NCSX Vacuum Vessel Fabrication

Slides:



Advertisements
Similar presentations
Bulk Molding Compounds, Inc.
Advertisements

Vacuum Vessel Production Readiness Review
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Chapter 27: Workholding Devices for Machine Tools
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Status of the 201 MHz Cavity and Coupling Coil Module Steve Virostek Lawrence Berkeley National Laboratory MICE Video Conference March 10, 2004.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Update of the ARIES-CS Power Core Configuration and Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
Hutch Neilson NCSX Project Manager Princeton Plasma Physics Laboratory Oak Ridge National Laboratory NCSX Research Forum #1 Princeton Plasma Physics Laboratory.
ARIES Review, PPPL L. M. Waganer, 4-5 Oct 2006 Summary of Low Cost Fabrication of Integrated Coil Structure L. M. Waganer With Support from Kevin Slattery.
Status of the Power Core Configuration Based on Modular Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
ORT-E A turn-key Engineering Based Manufacturer and systems integrator. Oak Ridge Tool Engineering, Inc. Oak Ridge Tool Engineering, Inc. Engineering Systems.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Construction of Wendelstein 7-X Max-Planck-Institut für Plasmaphysik
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
SFOBB East Span Seismic Safety Project Steve Margaris, Specifications Engineer, Caltrans.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
“Building Quality to Customer Satisfaction!”. TOTAL QUALITY MACHINING, INC.
1 Dimensional Control for the National Compact Stellarator Experiment R. Ellis, A. Brooks, T. Brown, W. Reiersen, S. Raftopoulos, B. Stratton Presented.
1 NCSX Modular coil winding pack To shim or not to shim? NCSX WBS 1 Engineering Meeting July 7, 2004 What is requirement? What is baseline winding pack.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) – Stage 3 1.Make sure the requirements for the tooling is well defined.
Presented by Brad Nelson Tom Brown, Mike Cole, Paul Fogarty, Paul Goranson, Phil Heitzenroeder, Wayne Reiersen, Dave Williamson, and others NCSX PAC Meeting.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
NCSX Metrology. Goals –Need to accurately make measure measurements for several NCSX systems Modular coil –As-built measurements of coil form –Conductor,
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
Dmitry Gudkov BE-RF-PM CLIC Module Working Group Engineering design of the adjustable supporting system for DBQ.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
NCSX NCSX Trim Coil Peer Review 11/6/07 1 Tom Brown Art Brooks Raki Ramakrishnan Mike Kalish NCSX Trim Coil Peer Review.
NCSX NCSX Vacuum Vessel R&D, Risk Management and Manufacture NCSX Preliminary Design Review October 7-9, 2003 Princeton, NJ Mike Viola, Phil Heitzenroeder,
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
NCSX November 18-20, 2003NCSX Performance Baseline ReviewMichael Viola 1 NCSX Vacuum Vessel R&D, Risk Management and Manufacture Mike Viola, Phil Heitzenroeder,
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
DRAFT Cost and schedule, staffing, metrology utilization 10 AM October 12, 2006 Mike Viola Field Period Assembly Manager.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Preparations for working on Station 1 November 22, 2005.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
8/15/2007Mike Viola1 NCSX Field Period Assembly + + = August 15, 2007 Mike Viola Field Period Assembly Manager.
12/19/2006Mike Viola1 December Lehman Review December 19, 2006 Mike Viola Field Period Assembly Manager NCSX Field Period Assembly + + =
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
QXF magnet integration Paolo Ferracin Joint LARP/CM20 HiLumi meeting Napa Valley, CA, USA 8-10 April, 2013.
NCSX Major Procurement Status July 20, Steady Progress on C1 and C2 The C1 was transferred to the 5 axis machine last Saturday; finish machining.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Full Anode Insert Pressure Cycle Simulation Device
Manufacturing of the first FCC-hh beam screen prototype for ANKA
Design of Distribution Feedbox at LHC P7
On the accuracy of port assembly at Wendelstein 7-X
© 2004 – 2011 PAVAC Industries Inc. All rights reserved
Fixtures, Jigs, and Check Gauges
Stellarator Program Update: Status of NCSX & QPS
Presentation transcript:

