O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 FAIR ACC planning and schedule O. Kester 6th FAIR - Machine Advisory Committee Meeting

Slides:



Advertisements
Similar presentations
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt EU FP7 FAIR pp - 1st Reporting meeting March 6, 2009 J. Eschke, GSI EU.
Advertisements

Peter Spiller, IHEP, Protvino GSI, Peter Spiller IHEP FAIR in kind Contributions.
FAIR GmbH and FAIR Project History, Status and Outlook
Introduction 1 Proposal for the structure of FAIR GmbH construction phase 2 Relationship between FAIR GmbH and GSI mbH construction phase Contract Site.
The Facility for Antiproton and Ion Research in Europe Günther RosnerNuPECC, Sevilla, 5/10/121.
Helmholtz Centre for Ion Research D. Krämer, 2nd Lab Directors Meeting, Protvino, January 15-16, 2008 Design and Engineering Issues; Standardization and.
Role of Management and Technical Coordination
Progress Report Günther RosnerNuPECC, Copenhagen, 15/6/121.
In-Kind Contribution Management Update Allen Weeks March 20, Lund.
SuperB. SuperB has been approved as the first in a list of 14 “flagship” projects within the new national research plan. The national research plan has.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
HL-LHC FP7 DS Status of the proposal Lucio Rossi - CERN 3rd General Meeting for application preparation – CERN 20 October.
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt CBM Collaboration meeting Status Interim MoU J. Eschke, GSI.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
1 1. Some recent views ( ) 2 Linac tunnel
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Introduction and Status EU Design Study Kick-off meeting April 14-15,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Introduction and Status EU CNI contract Kick-off meeting, December 1-2,
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
1 Future Circular Collider Study Preparatory Collaboration Board Meeting September 2014 R-D Heuer Global Future Circular Collider (FCC) Study Goals and.
Oct. 16, 20081CBM Collaboration Meeting, Dubna, Zbigniew Majka FAIR project status  Establishment of the FAIR GmbH  Accelerator construction  Civil.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
LHC Computing, SPC-FC-CC-C; H F Hoffmann1 CERN/2379/Rev: Proposal for building the LHC computing environment at CERN (Phase 1) Goals of Phase.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Proposal for ESS DTL Roadmap. Divide Into Four Phases 1.Conceptual Design Phase (In progress) 2.Technical Design Phase 3.Prototyping Phase 4.Construction.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
European Spallation Source Overview and Status Technical Advisory Committee 1-2 April 2015 James H. Yeck ESS CEO & Director General
SuperB project. The origin: infn roadmap 2006 early motivations – e+ e- after Dafne at LNF – SuperB’s synergy with ILC damping rings.
O. Kester, 8 th MAC meeting, Darmstadt, Towards a resource loaded schedule Status of project planning and procurement O. Kester 8.
O. Kester, NuSTAR annual meeting, 27/02/2013
Contents: -GSI organization structures -Tasks of GSI (accelerator) -Status of evaluations / technical developments -Overview -Note : (only) accelerator.
Delivery of FAIR In-kind items (feedback from India) Subhasis Chattopadhyay VECC-Kolkata & BI-Kolkata.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
MAC meeting (12-13 January 2010) Machine Advisory Committee participants: B.Sharkov (ITEP/FAIR) P.Belochitskii (CERN) S.Ivanov (IHEP, Protvino) M.Steck.
Progress Report Günther RosnerNuSTAR Annual Meeting, Darmstadt, 29/2/121.
Common Systems – Holger Kollmus Holger Kollmus FAIR - Machine Advisory Committee Meeting Common Systems and Controls.
GSI Helmholtzzentrum für Schwerionenforschung GmbH MAC12 – O. Kester November 2014 GSI Helmholtzzentrum für Schwerionenforschung GmbH.
Peter Spiller, November 2012, Structure and Tasks of the Project Division Primary Beams Peter Spiller Machine Advisory Committee Meeting.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Status of FAIR D. Krämer Dec. 1&2, 2010 – 4th MAC Meeting 1.
CBM Timeline Walter F.J. Müller, FAIR, Darmstadt
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
WP High Beta Cavities Delivery
Preparation Phase of the FAIR Project
High energy beam transport.
Oleksiy Dolinskyy December 1st, 2014
Status of HESR 18th March Gießen Dieter Prasuhn.
Systems Analysis and Design in a Changing World, 4th Edition
CSP 25th November 2010 Technical agreement number 3: overview
(Selected) Project Management Processes at the XFEL
(Procurement, testing of magnets)
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
Communication and Documentation Needs exemplified on WP 71
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
Bunker Internal Review Welcome & Charge
Elettra – Sincrotrone Trieste S.C.p.A.
NSS integrated installation plan workshop Introduction
DOE Review of the LCLS Project October 2006
Preliminary Project Execution Plan
Executive Project Kickoff
SNS-PPU upgrades the existing accelerator structure
East Hall under construction
LHC Computing, RRB; H F Hoffmann
Presentation transcript:

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 FAIR ACC planning and schedule O. Kester 6th FAIR - Machine Advisory Committee Meeting

