ENGINEERING n MANAGEMENT n ENVIRONMENTAL

Slides:



Advertisements
Similar presentations
CERTIFICATE 4 IN BUILDING BCGBC4004A. 18 week course First 10 weeks in classroom Following 8 in computer room 1.30pm pm (with 15 min break) Assessments.
Advertisements

Best Practices for an Owner Estimating Organization
Construction Cost Estimation Michael Mincic Civil Engineering Technology Department 22 February 2007.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
35 Estimating Building Costs Chapter Permission granted to reproduce for educational use only.© Goodheart-Willcox Co., Inc. Objectives Explain the process.
Assemblies Estimating Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Work Breakdown Structure –Early compilation of significant work items w/ associated cost and schedule considerations –Overview of project –First look.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
1 The Cost Approach An introduction Wayne Foss, MBA, MAI Wayne Foss Appraisals, Inc.
V-Cost Estimation 1.Costs Associated with Constructed Facilities
Types of Drawings University of Palestine Eng. Nagham Ali Hasan
EM15 – Contractors COST MANAGEMENT
Chapter 1 Introduction to Cost Estimates What is an Estimate? An estimate is an evaluation of a future cost. A building cost estimate is an attempt to.
CAPITAL COST ESTIMATES INSTALLED EQUIPMENT COSTS.
Cost Management Week 6-7 Learning Objectives
1 Construction Estimating PART 1 "ACCURACY" - First and foremost, your ability to achieve success at a targeted,
Construction Engineering Management Project Costing
Construction Cost Estimating Class #2: Concept Estimating Prof. Ralph V. Locurcio, PE.
Copyright ©2009 by Pearson Education, Inc. Upper Saddle River, New Jersey All rights reserved. Engineering Economy, Fourteenth Edition By William.
Chapter 8 Pricing Generally. Objectives Upon completion of this chapter, you will be able to: –Describe the general process of pricing a construction.
Landscape Business Concepts
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Specification & Quantities Estimating
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
BSBPMG504A Manage Project Costs 7.1 Estimate Costs Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of developing.
It’s not just a SWAG* * Scientific Wild Ass Guess Developing the Project Estimate.
Unit 18: CADD in Construction Lesson Objective Be able to explain the use of Building Information Modelling in buildings.
CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Allowances, Unit Prices, and Alternates ACT
Measurement and Payment
Costs and Cash Flows Estimation. Engineering Economic Analysis - Seven Steps 1. Recognition and formulation of the problem. 2. Development of the feasible.
1. 2 Cost & Price Analysis Breakout Session # 312 Beverly Arviso, CPA, Fellow, CPCM, CFCM, Arviso, Inc. Melanie Burgess, CPA, CFCM, Burgess Consulting,
DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.
1 Estimating. 2 Cost Management According to the PMBOK ® Guide, Project Cost Management knowledge area includes the processes involved in planning, estimating,
Chapter 3: Cost Estimation Techniques
Introduction to Management Accounting
2016 Alaska Western Workshop Cost Estimating 101
Project Management MGT 30725
Chapter 3: Cost Estimation Techniques
BIM EXECUTION PLANNING PROCESS
Bills of Quantities Introduction to FIDIC - Bills of Quantities -
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Estimating Project Costs
Costing and Project Evaluation
Assembling a Project Budget
Costs and Economics of Construction
(Additional materials)
Estimating the Cost for the Concrete Pad
Estimating the Cost for the Concrete Pad
Chapter 7: Project Cost Management
9/18/2018 Bids CONTRACTING Khamis…..
COST PLANNING AND ESTIMATION
The Cost Approach.
Estimating the Cost for the Concrete Pad
Project Estimating Overview
Estimating Capital Costs
BIM EXECUTION PLANNING PROCESS
Chapter 3: Cost Estimation Techniques
Budgeting: Estimating Costs and Risks
Chapter 3: Cost Estimation Techniques
Estimating the Cost for the Concrete Pad
ARCH 435 PROJECT MANAGEMENT
CTC 475 Review Inflation Inflation rate f is the rate of change in the value of currency (inflation/deflation) Inflation-free rate i represents a gain.
Estimating the Cost for the Concrete Pad
Cost Estimating Best Practices
ESTIMATE TAKE-OFF & RELATED MATH WORKSHOP - Part 2
Chapter 3: Cost Estimation Techniques
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

ENGINEERING n MANAGEMENT n ENVIRONMENTAL COST ESTIMATING APWA COMPLETE STREETS AND TECHNOLOGY CONFERENCE April 19, 2017 Wayne Richardson, PE, LEED AP ENGINEERING n MANAGEMENT n ENVIRONMENTAL

Fun Trivia Big Dig, Boston (ballooned from 2.6 B in 1985 to __?__ in 2005) A: $3.6 B B: $5.2 B C: $8.6 B D: $14.6 B E: $18.2 B

Answer: Big Dig, Boston (ballooned from $2. 6 B in 1985 to $14 Answer: Big Dig, Boston (ballooned from $2.6 B in 1985 to $14.6 B in 2005) Objectives Understanding Cost Estimates Definitions Types/Levels Working Sources Methodology Documentation

Avoiding Cost Overruns Without financial feasibility, there is no Project! Difficulties Cost overruns occur because original estimates are inaccurate Misrepresentation Pressure/Bias toward Underestimating Unrealistic schedules (time value of money) Intangibles and Unforseens (ex. Outreach) Costing is for Accounting, not Engineering Dept. Lack of experience, knowledge in cost management Requires Significant Effort for large complex (Public) projects Pinning Down General and Special Conditions Frequent changes in technology? Not usually a cause of cost difficulties

