Status of the ILCTA_MDB Horizontal Test Stand

Slides:



Advertisements
Similar presentations
ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Advertisements

Superconducting Spoke Resonator Cavities and Cryomodules
Progress and Plan for Superconducting RF Cavity RF Group.
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
Capture Cavity 2 Update Tim Koeth April 3 rd Testing at 4.5K.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
ESS cavities interfaces
S1G Experiment Schedule Plan H. Hayano. Assembly work after cavity arrived Assumption: cavity with VT, with pickup antena, with Ar or N2 filled,
SRF Cryomodule 2 Cavity Test Results Andy Hocker TD/SRF Dev Dept. All Experimenters Meeting, 10-OCT-2011.
F Status and Plans for SRF Facility Sergei Nagaitsev May 18, 2007.
The ILCTA_MDB Horizontal Test Stand for SRF Cavities Andy Hocker FNAL-TD AEM, 25-JUN-2007.
TESLA MEETING May 2003 Frascati LINAC TECHNOLOGY WORKING GROUP Working Group Linac techology introduction Cryomodule design and Assy. Tuner issue.
Lutz Lilje DESY -MPY- Module Issues XFEL Linac Review R. Lange/L. Lilje Ongoing Tests Module Designs Future tests.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
STF status Mar.22,2005 H. Hayano, KEK. STF Phase 1 Test Accelerator DC gun : 200kV CsTe photocathode for quick start UV(262nm) Laser (337ns spacing, 2820bunches)
S.Noguchi (KEK) ILC08 Chicago , Nov . 17, Cavity Package Test in STF STF Phase-1 E. Kako, S. Noguchi, H. Hayano, T. Shishido, M. Sato, K. Watanabe,
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Nikolay SolyakILC-GDE, Beijing, Feb.4-8, Fermilab 3 rd Harmonic Cryomodule Status N.Solyak, H. Edwards, D.Mitchell, M.Foley, T.Khabiboulline, E.Harms,
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
3.9 GHz Cryomodule Shipment to DESY E.Harms on behalf of the Third Harmonic Effort Team (AD & TD, with help from PPD, FESS, BS)
ILC FAST TUNER R&D PROGRAM at FNAL Status Report CC2 Piezo Test Preliminary Results Ruben Carcagno (on behalf of the FNAL FAST TUNER Working Group) 4/5/06.
Horizontal Test Stands and CC2 Results Andy Hocker Testing an alternative ILC cavity design at USPAS (Q 0 =2.23E+02)
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
E. KAKO (KEK) 2009' Oct. 26 ILC KEK Global Design Effort 1 Cavity Preparation for S1-Global Eiji Kako (KEK, Japan)
Definition of Work Area H. Hayano, KEK EDR-KOM-cavity at DESY Issues of Cavity and Cavity Package, Work Package discussion.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Detail plan of S1-Global H. Hayano (KEK),
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
NML/RFCA002 Status ILC Cryomodule meeting 3 July 2012 E. Harms.
CM2 Repair Status 8/13/2012 Tug Arkan 1. Latest Status After the warm end couplers were disassembled, it was decided to disassemble all the lower aluminum.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Page 1 CRYOMODULE 650 (TESLA Style) Stand Alone Tom Peterson and Yuriy Orlov Collaboration Meeting 25 Jan 2011.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
Gradient Degradation Experience at Fermilab (NML/CM-1) Elvin Harms TTC Meeting, Beijing 5-8 December 2011.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
Shuichi NoguchiTTC Meeting at Milano, Injector Cryomodule for cERL at KEK Cavity 2 Prototypes were tested. Input Coupler 2 Couplers were tested.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Cavities, Cryomodules, and Cryogenics Working Group 2 Summary Report Mark Champion, Sang-ho Kim Project X Collaboration Meeting April 12-14, 2011.
Cavity Dressing and CM2 Assembly Mini-Reviews Report (a. k. a
Cryomdoule Test Stand.
S1G Experiment Schedule Plan
Cryomodule test stand at ESS site
Status and plans for the 3.9 GHz section of XFEL
WP5 Elliptical cavities
FNAL recent coupler troubles
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
S1-G Webex meeting Global Design Effort
Jiyuan Zhai ( IHEP ) TTC Meeting, JLAB, 6 Nov 2012
Infrastructure and Test Facilities in the U.S.
IHEP Cryomodule Status
IHEP ILC Cavity Status Jiyuan Zhai (IHEP)
Cryomodule Assembly Plan
Cryomodule ESS FAT & SAT SRF meetinG on 07/11/2017
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Status of the ILCTA_MDB Horizontal Test Stand Andy Hocker FNAL-TD ILC R&D Meeting, 23-MAY-2007