NCSX Vacuum Vessel Fabrication 21st IEEE/NPSS Symposium on Fusion Engineering (SOFE 2005) MFE Engineering, NCSX and EAST Oral III.e – Sequoyah 3 4:00 PM Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel 3, D. McCorkle 3 1 Princeton Plasma Physics Laboratory, PO Box 451, Princeton NJ 08543 USA 2 Oak Ridge National Laboratory, Oak Ridge, TN 37831-6169 USA 3 Major Tool and Machine, Inc., Indianapolis, IN 46218, USA 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Introduction The National Compact Stellarator Experiment (NCSX) is being constructed at the Princeton Plasma Physics Laboratory (PPPL) in conjunction with the Oak Ridge National Laboratory (ORNL). A key element of this device is its highly shaped 3/8” thick Inconel- 625 vacuum vessel. The vessel is being fabricated by Major Tool and Machine, Inc. (MTM) in three identical 120º vessel segments, corresponding to the three NCSX field periods, in order to accommodate assembly of the device at PPPL. The vessel must have a total leak rate less than 5  10-6 t-l/s, magnetic permeability less than 1.02μ, and its contours must be within 0.188” (4.76 mm). The VVSA’s are scheduled for completion in January 2006. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Stellarator Symmetry Six identical 60° segments form the NCSX vacuum vessel. 120º vessel segments are formed by welding two 60º segments together. Each 60º segment is fabricated by welding ten press-formed panels together over a collapsible welding fixture which is needed to precisely position the panels. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Process Summary Ten Kirksite die sets (20 total – upper and lower) cast and machined Ten Panels formed per 60° segment Press – anneal – press – local rework Upper and Lower 5 panel sets joined on a fixture to form 60° ½ segments Each 60º upper and lower ½ segments welded together over a collapsible welding fixture. Two 60º segments welded together on a fixture to form 120º segments. Port holes bored and ports installed Leak checked and thermal cycled Ports cut off and shipped. Reassembled at PPPL after Modular Coils installed. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Prototype Vacuum Vessel (PVVS) Prototype vacuum vessel Solicit interest develop techniques Statement of Work defined manufacturing development activities for the 120º Vacuum Vessel Sub-Assembly (VVSA) and production of a full-scale 20º prototype vacuum vessel segment (PVVS). These activities were also meant to give the fabricator the experience needed to develop and submit a firm fixed price and schedule proposal for producing the three VVSA units. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Prototype Vacuum Vessel (PVVS) Two companies were chosen that submitted competitive solutions with the most promising technique. Both companies produced prototype vacuum vessels and Major Tool and Machine, Inc. was chosen for the production of the VVSA based on performance. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Panel Segmentation Ten panel segmentation scheme was chosen for each 60° segment for optimization of complexity of forming vs. weld distortion. 60 panels (6 sets of 10) are required for the entire NCSX vacuum vessel. 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Panel Forming A set of ten kirksite dies were cast and machined Press – anneal – press – local rework Gauges facilitate rework Rubber and wood carefully placed to make minor corrections Each panel is a work of art 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication The 60° fixture is ingeniously designed with many features Allows for the mounting of the ten panels in two 5-panel sections upper and lower. Keyed and segmented to allow for easy disassembly after the 60° segment is welded. Provides stiffness necessary to hold shape and control distortion of the segments during welding. Bolted together as one assembly or as two individual upper and lower assemblies. Cutouts allow a person to stand and weld within the fixture as well as allow for seams to be made which cross the fixture plates. 60° fixture 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication 60° Fixture Panels are tacked together in a three panel and a two panel configuration on the upper or lower fixture. Partial assemblies are then joined into one complete upper or lower five panel segment. Upper assembly Lower assembly 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Metrology measurements taken with a Laser Tracker CMM 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication 60° Segments Upper and lower segments are mounted back onto the complete 60° fixture and welded into their final configuration. This completes the formation of a 60° segment. Completed 60° segments 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication 120° Fixture The 120° fixture also has some unique features serving multiple needs.  Positions and joins two 60° degree vessel segments together: datum reference monuments, strategically placed adjusting rods, personnel access for completing weld. It is designed to uniformly support the highly shaped vessel surfaces (minimizing gravity induced distortion)  a separate center support structure provide support and rigidity for machining the port holes provide support during the installation of the port extensions and vacuum testing operations. 120° fixture 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication 120° Fixture The 120° fixture allows two 60° segments to be aligned and a best fit analysis is performed using Verisurf© software. Alignment and distortion control are critical. The final weld joins two 60° segments to form one completed 120° shell. The port holes are bored on a 5-axis mill. Completed 120° Segment Boring Port Holes 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Final Steps The port extensions are welded on, leak checked, cut off within 1” of the vessel surface (provides stiffness as well as a weld stub) at MTM and then reattached at PPPL, to accommodate assembly of the close-fitting modular coils that surround the vessel. The vessel is joined at assembly by welding custom machined 8” (20.3 cm) wide spacer “spool pieces.” Port 2 Port 6 Port 15 Port 7 Port 11 Port 5 Port NBI Port 16 Port 10 Port 4 Port 8 Port 9 Port 18 Port 17 Port 12 Port 3 - 9/28/2005 9/28/05

NCSX Vacuum Vessel Fabrication Acknowledgment Thank You Sketches and photographs provided by Major Tool and Machine Inc. This research is supported by the U.S. DOE under contract DE-AC02-76CH03073 with Princeton University and contract DE-AC05-00OR22725 with UT-Battelle, LLC. 9/28/2005 9/28/05