Spectrometer Solenoid Recovery: Options for Moving Forward Mark Palmer BNL April 5, 2016.

Slides:



Advertisements
Similar presentations
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
National Aeronautics and Space Administration ANSI/EIA-748-B Earned Value Management Systems (EVMS) 32 Guidelines ANSI/EIA-748-B Earned Value.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 The Genoa Tracker Solenoids and their Contribution toward a New Design Michael A. Green Lawrence Berkeley National Laboratory and Pasquale Fabbricatore.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
ANSI/EIA -748 EVMS 32 Guidelines National Aeronautics and Space Administration.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
RF Cavity / Coupling Coil Module
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
The U.S. Muon Accelerator Program Mark Palmer Fermilab MICE Collaboration Meeting 32 STFC-RAL February 8, 2012.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
Some Thoughts on Magnetic Measurements for MICE Michael A. Green Lawrence Berkeley Laboratory Berkeley CA 94720, USA.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
MICE RF Coupling Coil Magnets Update Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory October 6, 2010 Sofia, Bulgaria.
MICE Funding Update (U.S.) Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory CMPB Meeting August 1, 2007.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 5, 2016.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
Rob Connatser NSS Instrument Work Packages and XLPM.
1 MICE Coupling Coil Cryostating and Test Steve Gourlay March 1, Office of Science.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Spectrometer Solenoid Recovery: Options for Moving Forward Mark Palmer Fermilab October 26, 2015.
MICE Spectrometer Solenoids Step IV running
Closing Session Report
Comments on the February DOE Review
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Camera PDR/CD1 Planning 19 September 2008
Resource Loaded Schedule and Budget Profile
ANSI/EIA-748-B Earned Value Management Systems (EVMS)
Jim Fast Pacific Northwest National Laboratory
Mike Anerella December 17, 2013
Status of the MICE Construction Project
Project Management W. J. Foyt
Systems Analysis and Design in a Changing World, 4th Edition
Spectrometer Solenoid Recovery: Options for Moving Forward
Systems Implementation,
MQXF Planning Paolo Fessia, Frederic Savary, Ezio Todesco, Lucio Rossi - CERN Mike Anerella, Peter Wanderer - BNL Giorgio Ambrosio, Mark Kaducak - FNAL.
Spectrometer Solenoid Update
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
Spectrometer Solenoid Fabrication Status and Schedule
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Systems Analysis and Design
Presentation transcript:

Spectrometer Solenoid Recovery: Options for Moving Forward Mark Palmer BNL April 5, 2016

Outline Recap of December 2015 Review –Plan Assumptions –Review Overview –Preliminary Cost Estimate –Revised Risk Assessment –Key Recommendations Updated Plan for US-based Procurement –Planning Process –Cost Assessment –Options Peter Wanderer –Updated Engineering Effort –Engineering Package for a Make-Buy Decision April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)2

RECAP OF DECEMBER REVIEW April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)3

Plan Assumptions Critical assumptions: –US-based fabrication/procurement process –December schedule based on “in-house” (i.e., laboratory-based) repair Why? –Only route to expend funds immediately and hence shorten overall schedule –US Vendor procurement requires having all funds on hand to begin bid process »Final portion of US reserve not in hand until start of US FY17 Plan consistent with SSD being in place on the MICE beam line by mid-February 2018 –Can effectively consider this an “earliest possible” date April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)4

Spectrometer Solenoid Recovery Review Overview –Review held December 3-4 at Fermilab –Web-site: –Committee: Herman ten KateCERN(Chair) Jim KerbyANL Mike AnerellaBNL Peter WandererBNL Tom TaylorCERN Cesar LuongoJLAB Peter McIntyreTAMU Luigi MuzziENEA-Frascati –Observers: Bruce StraussDOE Josef BoehmRAL Oleg KiricheckRAL/ISIS April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)5

SS Recovery: Cost Estimate Preliminary cost estimate: $2.175M –Utilizes FNAL labor rates Least expensive US laboratory option Estimates considered closest to external vendor cost range Includes moderate contingency (given that all except one step previously executed) –Key elements: QP system upgrade Design, Fabrication Cold Test (pre-installation) of new cold mass –Goal: pre-train cold mass and show corrected training behavior prior to installation in cryostat –Critical process to minimize project risk Final Assembly of He vessel Disassembly of magnet Re-assembly (integration of new cold mass) Integration of SSD #2 in MICE Cooling Channel April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)6

Revised Risk Assessment Discussions at CM43 and October 2015 MPB looked at various options –But did not actually compare risks associated with the various options on a “level playing field”! Updated risk analysis –Assessed the likelihood of completely losing SSD He space integrity with additional quenches –Conclusion: Any option which re-uses current SSD after Step IV is VERY HIGH RISK!!! We can not certify the M1-M2 He space to vacuum feed-thru for repeated quenches Cooling Demo requires SSD warm-up and re-training, hence we assess the likelihood of magnet survival as being low NOTE: the above feed-thru is inaccessible until the damaged cold mass is removed from the cryostat Only realistic options for completion of MICE Cooling Demo –Build new cold mass Best option for mitigating risk while re-utilizing existing cryostat Closest to fitting within available US budget –Build new magnet Almost certainly exceeds funds available for US procurement –Re-build existing cold mass Recommended for serious consideration at December 2015 SSD Recovery Review As a back-up if problems encountered during fabrication of new cold mass April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)7