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Outline 1. FAIR ACC project structure 2. FAIR ACC scheduling 3. Resource and procurement strategy planning 4. Request for funding (Projektmittelantrag – PMA) 5. Requests concerning civil construction and radiation safety 2

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 FAIR ACC project management 3 O. Kester Project leader, chair AAB U. Weinrich (head) P. Karampougiouki, G. Aberin-Wolters (assistance) P. Busch ( Data and document management) G. Hickler (Engineering, procurement) C. Omet (Synchrotrons, support technical coordination) N.N. (component data base) W. Jacoby (scheduling, inkind contracts) Technical follow up team FAIR ACC project management group (ACC PO): FAIR ACC project lead AAB Project House Common Systems HESRS-FRSpBar-Sep P-linac HEBT CR H. Kollmus D. Prasuhn SIS 100 F. Hagenbuck L. GroeningK. KnieM. SteckM. Winkler P.Spiller Subprojects U. Weinrich Deputy FAIR project leader board (EXP, S&B,ACC,PMO) Head in kind coordinator W. Jacoby (acting) Head technical follow up co-chair AAB P. Spiller technical coordinator PMO

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 WBS of the subproject FAIR ACC

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 The scheduling process  Establishment of coordinated bottom up schedule started in AAB OB meeting on the 18th of May 2011  Joint coordination by W.Jacoby und U.Weinrich  SMART process  Specific: Down to 4th level => about 400 detailed schedules Until first beam delivery to experiments  Measurable: about 20 activities per detailed schedule  Ambitious: attempt to reach politically communicated goals  Realistic: attempt to get commitment from work package leaders  Terminated: per definition

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 The scheduling process continued  Stepwise approach: Completeness Quality within accelerator part Quality between different accelerators parts and building  Machine project leaders (MPLs) are responsible for the schedule of their machine project (boundary conditions)  Optimistic schedule planning  not resources limited  Use of MS Project server

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/ BOE of the different buildings BOE Facility  Beneficial occupation estimate is the starting point for assembly and installation  Components need to be ready to meet these dates

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Detailed status of scheduling process Accelerator (sub project) StructureQuantity Quality (MP internal) Quality (external) HEBTdefinedcompleteIn workNot yet started Super-FRSdefinedcompleteIn workNot yet started CRdefinedcompleteIn workNot yet started P-LinacdefinedcompleteIn workNot yet started SIS100definedcompleteIn workNot yet started HESRdefinedcompleteIn workNot yet started Pbar-separatordefinedcompleteIn workNot yet started Common SystemsdefinedIn workNot yet started

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Results from the bottom up schedule  Identification of critical paths Examples will be given in the talks of the MPLs  Procurement strategy with the schedule as base:  Identification of long lead items of each MP (magnets, cavities, beam diagnostics)  Determination of packaging of components concerning procurement  Identification of in-kind providers  Parameter list and functional description will be used to establish detailed specs together with partners  Further determination of the funding profile from the procurement plan 9

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Resource planning FAIR ACC  In-kind contributions Germany  PMA GSI and FZJ (cost book values escalated) International partners (according to cost book values)  Cash contributions to FAIR ACC (only international partners)  Manpower (FTEs deduced from the schedule):  Project management team (recruitment in progress)  Additional personnel for technical departments and groups (Document concerning strategically recruitment in preparation)  Collaboration with large scale facilities: Helmholtz centers (KIT, FZJ), CERN, IMP Lanzhou, DOE labs  Resource planning is supported by the managing adminstrative director of GSI – P. Hassenbach 10

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Request for funding to the BMBF (Projektmittelantrag – PMA)  PMA BuE has been submitted (June 2011) Covers the German contribution to the accelerators and the experiments (project fund from the BMBF and Hessen)  German in-kind contributions provided via GSI  PMA HESR has been approved (BMBF and FZJ)  GSI applied for Pre-financing for SIS100-dipole, SC magnet test bench and the CR-debuncher  accepted and start of early procurement  Details will be provided by U. Weinrich  status in-kind contributions 11

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 PMA and inkind contracts 12  Workpackage descriptions for all WPs have been delivered to the BMBF in September  Preliminary schedule has to be provided  Required for funding approval Final IKC of CR-Debuncher completed  Template for IKC of SIS100 dipole series New proposals cover controls (common systems), p-Linac components and magnet testing (common systems)

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Status of S&B planning activities 08 / 1109 / 1110 / 1111 / 11 completion of Lph (cost calculation) application for site roads and tree clearing (05.07) building application execution planning (Lph 5)

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Requests from FAIR S&B and SiST 14  Collision check has been completed  4 cases have to be investigated in detail  Room specific data (until October 20th)  Cable data for cable routing and cable trays (until October 14th)  Component data (position, media etc. – November 1 st )  Fine tuning of infrastructure requirements (end of November)  Support for establishing the radiation safety documents from the MPLs

O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 Summary 15  Project structure FAIR ACC established  FAIR ACC bottom up schedule now in the review phase  Recruitment and resource planning isin progress  Request for funding (Projektmittelantrag, PMA)  Early tendering process for CR de-buncher and SIS100 dipole series started  Data to be delivered to FAIR S&B and SiST