kostner, A. Nentchev, B. Neuherz, N. Neumeister, M. Padrta, P. Porth, H. Rohringer, H. Sakulin, J. Strauss,
TID and TS J. William Gu Data Acquisition 1.Trigger distribution scheme 2.TID development 3.TID in test setup 4.TS development.
Mircea Bogdan, 5/21/041 Chicago TDC Design and Implementation Mircea Bogdan (UC)
Presentation for the Exception PCB February 25th 2009 John Coughlan Ready in 2013 European X-Ray Free Electron Laser XFEL DESY Laboratory, Hamburg Next.
Bernardo Mota (CERN PH/ED) 17/05/04ALICE TPC Meeting Progress on the RCU Prototyping Bernardo Mota CERN PH/ED Overview Architecture Trigger and Clock Distribution.
DAQ Link integration update A Navarro Tobar*, JM Cela Ruiz 10/2/2015.
DHH Status Igor Konorov TUM, Physics Department, E18 PXD DAQ workshop Münzenberg –June 9-10, 2011.
E. Hazen - DTC1 DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University.
HF ROBOX PRR3 Apr 2003E. Hazen HF Front-End Electronics ● System Description – Overview – PMT Board, ROBOX, Patch Panel – Signal Cable, Front-end boards.
E. Hazen -- Upgrade Meetings1 AMC13 Project Development Status E. Hazen, S.X. Wu - Boston University.
E. Hazen1 MicroTCA for HCAL and CMS Review / Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen -- ACES ACES 2011 MicroTCA in CMS E. Hazen, Boston University for the CMS collaboration.
Eric Hazen1 Ethernet Readout With: E. Kearns, J. Raaf, S.X. Wu, others... Eric Hazen Boston University.
E. Hazen -- CMS Week HCAL Back-End MicroTCA Upgrade Status E. Hazen Boston University.
E. Hazen -- Upgrade Week1 AMC13 Project Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen -- xTCA IG1 AMC13 Project Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen -- Upgrade Week1 HCAL uTCA Readout Plan E. Hazen - Boston University for the CMS HCAL Collaboration.
E. Hazen -- TWEPP MicroTCA Developments in CMS E. Hazen - Boston University for the CMS Collaboration TWEPP 2012 – Oxford.
E. Hazen - Detector Electronics1 Detector Electronics New Developments.
10/28/09E. Hazen FNAL Workshop1 HCAL DAQ / Timing / Controls Module Eric Hazen, Shouxiang Wu Boston University.
E. Hazen1 New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister, Phil Lawson, Jason St John, Shouxiang Wu Boston University.
E. Hazen -- Upgrade Meetings1 AMC13 Project DAQ and TTC Integration For MicroTCA in CMS Status Report E. Hazen - Boston University for the CMS.
E. Hazen -- HCAL Upgrade Workshop1 MicroTCA Common Platform For CMS Working Group E. Hazen - Boston University for the CMS Collaboration.
E. Hazen1 AMC13 Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen1 Fermilab CMS Upgrade Workshop November 19-20, 2008 A summary of off-detector calorimeter TriDAS electronics issues Eric Hazen, Boston.
E. Hazen1 AMC13 Project Status E. Hazen - Boston University for the CMS Collaboration.
T. Gorski, et al., U. Wisconsin, April 28, 2010 SHLC RCT MicroTCA Development - 1 SLHC Cal Trigger Upgrade SLHC Regional Calorimeter Trigger MicroTCA Development.
E. Hazen -- Upgrade Week1 MicroTCA Common Platform For CMS Working Group E. Hazen - Boston University for the CMS Collaboration.
E. Hazen1 New DCC Status and Software issues Eric Hazen, Phil Lawson, Shouxiang Wu, Jim Rohlf, Arno Heister, Jason StJohn Boston University.
E. Hazen - CMS Electronics Week
DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University
26 Sept 2013E. Hazen - TWEPP / AMC13 Module CMS MicroTCA Overview E. Hazen – Boston University Representing the work of J. Rohlf, S.X. Wu, A. Heister,
Counting Room Electronics for the PANDA MVD
DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University
The Data Handling Hybrid
AMC13 Project Status E. Hazen - Boston University
DAQ and TTC Integration For MicroTCA in CMS
HCAL DAQ Path Upgrades Current DCC Status New DCC Hardware Software
TWEPP 2010 – Aachen Development of a MicroTCA Carrier Hub
Status of NA62 straw electronics and services
Status of NA62 straw readout
AMC13 T1 Rev 2 Preliminary Design Review E. Hazen Boston University
The First HCAL Readout Schedule! (7/22/99 UMD meeting)
AMC13 Module CMS MicroTCA Overview E. Hazen – Boston University
E. Hazen - Back-End Report
Current DCC Design LED Board
- PANDA EMC Readout System
ABC130: DAQ Hardware Status Matt Warren et al. Valencia 3 Feb 2014
AMC13 Status Report AMC13 Update.
Production Firmware - status Components TOTFED - status
A New Clock Distribution/Topology Processor Module for KOTO (CDT)
CoBo - Different Boundaries & Different Options of
HCAL Data Concentrator Production Status
COVER Full production should arrive today
MicroTCA Common Platform For CMS Working Group
MicroTCA Common Platform For CMS Working Group
AMC13XG (XG = Ten Gigabit)
ECAL OD Electronic Workshop 7-8/04/2005
xTCA in CMS Magnus Hansen Thanks to many CMS collaborators
DAQ Interface for uTCA E. Hazen - Boston University
New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister,
8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
University of California Los Angeles
The CMS Tracking Readout and Front End Driver Testing
FED Design and EMU-to-DAQ Test
HCAL DAQ Interface Eric Hazen Jim Rohlf Shouxiang Wu Boston University
Presentation transcript:

E. Hazen - Back-End Report1 AMC13 Status Update ● Version 1 (5Gb/s links, Virtex-6 chip) ● 15 modules built, all but 3 distributed to colleagues ● 1 at P5 participating for Slice test ● Version 2 (10Gb/s links, Kintex-7 chip) ● Design ready to send out, expect to send in next days. – Brief delay to study different high-speed base material options for PCB to ensure 10GB operation ● Prototypes expected in mid-January 2 pcs initial for lab testing 15 pcs total to produce (aim: yield > 12)

E. Hazen - Back-End Report2 AMC13 Rev 2 Changes ● Virtex 6 to Kintex 7 for 10G link support ● Two-way GbE switch removed, GbE to Spartan chip only ● (Never used Virtex GbE option) ● SDRAM size increased from 128MB to 512MB speed to 800MHz DDR (1600MT/s * 16 bits) ● Clock source changes: ● Rev 1 used 2x Si570 programmable XO ● Rev 2 uses Si5338B Quad programmable clock generator ● TTC Recovered clock to clock-capable input on Kintex 7 ● Changes to T1-T2 board connector pinout ● Maintain plug compatibility with existing connector ● Add 1 pin for additional 12V to be routed to T3 (plus additional GND) ● There are two diff pairs unused (GPIO pairs) unused for CLK, TTC

E. Hazen - Back-End Report3 Slice Test ● MicroTCA Crate installed with AMC13 and mCTR2 ● Firmware and software in place ● Full DAQ firmware for mCTR2c and AMC13 ● Full xDAQ control and readout software ● Runs taken at P5! ● Bunch structure seen ● LED and laser runs taken and verified ● Parasitic collider run taken and being analyzed – 25 events captured by HLT via normal CDAQ and saved (save 1/2^20 L1A) – 28 events captured by uTCA monitor buffer – EvN, OrN and BcN match (there is a BcN offset...) – Working on matching of QIE data... not as expected, but maybe a software issue. ● Data format very close to VME, so CMSSW analysis chain should work without much trouble on uTCA data uTCA crate at P5 with AMC13 and 6 mCTR2