John Polenz Emerson Network Power Liebert Services
Prior to the test During the test After the test
Just kill the input and let’er run till she drops and see how long it runs!
Do you use IEEE 1188, 450, &1106 as a reference and guide? Do you know what the Battery Manufacturer requirements are?
Most require initial/equalize charge – Really? 72 hour float after equalize and prior to testing Cool down? Dissipation of Gas build up on plates Initial/equalize Timelines for VLA can be extensive 150 hrs vs 24 hrs Ensuring Full state of Charge Construction events Constant current testing vs constant power
System functionality vs Battery capacity More than not with UPS applications Primarily acceptance testing No planning or knowledge of battery manufacturers requirements for capacity testing IOM not reviewed Timeline issues
Test requirements What is the actual sizing of the battery? You mean I have to know the sizing for the battery?
KVA/KW load Inverter efficiencies Power factor Aging factor Temperature Number of cells/string Put the info into the formulas- KVA Rating X Power Factor = KW Load KW Load ÷ Inverter Efficiency = KW Battery Load KW Battery Load ÷ # of Cells = W/Cell requirement This is the “WHY” you want to test as a system!
What prepping? The battery has been on float for a couple of days You discover that the battery has been discharged multiple times due to SAT requirements UPS voltage setting not verified prior to the test UPS End Cell Voltage not verified or known Voltage drop in system Battery and UPS to battery connections
Temperature is not considered as an issue Not prepped as required by the manufacturer Not enough time in schedule Didn’t have the information Didn’t realize the requirements existed Assumed just a 15 minute battery
No data recording Data logging equipment issues Inadequate data collected System data only at the UPS At the beginning and at the end of the test IR testing -Thermal concerns –when do we stop the test? Connection concerns High resistance –high temperatures Battery temperature No parameters established Cell reversal Equipment malfunctions
It didn’t make the time ! The system only ran for 6.5 minutes instead of 8 minutes Battery temperature was found to be 62F Not all the units met the ECV requirement! System vs. individual cell/unit ECV Some units fell below specified ECV Test ran for 15 minutes, but battery was sized for 10 minutes? Not tested at 77F(25C) Temperature was at 62F Didn’t ensure battery was at FSOC
Didn’t perform initial charge Didn’t perform initial charge properly Didn’t provide 72hr float prior to testing No monitoring for the test – only system level monitoring No data to prove or disprove
Metering not calibrated Only using UPS meters to collect system data Time not monitored during the test Not every cell/unit met the ECV cutoff – v/c
Didn’t make time! No final data review No calculations to verify test results Are not familiar with IEEE rate adjusted or time adjusted calculations No one knows actual sizing of the battery Test stopped before it should be Wrong ECV Wrong time No agreement on “stop test” criteria
Lack of prior planning When to stop the test is not known Improper equipment used Wrong size (voltage)load bank Can cause a fire Issues with equipment Out of calibration Doesn't measure properly Doesn’t record good data to be reviewed Doesn’t record the data at all
Test Equipment failures Facility damage Misinterpretation of battery capacity Delays in commissioning Additional costs incurred Expect tests to be run until the battery makes the numbers! Customer dissatisfaction Battery failed
Make no Judgment calls prior to data analysis Alarms customer! Plan the testing Agreement on: Testing parameters Testing procedures Capacity calculations/analysis process Timelines Know the battery parameters Sizing Temperature impact ECV
Collect proper data System level Cell/unit level The more the better! Analyze the data collected IEEE 1188, 450, 1106 Rate adjusted method Consult the battery manufacturer’s if there are questions/concerns