ECR (SPS Flange Impedance Reduction) Follow up for IWG C. Vollinger 16/08/2016.

Slides:



Advertisements
Similar presentations
Microwave Instability : Importance of impedance model
Advertisements

3.4d- Relationship between 2D and 3D objects CCSS.
2D Representations of 3D ObjectsProjector Resources 2D Representations of 3D Objects Projector Resources.
PCR Status report AESAG, September Supported by:
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
Toward a Multi-State Consensus on Rural Intersection Decision Support: Objectives u Gain understanding of issues involved with national rural intersection.
Shielding of the SPS Vacuum Flanges - Design Studies – Update Jose E. Varela and Jaime Perez 21 May 2015.
Update on wire scanner impedance studies
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
Coursework. Deadline: 20 th December 2013  The marks for Background and analysis lock down on 20 th Dec and are sent to the board. After this date changes.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
News and hot topics Impedance meeting 14/04/2014.
LIU-SPS RF Power upgrade | 09 December 2015.
Proposal: Use of ECRs for “Controls” Changes and Renovations Rende Steerenberg, Samy Chemli, Marine Gourber-Pace, Klaus Hanke, Verena Kain, Bettina Mikulec,
Technology Department MKP status L. Sermeus, L. Ducimetière TCM 18 November 2014.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
LIU-SPS planning – provisional LS1 / LS2 BLM, BPM MKE/MKDV/H aC 1 sextant aC 5 sextants RF 200 MHz LSS3 RF 200 MHz preparation RF 200 MHZ building.
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
Outcome of beam dynamics simulations - Scenarios, requirements and expected gains s LIU-SPS Coordination meeting 26/08/2015 A. Lasheen, E. Shaposhnikova,
Representing 3D Objects in 2DProjector resources Representing 3D Objects in 2D Projector Resources.
0 End of Year Arrangements Training Presentation for Access Practitioners.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
LIU-SPS Project baseline, objectives and reviews for 2016 B.Goddard 20/01/16.
Summary of discussion on isolating flanges E. Shaposhnikova With input from LIU-SPS BD WG (in particular H. Bartosik, F. Caspers and J. Varela), K. Cornelis,
Equations of Circles 1Projector Resources Equations of Circles 1 Projector Resources.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
1 st impedance working group meeting Christine Vollinger, Benoit Salvant Mandate Draft proposal for: Structure Procedures List of members Opening discussion.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Quality assurance for Manufacturing Dressed Cavities for SPS prototype cryomodule C. Parente (HL-LHC Technical Quality Officer) Date:
Sorting Equations of Circles 1
Brief Status SPS Prototype PSB Prototype Installed in LS1
Francois and Lau EATM 17 July 2012
Status and Progress of NSW HUB and Extension
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
Installation of an Instrument on a CERN machine
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Follow-up of new design of vacuum flange shielding
SPS - EYETS 2016/17 Vacuum systems planning
Update on HL-LHC triplet fingers
Teleconference ACS – FREIA 17th October 2017
LIU–PLI report LIU SPS meeting.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
10 MHz amplifier status G. Favia
Status of the BI Work Package in the LIU-PSB frame
Status of Vacuum Flange Shielding/ Comparison of RF-shielding Designs
Diffuser status October 2017
Acknowledgments: LIU-PT members and deputies, H. Bartosik
Update on PS Longitudinal Impedance Model
Overview & baseline of LS2 and roadmap for CRG
The situation for the coated magnets and what we learned in the LS1 installation: M.Taborelli, for TE-VSC.
Parts exchange for HL-LHC AUP Q1&Q3
Continuous Integration and Continuous Delivery ( Dev-Ops ) - Fortunesoft
Impedance working group update
OICA Proposal: Decision on Deployed Testing of DPPS
Team member1 Team member2 Team member3 Team member4 17 September 2009
Sorting Equations of Circles 1
Team member1 Team member2 Team member3 Team member4 Feb. **, 2009
Rubicon Q&A May 9th, 2017.
2D Representations of 3D Objects
Make sure everyone participates.
14 a-Equations of Circles 1
Scheme for Growth Pilot
LAMAS Working Group 6-7 December 2017
Results on RF-Measurements on 3-Convolution HL-LHC fingers
Status of the BI Work Package in the LIU-PSB frame
Update on the SPS Impedance Model
Equipment Maintenance Office Supplies Replenishment
Presentation transcript:

ECR (SPS Flange Impedance Reduction) Follow up for IWG C. Vollinger 16/08/2016

SPS Flange Impedance Reduction Flanges of the SPS with/without adjacent bellows shape cavities in the vacuum interconnects; These flanges are identified as one large source of impedance in the machine; Program of impedance reduction foresees the installation of flange shields and different designs were evaluated in the past. The so-called “double-tube” shield appears to give the best improvement in impedance reduction by reducing the R/Q by a factor of about 20 (with gap-filler included). 16/08/2016Christine Vollinger for IWG2

16/08/2016Christine Vollinger for IWG3

Steps taken after last IWG (#2 meeting) 16/08/2016Christine Vollinger for IWG4 1.Instead of rejecting the ECR, a delay of approval by 2 weeks to give room for further clarification was asked. 2. The decision on whether short-circuited flanges can be deployed everywhere cannot be made yet, so for the present the existing insulation scheme will be replicated. This decision needs to be taken before end 2016.

Strategy agreed with LIU-SPS and VSC 16/08/2016Christine Vollinger for IWG5 1.The agreed strategy for the EYETS is to produce the ~16 shields with the new design proposed in the ECR, while in parallel the impedance validation is made. A ‘yes/no’ answer will come from the impedance team ~2 weeks after the prototype shield is made available to them. If the answer is ‘no’, then the installation will be postponed. 2.As the only reason to go for this fall-back solution was the impossibility of getting production drawings ready in time for EYETS deployment, the final version for the YETS and LS2 can still be based on the more robust design initially proposed and validated as acceptable from impedance. Design work for this should therefore continue.

Tasks and Further Action Required 16/08/2016Christine Vollinger for IWG6 The impedance evaluation of the shield design presented in the ECR still needs to be made by simulation and measurement. RF do not anticipate problems, as it looks very similar to the PPS design in terms of impedance, but need to check that the addition of the insulated gap does not cause any unexpected effects. RF will launch the simulation as soon as the CATIA model is confirmed by VSC. (model available as of 16/08/2016) RF also need to make the measurements on a prototype or first production piece – VSC says this will probably not be available until end October, but will provide a date for the availability.