Key Things to Take Away Begin with End in Mind Use Judgement Be Inclusive Document Item Data Sources Include Assumptions QC PDF your POPCC

Definitions Cost Estimate Project Cost Management Cost Control Soft Costs Direct Costs Indirect Costs Distributable Costs Field Costs Allowance Alternates Prevailing Wage Factored Parametric Cost Index Mark-up

INDIRECT COSTS

Construction Estimating Type Classes Class C – Study Level (Order of Magnitude) Based On: Studies, Alternatives, Investment Types, Program Accuracy: +50% to -30% Contingency: 20 - 50% (Realistically, 20-40%) Class B – Budgetary Level Based On: Plans from 20%-30% Completion Accuracy: +30% to -15% Contingency: 10 - 25% Class A – Engineer’s Estimate Based On: Plans from 30%-100% Completion Accuracy: +15% to -5% Contingency: 5 - 10% Breakdown of labor and materials Change Order Estimates

Quantity Takeoff Prepare Hard copies Verify scale A quantity take-off is a precise count of the material within the project. A detailed quantity take-off is the only accurate method of determining, within a high degree of precision, the project costs. Other methods are mere guesses.

Quantity Takeoff - Prepare CSI Master Format Specification Review of Documents Summarize Cost Elements and Division of Responsibility Outreach to subcontractors and vendors Site Visit and/or Pre-Bid Meeting

Quantity Takeoff - Perform Documents Measure “Take It All Off” Specs as “Shopping list” Itemize Waste

Quantity Takeoff – Things to Look For: Dimensions, Scaling On-Site Storage Work Space and Staging Areas Abnormal Conditions Discrepancies Proprietary, Sole or Limited Source Products Special Labor Provisions Special Equipment Special Commissioning (LEED, BIM, Recycling, Made in USA, “Green”) Extended Warranties Specification Back-Check Completeness, Coordination & Contradictions

Quantity Takeoff - Documentation Things to Document: Specification Section Number and Listing, ie, “Section 12 24 00-Motorized Roller Shades” Item Description or Scope of Work RS Means Line Item Be as Specific as Possible Keep Items Separated Quantity – Mark on Plans and in Estimate Table

Quantity Takeoff - Documentation Things to Document: Sketch-up Unit of Measurement: Each, Square Footage, Cubic Footage, Linear Footage Vendor Quotes (Add Mark-Up of 10% to 25%) Percent Waste Variable Mark-Up

From Quantity Takeoff to Cost Estimate Job Conditions Economic Conditions Hoisting Conditions Contractor Management Experience Labor Availability Subcontractor Availability No matter how accurate the estimators are, each one will determine a different estimate amount because each evaluation will be completed differently. Each estimator may have used different steps for estimating quantities, using different waste factors, and different labor rates.

Cost Estimate - Sources Recent Bids Project Historical Estimates Engineering News Record Richardson Engineering Services, Inc. (Process Plants) Dodge Digest National Construction Estimator RS Means

Current Means & Methods Estimating software such as Timberline Precision, MC2, On-screen take-off, Adobe measuring tools… Microsoft Excel for creating custom cost spreadsheets Cost data books and Web based applications such as RS Means & Saylor Publications Productivity data books such as NECA (for electrical trades) & MCAA (for mechanical trades)

RS Means RS Means publications compiles construction cost data throughout the US & Canada Costs published in the various categories are national average costs and may need to be adjusted for specific locations Costs are organized in the CSI 50 division MasterFormat 2010 system

CSI MasterFormat 2010 system General Requirements Subgroup – Division 1 Facility Construction Subgroup – Divisions 2 – 19 Facility Services Subgroup – Divisions 20 – 29 Site and Infrastructure Subgroup – Divisions 30 – 39 Process Equipment Subgroup – Divisions 40 - 49

Cost Estimate: RS Means Methodology Primary Components Labor + Materials Extend Subs and Vendors General Conditions

Cost Types There are two types of costs found in the RS Means texts: Unit Price – Cost data is divided into the 50 divisions according to the MasterFormat system of classification and numbering Assembly Costs – Cost data is organized per assembly, which is a functional element of construction E.g., Footing including excavation, installation of steel & concrete, waterproofing and backfill

Reference Section This section contains information on: Equipment Rental Costs Crew listings Historical Cost Indexes City Cost Indexes Location Factors Reference Tables Change Orders Square Foot Costs Listing of Abbreviations

Basis for Cost Information The material prices in Means data cost books are “Contractor” prices. They are prices that an average Contractor with an annual sales volume of at least $ 4,000,000.00 and up would pay to his suppliers. While computing estimates, it is important to note the economy of scale factors such as size of Contracting company, small orders, type of materials, etc…

Cost Estimate – Factoring Items Project Size Multiplier Site Constraints City Costs Index Freight and Taxes Inflation or Escalation Factor Contingency Factor Check: Ask yourself, “What’s not included?” Check your work against previous budget estimates, bids for similar work, Owners expectations, etc...

Key Things to Take Away Begin with End in Mind Use Judgement Be Inclusive (what’s not included? Document Item Data Sources Include Assumptions QC PDF your POPCC Estimating is only partially technical science, the rest is artful judgment.