Key Recommendations Endorsed Cold Mass Fabrication as most plausible route forward (cost and time) Key Recommendations (my paraphrase): –Complete design and implement quench protection system changes as described at review –Use a vendor for new cold mass (leave open option to accept lab bids) –Increase current margin for E2 –Allow more time/effort for cold mass preparation than shown in December’s preliminary cost and schedule April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)8

UPDATED PLAN FOR US- BASED PROCUREMENT April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)9

Actions – Post Review Committee Report received in January MAP immediately: –Began preparations for an updated procurement package: Initially for Budgetary Quotes Then for Full RFP Process –Updated cost estimate Based on committee recommendations, implemented an adjustment to the fabrication effort (but retained FNAL fabrication rates):  ~$2.5M to complete –Opened initial contacts with vendors European US Japanese –Additional analysis of as-built design to identify required elements of any bid to fabricate (see next slide) April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)10

Process I Leverage BNL Experience w/RHIC e-lens solenoid  use BNL SC Mag. Div. to prepare updated procurement package –Tasks: 1.Evaluate existing models and documentation and prepare an incremental set of documents for vendors 2.Establish metrics for technical evaluation of vendor proposals Carry out 3D modeling of magnetic field to determine our level of flexibility in the design while maintaining the necessary SciFi Tracker field specifications Carry out 3D modeling of mechanical structure to ensure our ability to adequately evaluate vendor proposals 3.Carry out preliminary analysis to execute a US laboratory bid NOTE: such a bid is probably the only route to speeding up the fabrication process (otherwise we will need to accumulate FY17 funds for a full procurement) –Coordination: P. Wanderer, M. Anerella April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)11

Process II Approach: –Preparation of an “As-Built” bid package Use existing LBNL package Update drawing package with as-built information (use models created during 2010 re-build) Update package with “lessons learned”, updated design requirements, and technical evaluation information for vendor bids –Execute final design, procurement and fabrication effort for new QP system Commissioning to start in <1 month Then Step IV operations with SSD and SSU “as-is” April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)12

Technical Evaluations Validate 3D model for ‘as-built’ package –Required to define interface and field-engineering procedures for installation of new cold mass (Plate) –Forms basis to carry out updated 3D mechanical modeling (Witte, Marone) Evaluate coil design to: –Increase current margin (Gupta) –Preserve the field uniformity specification in the tracker volume Provide a technical basis for evaluating any bids –Can we define what “good enough” means? Following presentation by P. Wanderer will summarize the status of the engineering effort –Will emphasize a couple key points in advance April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)13

COST ASSESSMENT AND OPTIONS April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)14

Cost Estimate Based on US procurement requirements Preliminary estimates from some vendors –Preparation of bid package: $116K –Have received some preliminary cold mass fabrication estimates These are ranges and not budgetary quote quality 2 lowest estimates correspond to range ~$ M –Vendor values: $0.5M and $0.65M –Full estimate includes oversight, VAT, overheads and contingency NOTE: overall a large vendor range has been observed ($500K to $2M) –BNL cold mass test estimate: ~$363K –2 lowest estimates consistent with overall ~$2.1M procurement cost Suggests that use of Fermilab fabrication rates was reasonable for estimating vendor bids NOTE: Vendors have regularly indicated preference for full magnet bid April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)15 Exceeds US Reserve See talk by PG

Comments & Conclusion (I) Peter will describe: –Clear paths exist to optimizing current margin HOWEVER, the analysis of the mechanical issues indicates that any reasonable increase in current margin will NOT, by itself, mitigate the anomalous training behavior of these magnets  A more complete engineering solution is required! Our quoted cost –Represents our best estimate of funds that must be set aside to have a reasonable chance of success with a US procurement –Exceeds the available US reserve US-only procurement could only be provided by an earlier-than- planned conclusion of general US support in FY17 (~April 1, 2017) –Further adjustments to the estimate will only be feasible after validated bids are in hand April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)16

Comments & Conclusion (II) Other options may exist –Procurement of magnet could be moved outside of US (with partial or full funds transfer) –Other accounting systems have different rules and rates Different overheads No requirement to fully state EDIA and support costs provided by purchaser More palatable option? –Requires funding agency action April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)17

BACKUPS April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)18

Example of Arriving at a “Fully Wrapped” Cost Estimate Full Magnet Estimate Use ASG magnet estimate as example –Lowest magnet estimate received… April 5, 2016 Mark Palmer | MICE RLS/MPB Review (RAL)19 Contingency assessed as if formal bid.