Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016

Slides:



Advertisements
Similar presentations
BakerRisk also has the ability to utilize other software tools to complete a full flare system analysis: ChemCad® Dynamic flare header hydraulics Flare.
Advertisements

Review of Helium Venting Analyses
February 17-18, 2010 R&D ERL Roberto Than R&D ERL Cryogenics Roberto Than February 17-18, 2010 CRYOGENICS.
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
March 14, 2003 MICE Absorber/Coil Integration MICE LH2 Absorber 1.Assembly 2.Safety 3.Staging 4.Instrumentation.
Mucool cryo-design Christine Darve Fermilab/Beams Division/ Cryogenic Department 8/12/02.
SOLENOID LOW POWER COLD TEST
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
ESS Cryogenic Distribution System for the Elliptical Linac CM - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden J. Polinski.
Utilities 14 October 2008 Martin Nordby, Gordon Bowden.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM.
Safety Requirements and Regulations 10/3/20121Safety Requirements & Regulations James Sears.
ERL: G-5/e-Gun Cryogenic & Pressure Safety Committee Review ERL G-5/e-gun Beam Line Vacuum Failure Analysis April 24, 2009.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
R. Than J. Huang P. Orfin T. Tallerico Jan. 19, 2011
LH2 Safety Issues for MICE 1.O2/LH2 separation 2.No Ignition sources near LH2 3.Adequate ventilation 4.Affects: Windows: absorbers and vacuum Primary and.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
The cryogenic system of the HIE-ISOLDE project and its related hazards for persons N. Delruelle on behalf of the TE/CRG group HIE-ISOLDE Safety Review.
Installation of the T600 at Fermilab CSN2, September 22,
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
JLAB Pressure Systems Considerations Ed Daly. Outline Introduction Federal Law - 10CFR851 Compliance JLAB Pressure Systems Program –Complies with 10CFR851,
ESS Cryomodule Status Meeting – Elements of Safety | | Christine Darve Elements of Safety Applicable to the ESS 2013 January, 9 th Christine.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
NML Cryogenic System Arkadiy Klebaner Cryomodule One Commissioning June 3, 2011.
PXIE Cryogenics Concept Arkadiy Klebaner Session 5 / WG1 (CW Linac and PXIE) October 26 th, 2011.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
UITF ODH Assessment UITF Safety Review May 10, 2016.
LCLS-II Cryoplant Overview
CMTF Cryogenics Arkadiy Klebaner May 6, Outline CMTF cryogenic system scope Goals Key functional requirements Conceptual layout Cryoplant Current.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
Overview of the ESS Linac Cryogenic Distribution System
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
LCLS-II Cryogenic Distribution System CDS Surface Components PDR Jerry Makara December 16, 2014.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
Technical Procurement Plan
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
LCLS-II Technical Requirements
Cryoplant Controls Installation
Installation of the T600 at Fermilab
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
Process Requirements and Design Approach
2 K Coldbox Safety and ESH
2K Cold Box FDR Introduction
2K Cold Box PDR Introduction
1.3-GHz Cavity Vacuum Furnace at IB4
2K Cold Box Structure Analysis
Cryoplant Installation Scope
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Overview of Mechanical Design
Leak Detection Tutorial Work
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Testing/Commissioning of 2 K Cold Box
SC1R Cold Box PDR Mechanical Design
2K Cold Box Process Design
2K Cold Box Mechanical Design
Pressure Piping Analysis
Mathew C. Wright January 26, 2009
ILC Experimental Hall Cryogenics An Overview
ESS elliptical cryomodule
Charge 2. Equipment Protection 3. Definition and Documentation
Overarching Commissioning Plan
HAZOP Guidewords Base Set
Operator Training Requirements
SNS Cryoplant Commissioning Past Experiences
CryoPlant Commissioning
LERF Readiness Review Ed Daly / Matt Marchlik
Presentation transcript:

Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016 Safety and ESH Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016

Outline 2K coldbox and interfaces Pressure safety Design pressure Pressure relief in the 2K coldbox Pressure relief at the interfaces Other safety issues What-if analysis Summary LCLS-II 2 K Cold Box PDR, Sept 27, 2016

2 K Cold Box Components 5 CC + 1 CC with motors and magnetic bearing Process piping Bayonets Flow straightener Vacuum Jacket With manhole Vacuum pumps Relief devices Control valves MLI Instruments LCLS-II 2 K Cold Box PDR, Sept 27, 2016

2 K ColdboxInterfaces LHe dewar To 4.5K CBX U-tube Clean up return From Interface Box Vacuum Break Instrument Air Cooling water 3 atm He Guard Vac.