Horizontal Testing --- Context Surface Processing Cavity Fabrication Vertical Testing Ti Vessel Welding Horizontal Testing Cold String Assembly Pass! Fail! A. Hocker, 23-MAY-2007 ILC R&D Meeting

Components of a HTS Shielding cave (X rays from cavity) RF power Klystron/modulator/charging supply for high pulsed RF power Waveguide for RF delivery to coupler LLRF: control of forward power via feedback loop Cryogenics Keep cavity in superfluid He at 1.8 K Horizontal test cryostat (HTC) Insulating vacuum vessel with easy access Ports for vacuum, coupler, instrumentation Vacuum Insulating vacuum for cryostat, clean vacuum for cavity Diagnostics X ray detectors, Faraday cups (cavity dark current), etc. A. Hocker, 23-MAY-2007 ILC R&D Meeting

What you can do with HTS ILC R&D Meeting Piezo OFF Measure Q0 vs Eacc Piezo ON Study Lorentz force detuning Compensation (CC2 result!) better handling (N2 cabinet and caps) etc… Learn about coupler handling A. Hocker, 23-MAY-2007 ILC R&D Meeting

HTS Organization A. Hocker, 23-MAY-2007 ILC R&D Meeting

Cryostat (HTC) installation First few months of its life at MP9 Mods, prep work, leak checks, etc. Moved to cave in MDB in Jan 2007 Began interface to cryo distribution feed can …which led to more mods, repairs, etc. Eventually ready for cooldown by mid-February A. Hocker, 23-MAY-2007 ILC R&D Meeting

What we cooled down ILC R&D Meeting He pumping line He return “cavity” Jeff He supply A. Hocker, 23-MAY-2007 ILC R&D Meeting

Cryo commissioning experience First problem was getting the HTC to pump down Bad seal between HTC and feed can Kludged for commissioning, repaired afterward Cooled to 80K, introduced He to circuit Leak inside HTC, too small to pinpoint while warm, made wholesale seal replacement Reached 1.8 K on 14-MAR-2007 Impact on CC2 cryo was minimal Found a few problem thermometers Some uncertainty on 5 K shield temperature Lots more thermometry added to diagnose A. Hocker, 23-MAY-2007 ILC R&D Meeting

In parallel: C22 DESY sent us 3 junky (~20 MV/m) TESLA cavities (in He vessels) to play with (2 for CAF-MP9, 1 for HTS) Input couplers too C22 is 1996 vintage He return pipe in “wrong” position (actually no pipe at all) Support lugs different No HOM feedthrus Sat around open to air for years Sent to TJNL for HPR and vertical test Achieved 17 MV/m A. Hocker, 23-MAY-2007 ILC R&D Meeting

C22 prep work (“dressing”) Welded a Ti-to-SST transition elbow to C22 vessel for He return pipe Tried here, but eventually done elsewhere CAF-MP9 clean room work Installation of HTS end flange (burst disc, pump-out port w/ VAT valve) Installation of input coupler “cold part” Pumped down Installation of slow tuner (Saclay lever type) and fast tuner (piezo actuator) Installation of magnetic shielding (CC1) A. Hocker, 23-MAY-2007 ILC R&D Meeting

CAF-MP9 clean room photos C22 as arrived from TJNL Installation of burst disc/pump-out flange Installation of coupler “cold part” Done, pumping down A. Hocker, 23-MAY-2007 ILC R&D Meeting

Transporting C22 (MP9 → MDB) HTS installation cart Shipping fixture HTS cavity support “feet” Rotate 90° and unbolt fixturing Crane over to HTS cart A. Hocker, 23-MAY-2007 ILC R&D Meeting

C22 at MDB Temporary install to pressure test helium vessel (~2 lbs differential) Slow tuner (Saclay lever type) Fast tuner (piezo actuator) Fully dressed and ready to install A. Hocker, 23-MAY-2007 ILC R&D Meeting

Vibration instrumentation Geophones installed to measure longitudinal and transverse vibration of cavity and supports Want to learn about response at cold temperatures Proposed package for first NML cryomodule CC2 experience: vibes are an important diagnostic! HTS serves for both cryomodule production and R&D A. Hocker, 23-MAY-2007 ILC R&D Meeting

As of today Cavity installed Internal instrumentation checkout Coupler warm part installation Planning Doing! A. Hocker, 23-MAY-2007 ILC R&D Meeting

Next steps Close up cryostat and pump down (start tomorrow if all goes well) Begin cooldown next week In parallel, finish up RF system Warm back up and begin testing program WG switch charging supply 300 kW klystron modulator A. Hocker, 23-MAY-2007 ILC R&D Meeting

HTS test cycle/C22 plan Install cavity in HTC Warm, off-resonance coupler conditioning (high pulsed power processing) Cooldown to 1.8 K On-resonance conditioning of coupler/cavity Map out Q0 vs Eacc curve Test new widgets, algorithms, etc. Warmup Remove cavity CC2 experience + re-using CC2 systems = smooth commissioning A. Hocker, 23-MAY-2007 ILC R&D Meeting

Post-commissioning plans If time permits, uninstall/reinstall C22 to check reproducibility Fix what we need to fix Open for business First “real” test: Third-harmonic accelerating cavity for DESY’s FLASH Install 3.9 GHz klystron (in operation at A0) and waveguide Interleave 3.9 GHz (at least six) and 1.3 GHz testing as cavity production schedule allows Got a gadget or an idea you want to test in something very like a cryomodule? Come talk to me! A. Hocker, 23-MAY-2007 ILC R&D Meeting

USPAS in Houston, TX, January 2007 (Q0 = 2x102) Conclusions HTS commissioning about to begin! I’ll start a pool for C22’s max gradient in HTS In any event, it should do better than this one: USPAS in Houston, TX, January 2007 (Q0 = 2x102) A. Hocker, 23-MAY-2007 ILC R&D Meeting

Many thanks to… Elvin Harms, Helen Edwards, Ron Kellett, Ryan Montiel, Wade Muranyi, Allan Rowe, Rocky, John Reid, Tom Kubicki, Dan Olis, Brian DeGraff, Roger, Jay Theilacker, Arkadiy Klebaner, Rick Bossert, Bill Soyars, Christine Darve, Liujin Pei, Greg Johnson, Alex Martinez, Peter Prieto, Bob Dysert, Marv Olson, Dennis Nicklaus, Ron Rechenmacher, Margaret Votava, Mike Kucera, Brian Chase, Leon Beverley, Glenn Federwitz, Dan Wolff, Mike Andrews, Mayling Wong, Valeriy Poloubotko, Clark Reid, Tom Peterson, Tug Arkan, Brian Smith, Marco Battistoni, Timer Khabiboulline, Jeff Elliott, Fred Lewis, Paul Dubiel, Ruben Carcagno, Yuriy Pischalnikov, Mike McGee… A. Hocker, 23-MAY-2007 ILC R&D Meeting