Design pressure requirement Component Normal operating Design Pressure Pressure Temperature Vacuum jacket ~ 0 bara ~ 300 K External 1 bara Internal 0.2 barg Discharge piping to 4.5 K coldbox 1.2 bara ~ 27 K 6.2 bara Suction piping and CCs piping 0.027 bara 3.4 – 27 K 4.1 bara LHe dewar vapor return piping 1.25 bara 4.5 K 3 atm Helium supply 4 bara 300 K 11.2 bara LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Pressure rating of components 3-1/8” bayonets (LHe dewar 4.5K Vapor return) 12.4 bara [1] 5-3/16” Bayonets (30K discharge U-tube) 6.2 bara [1] 9-1/4” female bayonets (on Interface Box) 5.1 bara [1] CC motor cartridge 47 bara [2] CC wheel housing 4.1 bara [2] Cryogenic valves > 10 bara [1] LCLSII-4.8-EN-0791-R0, Jlab bayonet gate valves [2] LCLS-II cold compressor technical proposal, ALAT LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Operating Temperature Interfaces No. Interface Connection Operating pressure Operating Temperature 1 30 K discharge to 4.5K CBX 5-3/16” bayonet ~ 1.2 bara 25-30 K 2 3.5K suction line 10” internal pipe weld connection ~ 27 mbara ~3.5 K 3 4.5K vapor from LHe dewar 3-1/8” bayonet ~ 4.5 K 4 Cleanup return 1/2“ internal pipe weld 300 K 5 RT He supply 1” pipe 4 bara 6 Guard vacuum Weld < 10 Torr 7 Instrument air ~ 7 bara 8 Cooling water 1” pipe weld ~ 5 bara ~ 300K LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Utilities 1. Cooling water (For CC and Diffusion Pump) Pressure drop: <1bar Pressure head of water pump at SLAC: ~ 70 psi 2. Vacuum guard (For CC and bayonets) Vacuum will be used for the sealing intercept instead of helium. Helium guard is provided as an option. Relief plate set pressure: 1.2 bara 3. Instrument air For 6 pneumatic control valves Required pressure of 7 bara Safety valve set pressure: 11.2 bara LCLS-II 2 K Cold Box PDR, Sept 27, 2016

The reliefs are designed to: Safety Relief System The reliefs are designed to: Ensure safety in all modes (normal, failure, partial maintenance, etc.) Adequately relief system for all types of failures Prevent contamination during normal operations Reseal to maintain system integrity, minimize helium loss Vent outdoors for process piping Safety valve in guard vacuum LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Sub-atmospheric pressure Line B U-tube Safety relief setting 2 K Coldbox: Safety valves are installed at suction and discharge U-tube Vacuum Break CM process lines are protected at DB (FNAL): Safety valve relief at 2 bara Burst disk relief at 4 bara LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Subatmospheric System Relief Name Cryomodules & CDS (FNAL Scope) 2K CBX suction 2K CBX discharge Operating pressure 31 mbar ( normal operation) 1.2 bara (Cooldown) 27 mbara ( normal operation) <= 1.2 bara (Cooldown) 1.2 bara Safety Relief Pressure 2 bara (at RT) 4 bara (at LT) 4.1 bara 6.2 bara Location DB 2 K CBX 2 K VBX Type Spring loaded valve Burst disk ASME, guard vac. enclosure ASME, guard vac. enclosure Vents to Outdoors LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Preserve inventory in the event of total power failure Blowdown “Low pressure” relief for long term power outage. Preserve inventory in the event of total power failure LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Safety valves Primary relief valve requirements RV41712: static heat in-leak cavities at 4.5 K liquid RV41722: Thermal expansion in the case of loss of vacuum in 2K CBX RV41175/RV41200/RV41500:Thermal expansion in the case of loss of vacuum in 2K CBX RV41000: Vacuum Jacket protection Standards: ASME B31.3-2014 “Process Piping” ASME BPVC Section VIII Div. 1 – 2015 “Rules for construction of Pressure Vessels” API 520 – Part I 2014, “ Sizing, Selection, and Installation of Pressure Relieving Devices on Refineries, Part I-Sizing and Selection” CGA S-1.3-2008 “Pressure Relief Device Standards” LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Oxygen Deficiency Hazard (ODH) Fluid: Helium colorless, odorless, tasteless, non-toxic, inert Helium volume: Normal operation: < 10 Liter LHe (equivalent) Cooldown: < 100 liter LHe (equivalent) (~ 15000 liters in CMs.) ODH in the coldbox room has been analyzed and reviewed. SLAC ES&H Program Manager Concurrence. ODH class of Cryo building: class I Warning Signs Installed Oxygen Monitor Ventilation Training for personnel LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Electrical Electricity 480 VAC +/-24V 3 phase – 60Hz +/-1Hz, 13 kW/16 kVA for each CC motor. The electrical components will follow the following standards: IEC 60204-1: 2005 / A1:2008, Safety of machinery – Electrical equipment of machines IEC 61000-6-2: 2005 , Electromagnetic compatibility (EMC) – Part6: Generic standards – IEC 61000-6-4: 2006 / A1: 2011 Electromagnetic compatibility (EMC) – Part6: Generic standards IEC 61010-1 Safety requirements for electrical equipment for measurement, control, and laboratory use LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Noise The expected noise generated by the cold compressors will be lower than 85 dB when measured from 1 m distance from equipment [1]. The National Institute for Occupational Safety and Health (NIOSH) Allows all worker exposures to noise no more than 85 dBA for eight hours to minimize occupational noise induced hearing loss. The standards for occupational noise exposure adopted by the DOE State that personnel without hearing protection must not be exposed to an intensity of noise exceeding 85 dBA. [1] LCLS-II cold compressor technical proposal, ALAT LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Cold burn, etc Cold burn: Lowest temperature: 3.5 K The cryogenic pipes and equipment are vacuum insulated. Fall protection Height: 12.5 feet A platform will be built around the 2 K coldbox for maintenance. Confined space: A manhole on the side and a ventilation hole on the top provided for installing upgrade/downgrade piping spools inside. Any maintenance inside 2 K CBX jacket will be planed, reviewed and approved according to ESH manual Chapter 6. Seismic: to be completed LCLSII-4.8-EN-0227 “LCLS-II Engineering Note on Cryogenic Plant Seismic Design Criteria” LCLS-II 2 K Cold Box PDR, Sept 27, 2016

What-if analysis What-if analysis for the 2 K CBX has been performed and an EN was drafted.

Summary The related ES&H aspects are identified and addressed in the 2 K cold box design. Integrated pressure safety relief is designed in the 2 K cold box, cryoplant and CDS. What-if analysis was performed for the 2 K coldbox. LCLS-II 2 K Cold Box PDR, Sept 27, 2016

Thank you!